This document is Addendum #1 to a Request for Quotes (RFQ) issued by Marion County, Oregon for the Sinker Creek Bridge Micropile Installation project (PW1659-25). The addendum, dated 4/7/2025, provides clarifications and revisions to the original solicitation, including a revised plan set and responses to four key contractor questions. The questions address bridge load capacity, tree removal responsibilities, reinforcement bar sizing, and micropile foundation design alternatives. Specifically, the county clarified that the existing bridge should not be used for access, a 2.5-mile detour is available, the county will handle tree removal, the reinforcement bar size is #14 (revised from #13), and alternative micropile casing sizes may be considered if structurally viable.
The addendum does not introduce new pricing terms, set-asides, or funding details. It focuses on technical clarifications to ensure potential bidders have accurate information for preparing their quotes. The document indicates the quote covers only micropile installation items within a specified area on the project plans, suggesting a focused scope of work. No incumbent vendor information or specific budget constraints are revealed in this addendum. The primary purpose appears to be providing precise technical guidance to potential contractors to facilitate accurate and compliant quote submissions for the bridge infrastructure project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PW1659-25 - RFQ - Sinker Creek Bridge Micropile Installation Page 1 of 1
ADDENDUM #1
TO THE
REQUEST FOR QUOTES
PW1659-25 - RFQ - SINKER CREEK BRIDGE MICROPILE INSTALLATION
ISSUED ON 4/7/2025 8:00:00 AM
The following information in this addendum, hereby become part of the Request For Quotes. It is essential that all prospective Offerors note the content of this Addendum.
A. REVISED PLAN SET POSTED
B. Question and Answers:
1. What is the load capacity of the existing bridge? The existing bridge should not be relied upon for access.
a. The detour around is approximately 2.5 miles. We are working with the property owner to ensure the access is suitable for heavy equipment.
2. Sheet C-1 Note 7 states to remove 5EA trees. Is tree removal performed by the micropile contractor or the owner? If it is the micropile contractors responsibility, what bid item includes tree removal?
a. The County will be removing the trees. This quote only covers the micropile items within the red box on the third sheet of the plans.
3. Sheet J-2 shows a #13 GR80 Bar. #13 is not a standard bar size. Please confirm the required bar size.
a. The required bar size is #14. The plans have been revised to reflect this.
4. Specification Section 00515.05 (b) provides the option to submit an alternate design for the micropile foundations. If the contractor chooses to provide an alternate design, is the micropile casing required to be 12.750"x0.500w"?
a. Another size may be used if it can be demonstrated that it will work structurally.