Addendum 3 24-5000 OPM.pdf
PDF 110 KB Posted
- Solicitation number
- 24-5000
- Issued by
- Worcester County, Ocean Grove CDP, Massachusetts
About this file
Addendum No. 3 for RFQ 24-5000 is a document issued by the Town of Westborough, Massachusetts, detailing key information for the OPM Services for the Regional Emergency Communication Center (RECC) project. The addendum provides responses to 11 specific questions about the project, including details about staffing, building renovation, funding, and project scope. The project involves renovating a building to serve as a new emergency communication center, with an initial staffing plan of 4-5 people per shift and potential expansion capability for additional communities.
The project is funded through a state grant, with $4.7 million already awarded and an additional $8 million expected in the near future. A study by the Collins Center for the State 911 Awarding Authority has been completed, and a radio study has been conducted, with Westborough Tower designated for the new call center. The project has no fixed MBE/WBE requirements but encourages participation from minority and women-owned businesses. Preferred vendors include Motorola through Cyber Comm, and Green Mountain for tower studies. The design will be prepared to accommodate potential future expansion of communities and staff, with a building committee likely to be convened soon.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ 24-5000 OPM RECC CENTER Feb 8.pdf | ||
| Addendum 1 24-5000 OPM.pdf | ||
| LEGAL NOTICE RFP 24-5000 RECC CTR .pdf | ||
| Addendum 2 24-5000 OPM.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum No. 3
RFQ 24-5000
OPM Services for RECC 2/22/2024
Q1. Is there a Budget for this project and how much?
Ans: We have been awarded a Grant for $4.7million dollars and an additional $8 million will be granted in the near future.
Q2. Was a study done for this Building?
Ans: Yes, the Collins center did a study on this building for the State 911 Awarding Authority.
Q3. How many people will be housed in the renovated building per shift?
Ans: 4-5 people per shift. If more communities sign on later, than more people will be working during each shift.
Q4. Any Push back from the Residents/Neighbors on Phillips St?
Ans: No Residents are very eager to see the building improvements and it be functional. It’s a State Grant so no pushback from Residents either.
Q5. Any Radio Study done so far?
Ans: Yes, a complete Radio study was done. Westborough Tower will be used for the new RECC call center.
Q6. Any preferred vendor list for the project?
Ans: Motorola through Cyber Comm. We use Green Mountain for Tower Studies
Q7. Any MBE/WBE requirements for the Bids/Contracts?
Ans: No fixed percentage requirements but we do encourage the use MBE/WBE companies to bid on the work or be utilized for sub-contracting work.
Q8. Any other locations being considered for this project?
Ans: No other locations will be considered for this project at this point.
Q9. Will the Grant amount change if another community joins?
Ans: No one will be added until the project is completed and so the Grant amount will not change.
Q10: Will the Design be done to accommodate more communities/staff?
Ans: Yes, it will be designed with that in mind.
Q11. Is there a Building Committee for this project?
Ans: A Building Committee will likely be convened soon.
Prepared by:
Shab Khan, Chief Procurement Officer, Westborough Chief Patrick Purcell, Westborough Fire Chief