Addendum 2 Ashland Water Treatment Plant - Offsite Facilities.pdf

PDF 476 KB Posted

Attached to
City of Ashland, Water Treatment Plant - Offsite Facilities
Solicitation number
S-KA0010-00013815
Issued by
Jackson County, Amity City, Oregon

About this file

Addendum No. 2 is a supplemental document for the City of Ashland's Water Treatment Plant - Offsite Facilities project, issued on June 2, 2025. The addendum provides clarifications and modifications to the original bid documents, including updates to the Bid Form, Agreement, and various specification sections. Key changes include a new bid item for rock excavation, clarification on milestone dates (with Milestone 1 for Culvert and In-Water Work set for September 30, 2025), and responses to 27 contractor questions covering topics such as electrical tie-ins, turbidity monitoring, handrail specifications, and staging areas.

The addendum introduces a $100,000 Contingency Allowance and provides detailed guidance on its use, emphasizing that only the Owner can authorize allowance expenditures. The document specifies that the Contractor must provide third-party material testing, quality control, and special inspections, which will be considered incidental to the bid items. Additional clarifications include requirements for temporary work zone fencing, trail head access, and specific technical details about project components such as conduit installation, cable handrail specifications, and utility connections. The addendum does not fundamentally alter the project's scope but provides critical refinements to ensure clarity and precision in the bidding and execution process.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum No. 2 6/02/2025

TO: ALL HOLDERS OF CONTRACT DOCUMENTS FOR:

City of Ashland Water Treatment Plant – Offsite Facilities

The following Addendum shall be incorporated into the Contract Documents for the above referenced project.

ADDENDUM NUMBER TWO (2)

GENERAL

No changes for this addendum.

DRAWINGS

No changes for this addendum.

SPECIFICATIONS

Section 00 41 13: Bid Form

Replace table in 3.01.A with the following table.

Item No.

Description Unit Estimated Quantity

Bid Unit Price

Bid Amount

Unit Price Bid Items

1 Mobilization/Demobilization 1 LS $ $

2 Site Work, Grading and Road Construction

1 LS $ $

3 Erosion and Sediment Control 1 LS $ $

4 Landscaping 1 LS $ $

5 Bridge, Culvert and Streambed Improvements at Creek Crossing

1 LS $ $

6 24-inch Storm Drain Pipe, Manholes and Appurtenances

1 LS $ $

7 8-inch PVC, 16-inch DI, and 24-inch DI Pipe, Fittings, Valves and Appurtenances

1 LS $ $

8 8-inch Sewer Pipe, Manholes and Appurtenances

1 LS $ $

9 Direct Buried Electrical Ductbank, Fittings and Appurtenances

1 LS $ $

10 Fiber Optic Conduit, Fittings and Appurtenances

1 LS $ $

11 Rock Excavation 300 CY $ $

Total of All Unit Price Bid Items $

Allowances

A1 Contingency Allowance 1 LS $100,000 $100,000

Total of All Unit Price Bid Items + Allowances $

Section 00 52 13: Agreement

Replace 3.3.A as follows:

a. Milestone 1 – Completion of Culvert and In-Water Work: September 30, 2025

Add attached Section 01 21 00: Allowances in its entirety.

Section 01 22 10: Measurement and Payment

Delete 1.5.1 Renumber 1.5.B as 1.5.A.

Renumber 1.5.A through 1.5.I as 1.5.B through 1.5.J.

Add item 1.5.K as follows:

K. Item 11 – Rock Excavation:

1. Measurement: Limits of rock removal eligible for payment are as follows:

a. Buildings and Structures: Payment limits for all buildings and structures are:

i. Pre-construction rock surface, as determined in accordance with Engineer.

ii. Bottom of footing. Where under-slab piping or trench drains extend below the horizontal plane indicated in this paragraph, rock removal for such piping or trench drains shall be in accordance with this provision’s measurement limits for trenches.

iii. Vertical planes located 12 inches outside footing.

b. Trenches: Payment limits are:

i. Pre-construction rock surface, as determined in accordance with Engineer.

ii. Width of trenches shall be the outside diameter or outside edge (as applicable) of the Underground Facility plus 2 feet, exclusive of pipe bells, branches, hubs, spurs, and cradles.

