Addendum 2~1.pdf

PDF 131 KB Posted

Attached to
FY27 Millis Meter Modernization Installation
Solicitation number
BD-27-1440-MIBOS-MIBOS-132421
Issued by
Norfolk County, New Bedford City, Massachusetts

About this file

This is Addendum No. 2 to the Invitation for Bids for FY27 Meter Modernization Installation issued by the Town of Millis, Massachusetts Department of Public Works. The project involves replacing water meters and meter interface units (MIUs) at residential locations throughout the approximately 67.4 square-mile town area. The Town will furnish Neptune MACH 10 ultrasonic meters and compatible Neptune R900 MIUs to replace existing Neptune meters and MIUs currently in service. The addendum addresses bidder questions regarding project scope, installation procedures, equipment compatibility, and contractor responsibilities. The bid was due on September 17, 2026 at 9:30 a.m. local time. Installation work will be performed in geographic or account-based groups coordinated with the Town's billing and meter-reading operations, though contiguous routes are not guaranteed due to access, customer scheduling, and field conditions.

Prevailing wage is required for this contract, and bidders must comply with the prevailing wage schedule issued for this procurement, including submission of certified payrolls and compliance statements. The Town will provide an electronic list of addresses, telephone numbers, and account information necessary for scheduling and installation, which contractors must maintain securely and use solely for contract purposes. At least one appropriately licensed Massachusetts plumber must be on-site at all times during installation work to handle plumbing-related tasks and code compliance. Contractors are responsible for providing all tools, equipment, software support, testing, and materials required for complete standard installations in accordance with manufacturer requirements. Removed equipment must be retained and accounted for until the Town authorizes disposition through approved salvage, recycling, return, or disposal processes. The Town will designate an inventory location for new meters and removed equipment, and contractor-proposed temporary storage units require prior written Town approval.

View the file

Other files

File Type Posted
Addendum 1~1.pdf PDF
WageSchedule_20260710130438~1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY27 Meter Modernization Installation | Addendum No. 2 | 1

TOWN OF MILLIS, MASSACHUSETTS | DEPARTMENT OF PUBLIC WORKS

Addendum No. 2 FY27 Meter Modernization Installation

Owner Town of Millis, Massachusetts

Issue Date September 10, 2026

Bid Due September 17, 2026 at 9:30 a.m. local time

Subject Responses to Bidder Questions

This Addendum forms part of the Contract Documents and provides the Town's responses to questions received concerning the Invitation for Bids. Except as expressly clarified below, all requirements, terms, conditions, quantities, and deadlines in the IFB remain unchanged. Bidders shall acknowledge receipt of this Addendum in their bid submission.

General Project Questions

1. Is there an engineer's estimate for this project?

Response: No engineer’s estimate was prepared or will be provided

2. What is the approximate geographic area, in square miles, covered by the meters under this Contract?

Response: The work is distributed throughout the Town of Millis at residential homes, approximately 67.4 miles of town area.

3. What brand of meter is currently in use?

Response: The Town currently uses Neptune meters and MIUs. The replacement equipment furnished by the Town will include Neptune MACH 10 ultrasonic meters and compatible Neptune R900 MIUs.

4. What is the age and primary material composition of the service lines, such as copper, plastic, or galvanized material?

Response: There is mostly copper but not all. The material does varies due to age of houses in town.

4a. If the Contractor is identifying service-line material, is identification limited to a visual inspection of the material visible on either side of the meter?

Response: Yes. Identification under this installation Contract is limited to readily observable conditions at the meter and other information made available by the Town. The Contractor shall not perform destructive investigation, excavation, or other construction to identify service-line material. Suspected lead, unsafe material, or an uncertain condition shall be documented and reported to the Town for direction.

5. What is the procedure for inoperable valves?

Response: The Contractor shall stop work when proceeding could cause damage, immediately document and report the inoperable or damaged valve, secure the condition, and await Town direction. The Contract does not include construction; repair or replacement of public water infrastructure required to complete an installation will be undertaken by the Town. Work outside a standard installation requires prior written authorization before any compensable extra work is performed.

FY27 Meter Modernization Installation | Addendum No. 2 | 2

AMR AMI Data and Installation Questions

6. Will the Contractor disconnect existing devices, such as old touchpads?

Response: Yes, when required for the assigned installation. The Contractor shall remove or disconnect existing meter-reading equipment necessary to complete the applicable meter or MIU replacement, install the new exterior MIU or reconnect an existing compatible MIU as directed, and account for all removed equipment through the approved salvage, recycling, return, or disposal process.

7. Is existing wire present to the outside of each structure?

Response: Existing conditions will vary by location and are not guaranteed. The Contractor shall verify wiring and compatibility before disturbing the service. Except for Town-furnished meters and MIUs, the Contractor shall provide the incidental wiring, connectors, and materials required for a complete standard installation in accordance with the manufacturer's requirements.

