This is Addendum 2 to Request for Proposals RFP-010-27 issued by the Louisville Regional Airport Authority for a Common Use Passenger Processing System (CUPPS) and support services at Louisville Muhammad Ali International Airport in Kentucky. The addendum addresses 70 questions received from prospective bidders and clarifies system requirements, hardware specifications, pricing structure, warranty terms, and contractual provisions. The scope encompasses design, software development, hardware provision, system integration with the existing Art of Context Flight Information Display System (FIDS) and OAG data feed, installation, configuration for 70 ticketing positions and 55 concourse positions (with hardware deployed to 17 ticketing and 21 gate positions plus one mobile passenger processing unit), training, licensing, cloud or on-premises hosting options, and three years of technical support services. The original proposal deadline of November 18, 2026 has been extended to November 19, 2026 at 2:00 p.m. EST, with a public bid opening scheduled via Zoom on the same date. The contract term is three years with two optional one-year renewals, and implementation milestones include Ticketing Phase 1 on September 24, 2027, Concourse implementation on October 29, 2027, Ticketing Phase 2 on March 3, 2028, and Concourse A on December 14, 2029.
The pricing must include a lump-sum total for three and five years followed by itemized costs by category, with recurring support costs separately detailed for each year including optional extension years. All pricing excludes Kentucky sales and use tax, and hardware prices remain valid for 120 calendar days. The bid requires a $10,000 bid bond or irrevocable bank letter of credit valid for 120 calendar days, with a $50,000 performance bond required upon award. The Authority will provide network switches, cabinetry, cabling, Wi-Fi connectivity for the mobile cart, and cybersecurity software installation, while the proposer supplies all other hardware including the mobile cart monitor and assumes responsibility for airline host connectivity, application certification, airline-specific configuration, Level 2 and Level 3 technical support, and onsite equipment storage. Warranty commences upon final acceptance rather than tied to the three-year contract term, and the Authority clarified that indemnification obligations apply to third-party claims only, with pre-existing intellectual property remaining with vendors and technology providers.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| LRAA Addendum 2, Attachment C1, Node Table, RFP-010-27.xlsx | XLSX spreadsheet | |
| Addendum 1.pdf | ||
| LRAA RFP-010-27, CUPPS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
Louisville Regional Airport Authority
PURCHASING & PROCUREMENT
LOUISVILLE, KENTUCKY
Invitation No: RFP-010-27 Date: November 10, 2026 Post Bid Addendum No: Two (2) Title: Common Use Passenger Processing System and Support Services
The following shall clarify and/or modify the original Proposal Document(s) as issued by the Louisville Regional Airport Authority (the “Authority”). All information shall be collectively incorporated in part of the original Proposal Documents. Except as specifically added and/or revised by this Addendum all other conditions, provisions, and criteria within the original Proposal Documents are unchanged.
This second Addendum consists of thirteen (13) pages involving the following information:
Part 1. Questions received and the Authority’s response/stance
Part 2. Revisions & Clarifications *Proposal deadline extension
Part 3. Zoom link for public bid opening
Proposer must acknowledge receipt of this and any addenda either with Proposal or by separate letter no later than 2:00 PM EST, November 19, 2026.
BY: T’airra Bridgewaters Authorized Purchasing Officer
Receipt Acknowledged:
Company Name
BY:
Print Sign
Remainder of page left intentionally blank
2 | P a g e
Title: Common Use Passenger Processing System and Support Services
Part 1. Bid questions received and the Authority’s stance.
1) Question: ATTACHMENT C, III System Requirement, 3.3: Can you clarify what real time data feed is expected from the CUPPS?
AUTHORITY: If we can leverage the existing OAG feed delivered through Art of Context for our FIDS, please do so. If not, please propose whichever data feed you think works best with your solution.
2) Question: ATTACHMENT C, III System Requirement, 3.4: Does the integration of the existing FIDS corresponds to the integration of the FIDS application within the CUPPS environment? If yes, can you confirm if the FIDS application is a WEB application? If not, do we need to provide a FIDS system compatible with the existing FIDS screens?