Sides of trench shall be considered vertical.

iii. Depth of trench shall be a minimum of six inches below outside bottom of Underground Facility in the trench (excluding bells, hubs, and the like), unless shown or indicated otherwise on the Drawings.

iv. Length shall be equal to installed length of the Underground Facility, measured horizontally.

c. Rock removal where pay limits are not otherwise shown or indicated but required for the Work will be measured to lines directed or approved by Engineer, from pre-construction rock surface, as determined in accordance with Engineer.

d. No payment will be made for additional quantity outside the limits described in this Section.

2. Item includes (all in accordance with the Contract Documents):

a. Obtaining necessary and required permits and approvals.

b. Pre-blast surveys, or equivalent when explosives are not used.

c. Establishing magazine, magazine management, and handling of explosives, when used.

d. Loosening and removing rock by Contractor’s means and methods, in accordance with the Contract Documents.

e. Excavating, handling and proper disposal of excavated or removed material.

f. Remedy of damage to property and facilities caused by rock removal operations.

g. Other work, services, and materials required and necessary for rock removal not expressly included under other bid/pay items.

3. Not included in this bid/pay item:

a. Work expressly included under other bid/pay items.

4. Payment: Unit price per cubic yard for this item will be full compensation for all rock removal complete as shown or indicated in the Contract Documents, or directed by Engineer for the rock removal pay limits indicated and not specifically included under other bid/pay items or contracts.

Add item 1.5.L as follows:

L. Item A1 – Contingency Allowance:

1. Measurement: As indicated in the Agreement and Section 01 21 00 - Allowances, the Contract includes in this item a stipulated amount available as reserve for sole use by Owner, for costs authorized by Owner during construction, for Work not included under other bid/pay items.

2. Payment: Payment for Work authorized in accordance with Section 01 21 00 - Allowances, and performed under this item will be full compensation for providing all Work authorized under this allowance, complete as shown, indicated, or directed by Engineer in accordance with the associated allowance authorizations.

Section 40 05 51: Valves – Basic Requirements

Replace 3.3.A as follows:

A. There are no actuated valves. See Drawings for manual valves.

Delete table after 3.3.A.

CONTRACTOR QUESTIONS AND STATEMENTS MADE PRIOR TO BID

1. What are the coating requirements for the cable handrail shown on Sheets C104 and C105?

See Spec Section 05 52 02, Item 2.3.D.

D. Finish:

1. Architectural Class 1 coating per AA DAF 45:

a. AA-M12C22A41 clear anodized, throughout, except as noted. AA-M12C22A42 dark bronze anodized; at culvert crossing only.

2. Does Contractor need to supply an office trailer, maintain a website and use P6 for their CPM schedule?

Contractor’s office trailer as specified in Specification Section 01 30 00 Item

1.5 is not required but can be furnished if desired by Contractor. The Project Website as specified in Specification Section 01 30 00 Item 1.4.B.8 will not be required as long as Contractor provides an alternative electronic platform such as Procore or other as approved by Engineer that can be used for electronic transmission, exchange and archiving of project documents. CPM schedule does not have to be in P6 format but may be developed using other commercially available scheduling software such as MS Project or similar as long as the software meets the requirements of Section 01 32 16. Use of spreadsheets, such as MS Excel or Google Sheets, is not acceptable.

3. Is there a profile or a minimum bury depth for the 16” waterline between STA 109+00 and Glenview Drive?

Minimum bury depth shall be 4’-0”. Similar to Section F, Sheet 002C107 but for the 16-PWG only.

4. With in water work (June 15 – September 30) conflicting with fire season, please clarify when access to Horn Creek Road can be cut off to complete the work in the creek (remove existing culvert and install new structure).