8. Will reading or testing devices be provided when equipment is preprogrammed?

Response: No Town-furnished reading or testing devices are identified in the IFB. The Town will furnish the new meters and MIUs; the Contractor is responsible for the tools, equipment, software support, activation, testing, and confirmation of valid readings and communications required for accepted installations.

9. Will meters be installed in contiguous routes?

Response: Installations will be performed in geographic or account-based groups approved by the Town and coordinated with billing and meter-reading operations. The Town does not guarantee that every assigned group or route will be fully contiguous because access, customer scheduling, nonresponsive accounts, and field conditions may require return visits or sequencing changes.

10. What billing software does the Town use?

Response: The town uses Munis for their billing software.

11. Will the Town provide an electronic list of addresses, telephone numbers, and account information?

Response: Yes. The Town will provide the account and customer information reasonably available and necessary to perform the work, including service and contact information used for scheduling and installation records. The Contractor shall use that information solely for this Contract, restrict access to authorized personnel, maintain it securely, and return or destroy it at closeout as directed by the Town and applicable records-retention requirements.

Labor Compliance Tax and Logistics Questions

12. Is prevailing wage required under this Contract?

Response: Yes. The Contractor shall comply with the prevailing-wage requirements and wage schedule issued for this procurement, including submission of required certified payrolls and statements of compliance. Bid prices shall include all labor costs necessary to comply with those requirements.

13. Will the Contractor receive an account list identifying locations for Existing MIU Reused, MIU-Only Replacement, and Meter and AMI Module Replacement?

Response: Yes. The Town will provide work assignments or account data identifying the applicable installation category or Price Item for each location, based on the information available to the Town.

The Contractor remains responsible for verifying the service address, account information, meter size, existing meter and MIU identifiers, condition, and compatibility before performing work, and shall report discrepancies for Town direction.

FY27 Meter Modernization Installation | Addendum No. 2 | 3

14. How long must the Contractor retain old meters and other removed equipment?

Response: Removed equipment shall remain accounted for and securely stored until the Town verifies the applicable inventory and authorizes transfer into the approved salvage, recycling, return, or disposal stream. No fixed number of days is established. The Contractor shall coordinate disposition with the Town through the monthly inventory reconciliations and shall not dispose of or abandon removed equipment without written Town direction.

15. Will the Town provide an area for placement of a storage container?

Response: The Town will designate an inventory location for new meters, MIUs, and removed equipment.

A Contractor-proposed temporary storage unit may be placed only after the Town provides written approval of the location and security provisions.

16. What services must the licensed plumber provide, and may the Contractor keep a plumber on standby for leaking service lines?

Response: At least one appropriately licensed Massachusetts plumber must be on site in the Town at all times while any installation crews are working. The plumber shall perform or provide the supervision required for plumbing work associated with meter installations, water shutoff and restoration, watertight connections, routine installation issues, and code compliance. An off-site, on-call plumber alone does not satisfy this requirement. Leaks attributable to the meter or MIU installation shall be corrected by the Contractor. Preexisting homeowner-side leaks and conditions requiring Town attention shall be documented, made safe when necessary, and promptly reported for direction. Construction, excavation, or public-infrastructure repair is outside this Contract and will be undertaken by the Town.

End of Addendum No. 2 All other provisions of the IFB remain in full force and effect.

Acknowledgment of Addendum The Bidder acknowledges receipt of Addendum No. 1 and confirms that its bid includes all requirements and modifications stated herein.

Bidder Name: __________________________________ Date: ______________________________

Authorized Signature: ___________________________ Printed Name and Title: __________________

General Project Questions
1. Is there an engineer's estimate for this project?
2. What is the approximate geographic area, in square miles, covered by the meters under this Contract?
3. What brand of meter is currently in use?
4. What is the age and primary material composition of the service lines, such as copper, plastic, or galvanized material?
4a. If the Contractor is identifying service-line material, is identification limited to a visual inspection of the material visible on either side of the meter?
5. What is the procedure for inoperable valves?
AMR AMI Data and Installation Questions
6. Will the Contractor disconnect existing devices, such as old touchpads?
7. Is existing wire present to the outside of each structure?
8. Will reading or testing devices be provided when equipment is preprogrammed?
9. Will meters be installed in contiguous routes?
10. What billing software does the Town use?
11. Will the Town provide an electronic list of addresses, telephone numbers, and account information?
Labor Compliance Tax and Logistics Questions
12. Is prevailing wage required under this Contract?
13. Will the Contractor receive an account list identifying locations for Existing MIU Reused, MIU-Only Replacement, and Meter and AMI Module Replacement?
14. How long must the Contractor retain old meters and other removed equipment?
15. Will the Town provide an area for placement of a storage container?
16. What services must the licensed plumber provide, and may the Contractor keep a plumber on standby for leaking service lines?

End of Addendum No. 2