AUTHORITY: Integrate with the existing FIDS. Yes, we access it via a web application.
3) Question: ATTACHMENT C, VI & VII : It is mentioned 70 + 55 positions but provision of only 17 + 21 HW components for positions. Can you clarify this item? Other positions already have their HW devices? If yes please confirm which are the HW devices (Brand and Model) as well as date of installation? Can you clarify the purpose of the “Mobile passenger Processing Unit? Is this dedicated to boarding only? Printing TAG only? BP too?
AUTHORITY: No, the other positions do not have HW devices, they use legacy hardware and will not have common use devices deployed. The RFP states that programing will be completed for all positions (70+55), but not all positions will require hardware.
The Mobile Passenger Processing Unit is intended for use to process passengers at the gate (boarding only). The required equipment is included in the node matrix.
4) Question: ATTACHMENT C, IX : Can you clarify the exact content of the reports expected? CUPPS platform are able to deliver reports about the CUPPS usage (counters usage…, devices, printing counts) but not the “Flight Audit Information”
AUTHORITY: Please detail stock reporting capabilities and available customization options.
5) Question: Instructions to Proposers (ITP) Section VI, 6.1; Proposal Form, item C.ii: Please confirm the required proposal validity period. ITP Section VI 6.1 states 90 calendar days and the Proposal Form item C.ii states 120 calendar days.
AUTHORITY: Proposals shall remain valid for one hundred-twenty (120) calendar days.
6) Question: Definitions (Bank Letter of Credit / Bid Bond); Instructions to Proposers (ITP) Section VI, 6.1: Please confirm the minimum validity of the Bank Letter of Credit or Bid Bond. The definition states 60 days from the due date, which is shorter than the proposal validity period.
AUTHORITY: Bid bond and bank letter of credit shall remain valid for one hundred-twenty (120) calendar days.
Left blank intentionally
3 | P a g e
7) Question: Attachment A (Bid Bond form); Instructions to Proposers (ITP) Section V, 5.2:
Please confirm what is payment bond and how is it different from performance bond and bid bond?
AUTHORITY: Please refer to Definition of Terms – page T-2 – and Attachment A, subsection (b) – page A-1. Depending on use of subcontractors, a payment bond may be required.
8) Question: Proposal Form, Section IV (Affidavit); Instructions to Proposers (ITP) Section VI, 6.2: Please confirm if an affidavit notarized outside the USA (with apostille if needed), or by remote online notarization, is acceptable.
AUTHORITY: The affidavit can be completed, including remotely, by an active notary from any jurisdiction. If complete remotely or outside of the U.S., apostille is required.
9) Question: Questionnaire, item 9 (attestation): The attestation refers to 'Runway Marking Paint'. Please confirm that this is a typographical error and that the proposer may sign the page without change.
AUTHORITY: Yes, this is a typo and should refer to Common Use Passenger Processing System. Proposers may sign as-is or may cross out the reference to marking paint.
10) Question: General Conditions Section II, 2.1 and 2.2; Questionnaire, item 7; Proposal Form,
1.1 E: Please confirm that a proposer may submit as a prime contractor with named subcontractors for the scope of work along with approval process and timelines for appointing subcontractors. Please also confirm if the minimum qualifications in General Conditions Section II 2.1 and the references in Questionnaire item 7 can be met by a named subcontractor or the OEM of the proposed CUPPS platform, or only by the proposer or a joint venture member.
AUTHORITY: Subcontractors and OEMs must have equivalent technical experience, while the proposer must provide evidence of experience managing projects of similar scope.
11) Question: General Conditions Section II, 2.1(b) and 2.2; Questionnaire, item 7: Will the Authority accept verifiable experience and references from airports outside North America that are comparable in size and complexity towards Section 2.1(b) and Questionnaire item 7, and score them under Experience and References? If the Authority requires North American experience, will it accept that of a joint venture member or consortium partner in accordance with Section 2.2?
AUTHORITY: Please use North American references. Experience will be accepted in accordance with section 2.2.
12) Question: Attachment C, Section I and 2.1, 11.1; Proposal Form, 1.1 F: Please define 'hybrid CUPPS'. Does the Authority expect the core servers on the Authority VMware platform, a cloud-hosted service, or a mix? Is a fully cloud-hosted option acceptable?
