Addendum 2 SOCC RFP Fire Tower.pdf
PDF 169 KB Posted
- Attached to
- RFP - Fire Tower
- Solicitation number
- S-P00675-00006007
- Issued by
- Coos County, Condon City, Oregon
About this file
This document is an Addendum to a Request for Proposals (RFP) issued by Southwestern Oregon Community College for the construction of a Fire Tower. The RFP was originally issued on March 6, 2023, with a closing date of April 6, 2023, at 3:00 PM. The Addendum provides clarifications and additional details regarding the project scope, including the preferred design, interior square footage requirements, container specifications, and the number of burn rooms to be included. The Fire Tower is to be located in Coos County, Oregon, and the project is open to negotiation within a budget constraint, with the structure not to exceed 3,500 square feet.
The clarifications provided in the Addendum indicate that the College is open to different design options, but the interior training space should be approximately 2,500 square feet, with the first floor being larger and the second, third, and fourth floors being equal in size. The Addendum also specifies that two stacking containers, each 10 feet long, 20 feet wide, and 9 feet tall, are required for the maritime simulation, and these containers do not need to be new. Additionally, the Addendum states that two burn rooms, each 12 feet by 12 feet or larger, are to be included on the ground floor and the second floor.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 1 SOCC RFP Fire Tower.pdf | ||
| RFP Fire Tower.pdf | ||
| Intent to Award~23.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSALS
Fire Tower
Addendum #2
Addendum #1 Issue Date: March 13, 2023
Addendum #2 Issue Date: March 24, 2023
RFP Issue Date: March 6, 2023
RFP Closing Date and Time: April 6, 2023 at 3:00 PM
This Solicitation Addendum is issued to the above referenced RFP and forms a part of the contract documents and modifies the original scope of work, specifications and drawings, requirements and deadlines. Except as changed by this Addendum, all terms, conditions, scope of work, plans, specification, requirements and deadlines in the original RFP and previous addenda remain unchanged.
PLEASE NOTE THE FOLLOWING CLARIFICATIONS, ADDITIONS, CORRECTIONS OR REVISIONS TO THE ABOVE
REFERENCED RFP HIGHLIGHTED BELOW:
Below are questions that have been submitted to Southwestern Oregon Community College since the publication of the RFP. Questions posed are in red and answers are in blue.
1 Clarification Q: Can the college provide any additional information on the preferred design? We can construct a 4-Story, 2500 sq. ft. Tower many different ways.
A: Understanding budget constraints, it is open to negotiation. We would not see the structure exceeding 3,500 Sq. Ft.
2 Clarification Q: Is the 2,500 sq. ft. requirement considering interior training space, exterior training space, or both interior and exterior training space combined?
A: Only interior training space was considered. 2,500 Sq. Ft. was an approximate estimate.
3 Clarification Q: Can the College advise on the total interior sq. footage required for each level of the Tower?
A: First floor could be a larger Sq. Ft. space, but the 2nd, 3rd, and 4th floors should be equal in size.
4 Clarification Q: Can the College advise on the total number of containers required and sizes (e.g., 40-ft, 20-ft, etc)?
A: For the maritime simulation, two stacking containers are sufficient. 10 feet long, 20 feet wide, 9 feet tall.
5 Clarification Q: Should the container be new/1-Way condition?
A: Not necessary for the containers to be new.
6 Clarification Q: What height is desired for the containers (e.g., standard height or high-cube)?
A: 9 feet tall
7 Clarification Q: Is only one burn room to be included?
A: Two total burn rooms in the entire structure. This can be located in the
RFP:
3) SCOPE OF WORK
d) Additional Considerations iii.) Burn Rooms 12’ x 12’ or larger on Ground Floor and Second Floor
End of Addendum #2