Addendum 2- Biltmore Village - rev.pdf
PDF 142 KB Posted
- Attached to
- Biltmore Village Infrastructure Project
- Solicitation number
- 298-FY27-CAM-BiltmoreConst
- Issued by
- Buncombe County, North Carolina
About this file
This Addendum No. 2 to the City of Asheville's Biltmore Village Infrastructure Project (Project Number 298-FY27-CAM-BiltmoreConst) provides responses to bidder questions and updates to project plans and specifications. The addendum addresses clarifications on grading plans, contract documents, grant conditions, base bid structure, conduit inclusions, ABC stone specifications, demolition material ownership, trench drain details, fill dirt and topsoil requirements, brick sidewalk patterns, root bridging, granite curb sourcing, asphalt repair sections, downspout connections, streetlight removal, utility manhole adjustments, project phasing, access requirements, staging areas, NCDOT encroachment agreements, and testing responsibilities. The addendum comprises 60 total pages including 4 pages of answers to questions, 15 plan sheets, and 41 pages of bid form and specifications. Key clarifications include confirmation that HDPE and Schedule 40 conduits are add alternates rather than base bid items, ABC stone depth specifications of 4 inches at sidewalks and 8 inches at driveways, confirmation that demolition materials become contractor property except reusable historic brick and granite curbs, and trench drains quantified as 8-inch-wide linear feet. The City will provide concrete, asphalt, and compaction testing, and will remove streetlights prior to contractor work at intersections. The contractor must develop a phasing plan for owner approval and is responsible for any NCDOT encroachment agreements if work extends into NCDOT right-of-way on Hendersonville Road, Lodge Street, and Brook Street.
The project is funded through grants from the Asheville Tourism Development Authority and the North Carolina Department of Commerce Rural Economic Development Small Business Infrastructure Grant, with no federal provisions or requirements for Davis-Bacon, Build America Buy America, HUB participation, or good-faith-effort forms. Work associated with Swan Street, Kitchin Place, Boston Way, and Biltmore Plaza crosswalk improvements must be segregated into four sections on pay applications for billing against appropriate grants. Temporary staging space in on-street parking areas is permitted with prior approval as part of the phasing plan. The contract requires acknowledgment of this addendum in the submittal; failure to do so may result in the bid being deemed non-responsive.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| POSTED Addendum 1- Biltmore Village 10-22-26.pdf | ||
| POSTED Biltmore Village Advertisement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum No. 2 Issue Date:
Project Name:
Project Number: 298-FY27-CAM-BiltmoreConst
TO: Prospective Applicants
ThisaddendumformsapartoftheRequestforBidsandmodifiestheoriginalProjectNumber 298-FY27-CAM-BiltmoreConst only to the extent specifically noted below. Failure to acknowledge this addendum in the submittal may subject the submitter to being deemed non-responsive.
ThisAddendumispostedontheCityprocurementwebsiteatwww.ashevillenc.gov/bids. This istheofficialsourceofthisaddendum. Alladdendaandattachmentsshallbepublishedtothe same location.
ThisAddendumconsistsof4pagesofAnswerstoQuestions,15plansheets,41pagesof the bid form and specifications. This is 60 pages total.
This Addendum is to address Responses to Questions and make minor updates to plans
Answers to Questions Question: The Grading Plan was noted “to be addedwith first addendum” but was not included in Addendum No. 1.Answer:G-1 is included in thisissuance.
Question:TheDraft Contract Documents were notedto be posted with Addendum 1, but were not included. (Please issue the contract, General and Supplementary Conditions, insurance requirements, retainage, contract duration, and liquidated damages before the bid date,) and advise the anticipated Notice to Proceed date supporting the January 4, 2027 construction start.
Answer: Draft contract documents are now provided.NTP will be issued immediately after the construction contract is approved by council and has all COA and contractor signatures.
Question:Please identify the grant conditions thatflow down to the Contractor, including any HUB participation, required good-faith-effort forms, certifications, reporting, and whether any federal funds apply that would invoke Davis-Bacon, Build America Buy America, or other federal provisions.Answer:The grants involved in this projectare through the Asheville Tourism Development Authority and the NC Department of Commerce Rural Economic Development Small Business Infrastructure Grant. There are no requirements regarding any of the aforementioned items. On each pay application, the work associated with Swan Street, Kitchin Place, Boston Way and Biltmore Plaza crosswalk improvements shall be broken out into 4 sections so they can be billed accordingly against the appropriate grant. No federal provisions apply to this recovery project.
page1of4 http://www.ashevillenc.gov/bids
Question: Please confirm the Base Bid in 8.1 is to equal the Total Bid of the 8.3 unit price schedule, including the $20,000 allowance.Answer:Confirmed.
Question: Are the HDPE and Schedule 40 conduit includedin the Base Bid or are both priced as adds? Answer: The HDPE and Schedule 40 conduits are not part of the base bid. Each is an add alternate. Note there is a revised bid form attached incorporating changes below.
Question:ABC stone please clarify and update crossreferences. Answer: a.) ABC depth at sidewalks is 4” b.)ABC at driveways is 8” c.)bid quantity has been updated d.) It is confirmed that ABC beneath sidewalks, aprons, and ramps is paid under Item 17. e.)ABC beneath the granite curb has been removed from the scope of work and replaced with a concrete footer, now Item 11b.
Question:Regarding removing and stockpiling existinggranite curb and bricks, please confirm which materials remain City property, which are salvaged and stockpiled and which is to be disposed of. Answer:All demolition materials becomethe Contractor’s property except for the reusable historic brick and reusable granite curbs (which will be salvaged and stockpiled).
Marble markers will become contractor’s property and are incidental to Line 5. Bid form and Section 4 have been updated.