AUTHORITY: Hybrid refers to some positions that will use the CUPP while other positions will continue to use the Airline proprietary hardware. This does not relate to delivery of the system via on premise or cloud based.
13) Question: Attachment C, 6.2, 7.2 and 11.1; Attachment D, D4 to D8: Please give the node table as an Excel file with the device count for each position, confirm that 'Appendix' means Attachment D, and confirm the airlines for initial configuration.
AUTHORITY: Node Table included in Part 2 of this addendum. The initial configuration will be finalized during the design process.
4 | P a g e
14) Question: Attachment C, 6.1, 7.1 and 11.1: Please confirm that the proposer supplies no network switches and that 'switch-port capacity' means CUPPS licensing and configuration for 70 ticketing and 55 concourse positions.
AUTHORITY: Confirmed. The Authority will provide the switches as needed and the Proposer will develop the software architecture
15) Question: Attachment C, 8.1; Attachment D, D7: Please confirm if the Concourse A hardware and implementation is in the base price, or is to be priced as an option.
AUTHORITY: The Concourse A hardware and implementation is included in the base price.
16) Question: Attachment C, 4.5: Please supply the cybersecurity and information security requirements referred to in Attachment C 4.5.
AUTHORITY: The Authority will install existing cybersecurity software on the endpoints.
17) Question: Attachment C, 3.5; Questionnaire, item 3: Please confirm that automatic updates may be staged (tested first, then deployed automatically in a maintenance window) to protect airline applications.
AUTHORITY: Yes, this approach is acceptable.
18) Question: Questionnaire, item 2; Attachment C, 2.3: Please confirm which screens are in the Emergency Alert override scope and whether the trigger comes from FIDS or the EOC.
AUTHORITY: The trigger for screen overrides will come from FIDS.
19) Question: General Conditions Section VIII, 8.3; Proposal Form, 1.1 H: Please confirm the approval process for after-hours and overnight work for cutovers.
AUTHORITY: We prefer to schedule cutover activities during regular work hours, but can accommodate after-hour work as necessary.
20) Question: General Conditions Section XI, 11.3 and Section III, 3.2; Draft Agreement Section XX, 20.3; Proposal Form, 1.1 F: Please confirm (a) if the warranty starts for each phase or at final acceptance, and (b) if support after the warranty, for the rest of the term and each option year, is to be priced as recurring annual cost.
AUTHORITY: Warranty begins upon final acceptance, and support costs must be itemized separately by year including the two optional one-year extensions.
21) Question: Draft Agreement Section IX, 9.1 and Section IV, 4.1: Please confirm the payment schedule for the bidder (for example, by milestone or at acceptance).
AUTHORITY: The company should submit detailed monthly invoices for all provided products and services.
22) Question: Draft Agreement Section XI, 11.2; General Conditions Section VI, 6.2: Draft Agreement Section XI 11.2 cites Attachment D, while General Conditions 6.2 cites Attachment E. Please confirm that Draft Agreement Section XI 11.2 refers to Attachment E.
AUTHORITY: Yes, company shall comply with the airport security procedures set forth in Attachment E. This has been corrected in Part 2 of this addendum.
5 | P a g e
23) Question: Draft Agreement Section XVII, 17.2; Attachment C, Sections VIII and XI (requested change under ITP Section XIII, 12.1): Draft Agreement Section XVII 17.2 provides an extension of time when a party is delayed by causes outside its reasonable control. Please confirm that such causes include delays caused by the Authority's SDF Next construction programmed, access restrictions set by the Authority, Authority-supplied items listed in Attachment C Section XI, and airline host-system readiness or certification. Please also confirm that the Company may request an equitable price adjustment for additional costs caused by such delays. The Proposer does not request any change to the operational dates in Attachment C Section VIII.
AUTHORITY: This covers delays caused by construction or necessary materials supplied by the Authority. The company must promptly notify the Authority of any delay or potential delay regarding required materials or site access. Reasonable price adjustments will be considered and negotiated in good faith.
