Addendum 2~2.pdf

PDF 32 KB Posted

Attached to
RFQ - Sinker Creek Bridge Micropile Installation
Solicitation number
S-C25102-00013210
Issued by
Marion County, Oregon

About this file

This document is Addendum #2 to a Request for Quotes (RFQ) issued by Marion County, Oregon for the Sinker Creek Bridge Micropile Installation project, designated as solicitation PW1659-25. The addendum, issued on 4/7/2025, establishes a mandatory completion date for all work items no later than June 30, 2025, and formally becomes part of the original Request for Quotes.

The addendum provides a critical update to the project timeline, specifying the final date by which all project work must be completed. No additional details about pricing, set-asides, or funding sources are included in this specific document. The addendum reinforces the procedural requirements for prospective offerors and ensures all parties are aware of the established project completion deadline.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PW1659-25 - RFQ - Sinker Creek Bridge Micropile Installation Page 1 of 1

ADDENDUM #2

TO THE

REQUEST FOR QUOTES

PW1659-25 - RFQ - SINKER CREEK BRIDGE MICROPILE INSTALLATION

ISSUED ON 4/7/2025 8:00:00 AM

The following information in this addendum, hereby become part of the Request For Quotes. It is essential that all prospective Offerors note the content of this Addendum.

A. Completion Date:

Complete all work items included in this RFQ no later than June 30, 2025.