Question:Trench Drain Detail: Item 22 carries TrenchDrains as 110 EA, while Line 22 provides payment per linear foot. Please clarify. The detail notes the trench width “varies – see chart,” and no chart is included.Answer:Trench drainsare to be 8” wide and quantified as linear foot. Bid form and detail have been updated.
Question:Bid Item 20; Section 3, Line 20; Sheet S-1,General Note 13: Item 20 is titled “Fill Dirt – Topsoil” (1 LS), while Line 20 addresses fill dirt only. Please confirm whether this item includes topsoil for tree strips, and provide an estimated quantity of each.Answer: Fill dirt is for areas where concrete and stone base are being changed to landscape areas with grass as well as backfill to sidewalks that had adjusted cross slopes. 1” of topsoil raked in new landscape areas (previously concrete, brick or stone).
Question:Brick Sidewalks, clarify contradictory notesand detail information regarding salvaged and new brick. Answer: Plans now indicate both runningbond and herringbone brick areas are to be a mix of salvaged and new brick. Brick Patterns detail updated on sheet D3.
Question:Please confirm root bridging without concretebase is not included in line item 13.
Please confirm the pay item for hand or air spade excavation.Answer:Root bridging and air spade now has their own line items. Quantities of subslab concrete for not occurring in the root bridging area have been deducted from line item 13.
Question:Section 3, Line 11; Sheet S-1, General Note8: Line 11 defines new granite curb as stockpiled curb from this project or from the Beaucatcher Reservoir stockpile, and Note 8 directs the Contractor to work with the Landscape Architect to source additional historic curb if required.
Please confirm the quantity, profile, and condition of curb available at Beaucatcher, including radius and corner pieces, and how additional curb will be furnished and paid if the stockpiles cannot supply them.Answer:Curb removal, purchasingand replacement have been better defined as well as line items added. If the stockpile at Beaucatcher cannot supply the granite needed for the project, newly purchased granite shall follow specification for granite curb that is
2of4 now included under specifications.
Question: Bid Item 9; Sheet D3, Section AA: Line9 describes B25.0B base and 2” S9.5B surface over 8” compacted stone, paid per ton of base course, while Section AA shows 2” S9.5B over 2” B25.0B. Please confirm the asphalt repair section and stone depth, and whether the 36 TON in Item 9 includes both mixes.Answer:Road repair section is a total of 4” asphalt and 8” CABC.
Question:Sheet S-1, General Note 12 and plan callouts: All downspouts are to connect to trench drains discharging through the face of curb. Please confirm the number of downspout connections, whether granite curb is to be cored, and responsibility for connection work on private downspouts. Answer:Currently there are 10downspout connections. Contractor is responsible for reattaching currently connected downspouts. Granite curb is to have a space between curbs to allow for trench drain.
Question:Addendum No. 1 removes street light removal,storage, and reinstallation from the scope. Please confirm Item 33 is deleted from the Bid Form, and whether the lights the layout plans show as “removed, stored, reinstalled at shifted location” at the new ramps will now be protected in place by the Contractor or relocated by the City before construction.Answer:
Streetlight removal, storage and reinstallation is now deleted from the Bid Form and notes on the plan have been updated. At intersections where street lights were previously indicated as to be removed, the City of Asheville will remove the street lights prior to contractors work.
Question:Bid Item 35; Section 3, Line 35; Sheet S-1,General Note 3 and plan callouts: Item 35 (5 EA) addresses manholes, while Note 3 requires all utilities and structures to be adjusted to match adjusted elevations and the plans call out water and utility meters to be adjusted flush with the brick surface. Please confirm the total count of structures and boxes to be adjusted under Item 35, and whether Asheville Water Resources performs any meter work.Answer: It is anticipated that there will be minor adjustments to the two existing utility manhole lids and one small water valve lid. The manhole lids are now a separate line item from the one small water valve lid which is incidental to the brick sidewalk work.
Question:Advertisement, Description of Work; Section4, Day and Time Restrictions: The City is to provide initial phasing and sequencing. Please issue the bid phasing plan, including phase limits, maximum concurrent work areas, anticipated duration, any event restrictions beyond the working-hour and holiday limits in Section 4, and known parcel-owner time restrictions.Answer:
The contractor is to provide a phasing plan for approval by owner.
Question:Sheet EX-3, General Access Notes; Section3, Line 3 and Special Provisions Introduction: Continuous access to walks, drives, and business entries is required during replacement of those same walks, and lanes on Hendersonville Road and Brook Street may not be closed or narrowed for concrete delivery. Please confirm permissible temporary closures and notice periods, permissible truck and pump locations along those frontages, and whether the shuttle service listed in Line 3 is required.Answer: Temporary closure and notice periods will be developed along with the phasing plan.
Question:Section 4, Remove and Stockpile: Section4 directs granite curb to be stockpiled on the right-of-way and brick in a laydown area. Please identify the laydown area and the extent of
3of4 right-of-way storage permitted, and whether on-street parking may be used for staging.
Answer: Temporary staging space in the on streetparking areas will be permitted, with prior approval, as part of the phasing plan. On street parking in the prescribed area may be used for storage and laydown space.
Question:Please confirm whether the City will obtainany required NCDOT encroachment agreement for work on Hendersonville Road, Lodge Street, and Brook Street?Answer:If the contractor anticipates encroachment in the NCDOT ROW, he is responsible for any encroachment agreements.
Question: Will the City will provide concrete andcompaction and asphalt testing?
Answer: The City will provide testing for concrete,asphalt and compaction.
I understand that failure to acknowledge any addenda may cause this bid/proposal to be deemed non-responsive.
Authorized Signature Company Date
- End -