24) Question: Draft Agreement Section XXVIII (requested change under ITP Section XIII, 12.1): Requested change: please add a limitation of liability clause: "The Company's total aggregate liability arising out of or in connection with this Agreement shall not exceed one hundred percent (100%) of the total amount paid/payable under this Agreement." Please also amend Section XXVIII so that the indemnity applies to losses to the extent caused by the negligence, willful misconduct or breach of the Company or its subcontractors.
AUTHORITY: The Authority respectfully declines this request.
25) Question: Draft Agreement Section XVII, 17.2, Section XII, 12.1 and Section XXII, 22.2;
General Conditions Section VIII, 8.2 (requested change under ITP Section XIII, 12.1): Please confirm that the reasonable opportunity to cure under Draft Agreement Clause 17.2 also applies before the Authority exercises its step-in rights under Draft Agreement Clause 22.2 and General Conditions Clause 8.2, except in emergencies affecting airport operations or safety.
AUTHORITY: A reasonable opportunity to cure will be provided, except in emergency circumstances impacting airport operations. During an emergency, problems must be addressed immediately and resolved as quickly as possible.
26) Question: Draft Agreement Section VI, 6.2 (requested change under ITP Section XIII, 12.1):
Draft Agreement 6.2 allows the Performance Bond to be drawn on termination for default.
We request that the bond may be drawn only after the cure period in Section XVII 17.2 has expired.
AUTHORITY: The Authority will give the company a reasonable cure period before declaring a default or drawing on the performance bond.
27) Question: Draft Agreement Section VIII, 8.2 and 8.3 (requested change under ITP Section XIII, 12.1): Draft Agreement 8.2 and 8.3 make documents and material generated under the Agreement the property of the Authority as works made for hire. Please confirm that this does not apply to pre-existing intellectual property of the Company or its technology providers, including software, tools, methods and standard product documentation, which remains with its owners, and that the Authority receives a license to use it for the purposes of the Agreement.
AUTHORITY: That is correct – this does not include pre-existing intellectual property of the Company or its technology providers.
6 | P a g e
28) Question: General Conditions Sections VI, 6.5, VIII, 8.2 and IX, 9.2; Draft Agreement Sections VI, 6.2, XXI, 21.2 and XXII, 22.2 (requested change under ITP Section XIII, 12.1):
The Agreement allows the Authority to recover costs by reimbursement, direct billing and the Performance Bond (General Conditions 6.5, 8.2 and 9.2; Draft Agreement 6.2, 21.2 and 22.2). Please confirm that any deduction or recovery is limited to reasonable, documented costs, is made after written notice to the Company, and is not recovered more than once for the same event.
AUTHORITY: Confirmed.
29) Question: Instructions to Proposers (ITP) Section II; Proposal Form, 1.1: Please confirm any portal file-size limit and where the Bid Bond, proof of insurance and Questionnaire are placed in the single PDF.
AUTHORITY: No size restrictions. The Bid Bond and insurance certificate can be paired with the Questionnaire. Please refer to Proposal Form, section I of page PF-2.
30) Question: Draft Agreement Section IV, 4.1: The not-to-exceed amount is blank. Is there an approved budget or NTE value for the 3-year term, and does it include the extension years?
AUTHORITY: The final contract total depends on the bids received and will be added after the award is made.
31) Question: Proposal Form Section I, F: Please confirm the expected price format: one lump sum, or itemized prices per phase (Ticketing Ph1, Concourse, Ticketing Ph2, Concourse A) and per category. Will LRAA issue a price schedule template?
AUTHORITY: Proposer should provide three and five-year lump sum totals, followed by itemized cost by identified categories. Pricing shall be all inclusive and easy to interpret.
32) Question: Proposal Form Section I, F; Specifications (Attachment C) Section X, 10.4: Is recurring support to be priced for each of years 1–3 and for each extension year separately?
Does support for years 2 and 3 start after the 12-month warranty?
AUTHORITY: Please refer to question number 20 and provided response.
