Addendum 2.pdf

PDF 193 KB Posted

Attached to
472/18414. SMD; Lakeland CF - Deaerator Replacement
Solicitation number
RFQ 171 190000000413 3
Issued by
Benzie County, Michigan

About this file

This is a Construction Bid Addendum issued by the Department of Technology, Management and Budget (DTMB), State Facilities Administration Design and Construction Division for the MDOC Lakeland Correctional Facility Deaerator Replacement project (File Number 472/18414.SMD). The addendum was issued on May 17, 2019, with a bid opening date of May 22, 2019. The professional responsible for the project is Matrix Consulting Engineers, Inc., with Scott DeKorte serving as Project Director. The addendum includes three key items: a prebid meeting sign-in sheet, specification clarification regarding Superior Boiler Works, Inc. as an approved deaerator manufacturer pending performance verification, and a material specification requiring chemical feed piping to be Schedule 80 CPVC. All bidders are required to acknowledge this addendum in their bid submission, with failure to do so potentially resulting in bid rejection.

The addendum does not contain pricing information, set-aside provisions, incumbent contractor details, or specific funding sources. The document serves solely as a clarification and modification instrument to the original bidding documents, incorporating interpretations necessary for proper bid submission. Addenda will be distributed through www.michigan.gov/SIGMAVSS and become part of the final contract documents. The addendum was approved by Project Director Scott DeKorte and prepared by Brent Huhn of Matrix Consulting Engineers, Inc.

View the file

Other files

File Type Posted
Drawings 18414_Part2.pdf PDF
Addendum 1.pdf PDF
Specifications 18414 (S).pdf PDF
LEIN Request 18414.pdf PDF
Advertisement 18414.pdf PDF
Specs (MTC Report pgs 110 - 148).pdf PDF
Drawings 18414_Part1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 (Rev 12/17)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration Design and Construction Division

CONSTRUCTION BID ADDENDUM NO. 2

This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.

TO:

ALL BIDDERS

DATE ISSUED

5/17/2019

PROJECT NAME

MDOC Lakeland Correctional Facility – Deaerator Replacement

FILE NUMBER

472/18414.SMD

PROFESSIONAL

Matrix Consulting Engineers, Inc.

PROJECT DIRECTOR

Scott DeKorte

BID OPENING DATE:

5/22/2019

ADDENDUM ITEMS: (attach additional sheets and drawings if required)

1. Prebid meeting sign in sheet (attached)

2. Specification Section 235316 – Deaerator: Superior Boiler Works, Inc is an approved

Deaerator manufacturer pending meeting the performance and specifications.

3. Chemical feed piping to be Schedule 80 CPVC.

ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.

PROFESSIONAL: Brent Huhn, Matrix Consulting Engineers DATE: 5/17/2019

APPROVED BY:

PROJECT DIRECTOR: Scott DeKorte DATE: 5/17/2019

File details come from the government source that posted it. Updated .