Addendum 1~1.pdf

PDF 104 KB Posted

Attached to
FY27 Millis Meter Modernization Installation
Solicitation number
BD-27-1440-MIBOS-MIBOS-132421
Issued by
Norfolk County, New Bedford City, Massachusetts

About this file

This is Addendum 1 to a state and local contract opportunity. The addendum modifies the original solicitation terms and conditions. Key modifications include clarifications to the scope of work, updated requirements, and corrections to previous solicitation documents. The addendum specifies revised submission requirements and any changes to the evaluation criteria or technical specifications that bidders must address in their proposals. All prospective bidders are required to acknowledge receipt of this addendum as part of their bid submission to ensure compliance with the modified solicitation requirements. The effective date of the addendum and any revised deadlines for bid submissions are established to allow adequate time for bidders to incorporate the changes into their responses.

The addendum addresses pricing adjustments, clarifications on cost proposals, and any modifications to payment terms or conditions outlined in the original solicitation. Any changes to set-asides, minority-owned business enterprise preferences, or other socioeconomic program requirements are detailed within the addendum. The document ensures that all bidders operate under consistent and current information, preventing disputes related to incomplete or outdated solicitation documents. Bidders must verify that they have received all addenda issued for the solicitation prior to submission to avoid rejection of non-responsive proposals.

View the file

Other files

File Type Posted
Addendum 2~1.pdf PDF
WageSchedule_20260710130438~1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Town of Millis | IFB #27-DPW01 FY27 | Addendum No. 1

Addendum No. 1 FY27 Meter Modernization Installation

Awarding Authority Town of Millis, Massachusetts

Contract Number IFB #27-DPW01 FY27

Addendum Date September 10, 2026

Bid Due September 17, 2026 at 9:30 a.m. local time (unchanged)

This Addendum forms part of the Invitation for Bids and responds to questions received. Except as expressly modified below, all requirements, terms, conditions, and the bid deadline remain unchanged.

Bidders must acknowledge receipt of this Addendum in their bid submission.

Questions and Responses

1. Question: Is this project subject to Massachusetts prevailing-wage requirements? The IFB describes it as a Chapter 30B non-construction service and does not include a wage schedule;

however, Sections 1.15 and 1.19 require certified payroll documentation. If prevailing wages apply, please issue the applicable wage schedule by addendum.

Town response: Yes. The Massachusetts prevailing-wage requirements apply to covered labor performed under this Project. The enclosed wage schedule, issued July 10, 2026, under Wage Request Number 20260710130438, is incorporated into the IFB and shall be made part of the Contract.

Contractors and subcontractors must pay the applicable rates, submit required weekly certified payroll reports and statements of compliance, and comply with all posting and update requirements stated in the wage schedule. References in the IFB to procurement under Chapter 30B or to the Town's responsibility for separate excavation or infrastructure work do not waive these obligations.

2. Question: Please confirm whether a bid bond is required with the submission and identify the required performance and payment security after award.

Town response: No bid bond or bid deposit is required with the bid. No performance bond is required.

The successful bidder shall provide, before contract execution, a payment bond in an amount not less than 50 percent of the total contract price, issued by a surety authorized to do business in Massachusetts and otherwise acceptable to the Town. To the extent Appendix F, Section 4, is inconsistent with this response, this Addendum controls.

3. Question: May the bidder satisfy the Massachusetts plumbing-license requirement through a properly licensed plumbing subcontractor? If so, must that subcontractor be identified with the bid?

Town response: Yes. A bidder may satisfy the plumbing-license requirement through a properly licensed plumbing subcontractor. The subcontractor is not required to be identified with the bid. The successful bidder must identify the plumbing subcontractor and all licensed plumbers who will work on the Project in the post-award submittal required within 28 days after the Notice to Proceed, and must provide valid license information to the Town and the Building Department before plumbing work begins.

Town of Millis | IFB #27-DPW01 FY27 | Addendum No. 1

4. Question: Must the prime contractor hold a Massachusetts plumbing business license, or is supervision by the required Massachusetts-licensed plumber sufficient?

Town response: The prime contractor is not required to hold a Massachusetts plumbing business license if all plumbing work is performed through a properly licensed plumbing subcontractor. All plumbing work must be performed by, or under the legally required supervision of, appropriately licensed Massachusetts plumbers. At least one licensed plumber must be present in the Town/on site whenever crews are performing work, as required by IFB Section 1.5. The contractor and subcontractor remain responsible for complying with all applicable Massachusetts licensing, permitting, and supervision requirements.

5. Question: Item 4 lists a salvage-credit quantity of 2,476 'meter and AMI module' units, although Item 2a reuses 530 existing MIUs and Item 2b replaces only 32 MIUs. Please clarify exactly what removed equipment receives the salvage credit under each installation type.

Town response: Item 4 represents one salvage-credit unit for each completed installation/account for which the applicable removed equipment is accepted into the Owner-approved salvage stream. The estimated 2,476 units equal the total estimated installations under Items 2a, 2b, and 3. The credit is applied as follows:

IFB Item Estimated Qty. Removed Equipment Eligible for Salvage Credit Units

2a 530 Removed 5/8-inch water meter only; the existing MIU is reused. 1 per accepted installation

2b 32 Removed existing MIU only; the water meter remains in place. 1 per accepted installation

3 1,914 Removed 5/8-inch water meter and removed MIU, treated together as one salvage unit for the account.

1 per accepted installation

No separate or duplicate salvage credit will be applied to the meter and MIU removed under the same Item 3 installation. Salvage credits are based on actual verified quantities accepted by the Owner, not the estimated quantities.

Acknowledgment of Addendum The Bidder acknowledges receipt of Addendum No. 1 and confirms that its bid includes all requirements and modifications stated herein.

Bidder Name: __________________________________ Date: ______________________________

Authorized Signature: ___________________________ Printed Name and Title: __________________