33) Question: Draft Agreement Section IV, 4.3 (requested change under ITP Section XIII, 12.1):
Request annual escalation on recurring support and extension years. Hardware prices should be held for XX days, with relief for US tariff or customs duty changes after bid date.
AUTHORITY: Ongoing support costs for subsequent years fall entirely to the proposer and represent a key competitive scoring factor. All rates will remain valid for one hundred-twenty (120) calendar days.
34) Question: Instructions to Proposers Section X; Specifications (Attachment C) Section VIII, 8.2: If the Notice of Award or Effective Date is later than January 2027, will the 24 Sep 2027 Phase 1 date and other milestones move day for day?
AUTHORITY: No, the milestones for beneficial use of the system will not change.
35) Question: Specifications (Attachment C) Section VIII, 8.1: Please confirm which positions are in each milestone.
AUTHORITY: This is provided by the naming of the milestones. Ticketing milestones are noted as east and west with dates and are referenced in the node table documents.
Concourse Improvements include implementation in Concourse B and Concourse C. the Concourse A milestone includes positions in Concourse A.
7 | P a g e
36) Question: General Conditions Section III, 3.2; Specifications (Attachment C) Section VIII, 8.1: The Concourse A go-live (14 Dec 2029) falls near the end of the 3-year term. How will its warranty and support beyond the term be contracted?
AUTHORITY: The warranty is not related to the three-year term, it is tied to the completion of construction and will commence at the time of acceptance by the Authority. The support of Concourse A (and previous milestones) will be either negotiated with the current provider or procured separately.
37) Question: Draft Agreement Section XII, 12.2 to 12.4 (requested change under ITP Section XIII, 12.1): On termination or scope cut for convenience, please confirm payment for licenses, hardware ordered or delivered, and committed vendor costs. Any unamortized one-time costs to be paid in full.
AUTHORITY: The Authority will pay for delivered products and services, plus any pending hardware orders, as long as the items ordered are correct.
38) Question: Draft Agreement Sections XII, 12.1 and XVII, 17.2 (requested change under ITP Section XIII, 12.1): [Contract change] Termination for default should follow written notice and a 30-day cure period, in line with DA 17.2.
AUTHORITY: The Authority respectfully declines this requested change. 30 days may be an exorbitant amount of time to cure, depending upon the issue. To that end, we believe the “reasonable opportunity” is appropriate because that depends upon the circumstances present. Moreover, there may be issues surrounding default that warrant termination and the Authority does not want to be bound by a repeating cycle of 30-day cures that could last months or years.
39) Question: Draft Agreement Section IX, 9.2 and 9.3: Please confirm prices should exclude Kentucky sales and use tax, given LRAA's exemption certificate. Will LRAA provide a W-9 or exemption details for hardware purchases?
AUTHORITY: Confirmed. The awarded vendor will be provided the Authority’s W-9 and exemption certificate.
40) Question: Draft Agreement Section IX, 9.2: If a non-US entity is the contracting party, will LRAA withhold any US tax on payments? Can payments be made by wire in USD to a non- US account?
AUTHORITY: No, the awarded company will be responsible for paying all federal, state, and local taxes which may be assessed against it or its equipment, materials, supplies, or services to be provided under this agreement. Please refer to sections 9.3 and 9.4 of the Draft Agreement.
41) Question: Specifications (Attachment C) Section III, 3.2: Who pays for airline host connectivity (SITA/ARINC or airline networks), airline application certification and airline-specific configuration?
AUTHORITY: These costs should be included in the proposal.
42) Question: Specifications (Attachment C) Sections II, 2.3 and XI, 11.1; Attachment D – Plans (node table): Please confirm LRAA supplies the monitor for the mobile cart as well (node table shows 1 monitor). Are network switches, cabinetry and cabling fully excluded from our price?
AUTHORITY: The Authority will NOT provide the monitor for the Mobile Cart; the Proposer will. Refer to Attachment C, article XI., section 11.1 (page C-5).
8 | P a g e
43) Question: Specifications (Attachment C) Sections VI, 6.4 and VII, 7.5: How long must backstock unit prices stay valid, and can they be indexed?
AUTHORITY: We recognize that computer hardware prices fluctuate rapidly. Please specify the timeframe you can guarantee quoted prices for backstory inventory.
44) Question: General Conditions Section VIII, 8.3: Is after-hours and weekend installation work approved in advance for the zero-disruption cutover, or is it priced as an extra?
AUTHORITY: The installation of equipment at the positions can be scheduled as to not interrupt service. Proposer should assume that after hours and weekend installation is not required.
45) Question: Instructions to Proposers Section V; Draft Agreement Section VI: Can a bank-issued standby LC (SBLC) from an international bank, confirmed by a US bank, replace the bid and performance bonds? Must it be drawable in Louisville?
AUTHORITY: No, you must use the provided bond documents. However, a standard commercial bank letter of credit or certified cashier’s check may be submitted instead of the bid bond, provided it is received before the bid deadline.
46) Question: Draft Agreement Section VI, 6.2: Please confirm the Company's maximum liability for termination by default.
AUTHORITY: We are unable to confirm that the maximum liability would be equivalent to the performance bond as that would nullify Section XXVIII (indemnification) and Section 11.5 relating to fines and damages for breaches of airport security.
47) Question: Attachment C (Specifications), Section VIII, 8.1 (Schedule Requirements);
Section VI, 6.1–6.4 (Ticketing) and Section VII, 7.1–7.5 (Concourse); Attachment D (Plans), pages D-4 to D-8; Proposal Form, 1.1(F): What are the exact quantities of bulk hardware that need to be included in the proposal for phases starting on 9/24/2027, 10/29/2027, 03/03/2028 and 12/14/2028.
AUTHORITY: The above referenced tables include the naming convention and hardware necessary for each milestone. The nodes have been provided as an excel file to assist the proposal process. Please refer to Part 2 of this addendum.
48) Question: Attachment C (Specifications), Section III (System Requirements), 3.1 and 3.1(a):
The Company needs to configure 7 airlines initially, and it then mentions one separate test company. Could you please clarify if that would be a local-DCS? Or do we need to create a test bed with a generic airline?
AUTHORITY: Test bed with generic airline.
49) Question: Further to the Authority’s response regarding subcontracted support (Attachment C, Sections 3.5 and 10.4–10.5) can the Authority confirm that Level 1 support and maintenance will be the proponent’s responsibility? If so, can the Authority specify the required on-site coverage hours?
AUTHORITY: Yes, level 1 support will be provided by the Authority.
50) Question: "Ref 3.1 Support at least ten airlines plus one test company for equipment troubleshooting and system validation. Ref 3.1a Initial configuration for American, Allegiant, Breeze, Delta, Sun Country, Southwest, United, and one separate test company." Can the Authority please clarify the identity and scope of the 'one separate test company' listed in the initial configuration. Is this a specific airline testing environment, a ground handler, or an internal airport test profile, and what specific application package is required for this entity?
AUTHORITY: Internal airport test profile with generic airline.
9 | P a g e
51) Question: "Ref 3.3 Real-time flight data feed; integrate with the existing Art of Context FIDS and the OAG flight-data feed.
Ref 3.4 Display airline branding, flight information, and airline counter status (open, closed, priority) at ticket-counter and gate locations.
Ref 3.10 Hold flight records in a transmission queue during connection failure; ability to purge and refresh with a new snapshot based on time-rule criteria; update displays immediately after network disruption.
Ref 4.1 Client access for multiple users with appropriate security rights to update master and daily flight schedules, display content, and security access, and to administer the System."
We understand that flight scheduling, data queueing for public displays, and FIDS/OAG data integrations are functions of an Airport Operational Database (AODB) or Flight Information Display System (FIDS), rather than a core CUPPS platform.
Can the Authority please confirm our understanding that these display management and flight data feed requirements are out of scope for the CUPPS platform?
AUTHORITY: The display management will be handled through the integration with the FIDS. The data feed requirements for the CUPPS should leverage the existing data feed with OAG through Art of Context, if possible, and if not, the CUPPS proposer will need to include a data feed to drive information needed for CUPPS.
52) Question: The signature page below references “Runway Marking Paint.” Can the
Authority please confirm that this form should be signed as is?
AUTHORITY: Please reference question 9 and provided response.
53) Question: I believe we will need to submit pricing only for the 3 initial years of the contract.
Is that correct?
AUTHORITY: Please reference question 31 and provided response.
54) Question: What is LRAA's definition of a "hybrid" Common Use Passenger Processing System referenced on page 48?
AUTHORITY: Please reference question 12 and provided response.
55) Question: Please clarify what type of integration is required from the Common Use Passenger Processing System to the Art of Context Flight Information Display System.
AUTHORITY: The display changes will be handled through Art of Context.
56) Question: Is LRAA seeking a desktop link to the FID's system?
AUTHORITY: We can provide the URL for a desktop link to the FIDS.
57) Question: Is LRAA open to a financial surety alternative to a Bond, such as escrow or a deposit?
AUTHORITY: No
58) Question: Wi-Fi Connectivity - RFP Page 50 | Attachment C, Section VII.7.2: Please confirm that the Authority will provide all Wi-Fi connectivity required for the mobile passenger processing unit.
AUTHORITY: Confirmed
59) Question: FIDS and OAG Integration - RFP Page 48 | Attachment C, Section III.3.3: Please clarify the intended interface between the CUPPS system, FIDS, and OAG. Specifically, please confirm whether airline agents are expected to manually activate their assigned
10 | P a g e counter/gate within the Art of Context FIDS application, accessible through a desktop icon after agent login, or whether CUPPS login/logout events are expected to automatically activate/deactivate the corresponding FIDS position.
AUTHORITY: The CUPPS login will activate/deactivate the FIDS position based on the credentials entered.
60) Question: Technical Support Responsibilities - RFP Page 52 | Attachment C, Section
X.10.4: Please confirm that Level 1 onsite support will be provided by the Authority, with the CUPPS provider responsible for remote Level 2 and Level 3 support and onsite dispatches as required.
AUTHORITY: Yes, level 1 support will be provided by the Authority.
61) Question: Warranty Specifications - RFP Page 19 | General Conditions, Section XI.11.1:
While hardware and services will conform to all provisions of the Proposal Documents and applicable product specifications, we are concerned that the language in this section is subjective and could be interpreted differently over the contract term. Would the Authority consider amending this section to incorporate only objective specifications?
AUTHORITY: While we think the standards of what is available over time could change, we believe the interpretation would remain the same as it is “new and unused, of the latest products in production to commercial trade and shall be of the highest quality as to materials used.”
62) Question: Service Resolution Requirements - RFP Page 19 | General Conditions, Section XI.11.2: This provision is unclear in light of the service level agreements (SLAs) that will be included in our standard service schedules. Would the Authority consider deleting this section to avoid potential inconsistencies?
AUTHORITY: The intent is to prevent excessive delays in resolution. Please refer to Part 2 of this addendum for the revision.
63) Question: Works Made for Hire - RFP Page 31 | Draft Agreement, Section VIII.8.3: We have not identified any deliverables in the Proposal Documents that would constitute works made for hire, and the reference to "all documents" in Section VIII.8.3 appears overly inclusive. Would the Authority consider removing this section or otherwise clarifying which works made for hire are contemplated?
AUTHORITY: Section 8.3 further clarifies sections 8.1 and 8.2. The reference of “all documents” should be “Proposal Documents” as defined in section 8.2. Please refer to Part 2 of this addendum for the revision.
64) Question: Termination for Default - RFP Page 34 | Draft Agreement, Section XII.12.1:
Given the provision allowing immediate termination for default, would the Authority consider adding a materiality qualifier to this section?
AUTHORITY: The Authority respectfully declines this request.
65) Question: Indemnification - RFP Page 41 | Draft Agreement, Section XXVIII: To avoid confusion with standard breach-of-contract claims, would the Authority accept a clarification specifying that the indemnification obligations apply to third-party claims?
AUTHORITY: Yes, the Authority clarifies that the indemnification obligation is as to 3rd party claims.
11 | P a g e
66) Question: Employee Background Checks - RFP Page 16 | General Conditions, Section VI.6.3: Under SITA's company policy, employee background checks are conducted at the time of employment and cover the preceding seven years, rather than being conducted on a rolling basis. Would the Authority accept an affidavit attesting to compliance with this policy?
AUTHORITY: Yes.
67) Question: Attachment C, Item 2.1 – As per pre-bid feedback, hybrid and/or full cloud is acceptable.
AUTHORITY: On premises, hybrid or full cloud is acceptable.
68) Question: Attachment C, Is the Airport 100% common use?
AUTHORITY: No, the Airport does not have common use. It implements a hybrid system. Please reference question 12 and provided response.
69) Question: Attachment C, Item 3.3 Is FIDS a requirement or just the integration to the current airport FIDS? What is expected from the integration?
AUTHORITY: Only integration to the current FIDS. All display content management will be handled through the FIDS.
70) Question: Attachment C, Will the authority provide storage for the hardware required for the 70 ticket counters and 55 gates? Is it acceptable to deliver all at once and deploy additional positions as construction is completed?
AUTHORITY: Please review the proposal. The RFP does not include installing 70 ticket counters and 55 gates. Storage for the equipment needed (17 ticketing counters + 21 gate counters + 1 mobile unit) is the responsibility of the Bidder
71) Question: Attachment C, Please confirm that Level 1 support activities are to be provided by the Authority IT staff.
AUTHORITY: Please reference question 60 and provided response.
12 | P a g e
Title: Common Use Passenger Processing System and Support Services
Part 2. The Authority hereby makes the following revisions and provides the following clarifications:
1. RFP, Instruction to Proposers, article II titled Proposal Submission is hereby revised as follows:
Proposal Documents and all related information shall be submitted electronically via the Authority’s bidding website at www.flylouisvillebids.com by no later than 2:00 p.m. EST on November 19, 2026.
2. Draft Agreement, article XI. Security Requirements, subsection 11.2 is hereby revised in its entirety as follows:
As required by the Authority, the Company shall obtain, at its sole expense, Authority Identification ("Security ID Badge") for each employee that will perform the Services. The need for a Security ID Badge may vary depending on the area in which work will be performed. In addition, the Company shall comply with the Airport security procedures set forth in Attachment E which includes participation in a security training class by each of the Company’s employees assigned to work at the Airport.
3. Node Specifications are hereby incorporated as Attachment C1, in Excel format.
4. RFP, General Conditions, article XI, subsection 11.2 is hereby revised in its entirety as follows:
11.2 The Company shall resolve all service-related issues as quickly as possible, including any third-party problems, without causing unreasonable delays for the Authority.
5. Draft Agreement, article VIII. Confidential Information, subsection 8.3 is hereby revised in its entirety as follows:
8.3 Proposal Documents shall be the property of the Authority, shall constitute works made for hire, of such shall be delivered by the Company to the Authority at no additional cost or expense to the Authority on demand, but in no event later than upon final acceptance, or termination of this Agreement.
13 | P a g e
Title: Common Use Passenger Processing System and Support Services
Part 3. Public Bid opening by way of Zoom via the link below.
Tairra Bridgewaters is inviting you to a scheduled Zoom meeting.
Topic: CUPPS, LRAA RFP-010-27
Time: November 19, 2026 02:00 PM Eastern Time (US and Canada)
Join Zoom Meeting https://us02web.zoom.us/j/88602210218?pwd=LUuMHybrKPhQUM2paDpoNigCugjzac.1
Join and take notes https://us02web.zoom.us/j/88602210218?pwd=LUuMHybrKPhQUM2paDpoNigCugjzac.1 &mynotes=on
Meeting chat link https://us02web.zoom.us/launch/jc/88602210218
Meeting ID: 886 0221 0218 Passcode: 723870
One tap mobile +16468769923,,88602210218# US (New York)
+16469313860,,88602210218# US
Join by SIP
• 88602210218@zoomcrc.com
Join instructions https://us02web.zoom.us/meetings/88602210218/invitations?signature=SVTQgAHsWd8ug EAbfqdNhRn28cRlHinkfpN9MI9MzVM
End of Addendum Two (2)
File details come from the government source that posted it. Updated .