Contractor shall maintain access to Horn Creek Road at all times during construction. Contractor shall develop a plan for providing temporary access to Horn Creek Road during construction and provide to Owner and Engineer for review and approval. A Contingency Allowance has been added to the project that will be used to pay for all work associated with providing temporary access to Horn Creek Road during construction.

5. Are there any permits that the Contractor will be responsible for obtaining for this project?

Contractor to obtain applicable City of Ashland permits. Permits may include but not be limited to the following:

Building: Commercial Electrical Building: Commercial Grading/Excavation Building: Structural Permit Public Works: Misc. Concrete Permit Public Works: Right-of-Way Permit Public Works: Street/Alley Excavation Permit Public Works: Dust Suppressant Permit Public Works: Encroachment Permit

Refer to City of Ashland website for additional information.

6. Is a geotechnical report available for review?

Yes. A geotechnical report is available and will be added to the Oregon Buys website where it can be downloaded.

7. Is a stamped water management plan from the Contractor required?

Yes, see Specifications Section 35 10 00 and refer to Items 1.3.C and 1.4.A.1.

8. Please confirm that the 24” RW pipe is the only water line to be connected to the existing, all others will be capped?

Correct. Tie-in of the 24” RW will be completed as part of the project. No other connections are required. Removal of the bypass and bypass valve as noted in Keyed Note 1 on Sheet 002C101 will not be required. Keyed Note 1 shall be revised as follows:

TEMPORARY FINISHED WATER TO NEW WTP RW PIPELINE

BYPASS AND BYPASS VALVE REQUIRED TO PROVIDE WATER

TO NEW WTP FOR STARTUP AND COMMISSIONING.

9. Would Ductile Iron Pipe be considered in place of RCP for the storm drain pipes?

Storm drain pipes shall be RCP and ductile iron pipe will not be allowed.

10. Will the 600A sectionalizer and all conductors be provided and installed by Ashland Power?

Correct. Ashland Electric will furnish and install the 600A sectionalizing cabinet. Conductors will be installed by Ashland Electric as part of the future WTP project.

11. Provide additional clarification for electrical tie-ins.

a. Primary by City of Ashland? Contractor to install conduits, pullboxes and pad for sectionalizer cabinet per Ashland Electric requirements.

b. Secondary (e.g., chases, conduit, setting up transformers) by Contractor? No secondary on this project, only primary. Secondary from transformer to be installed in future as part of WTP project, by Contractor.

c. Fiber? Conduits to be installed up to pullbox as shown on the drawings. Fiber to be installed at a later time by Ashland Fiber (the City).

12. Has a Staging Area been identified?

City may allow the future WTP site location and parking lot next to the Granite Street Reservoir as area for Contractor staging. Contractor to coordinate with City to confirm.

13. Will turbidity monitoring be required?

Yes, see Specification Section 35 10 00 and State of Oregon Standard Specification 00290.30(a)(8)

14. The specifications and the description of the pay items mention geotextile fabric but none is shown on the typical section or elsewhere in the plans. Is geotextile fabric required on the road?

Geotextile fabric is not required for the road however it is mentioned elsewhere in the plans and part of state referenced details.

15. Please clarify if the contractor is not required to provide any material testing, quality control, or inspections for the project?

Contractor shall provide services of a third party to complete all material testing, quality assurance/quality control and special inspections required for the project. This work shall be considered incidental to the various bid items to which it pertains.

16. Are there any temporary work zone fencing requirements to keep the public out of the work zone?

Yes. Fencing will be required to isolate Granite Street from the work zone.

This will be considered incidental to the project.

17. Are there any requirements to maintain access to trail heads on the west side of the creek while the culvert is being replaced or during utility installations? Any signage or notifications required for closures?

City of Ashland will coordinate access to trail heads during completion of the project.

18. In regard to the handrail, how are the cables to be installed, drilled through or attached to the face? What does hand tight for the cable mean, typically a turn buckle is used to put tension on the cable?

Cable infill is attached to end posts using tension fittings that are to be hand tensioned. Line posts are drilled through.

19. Is hard rock excavation to be incidental to excavation and pipe installations?

A new bid item for rock excavation has been added. See revised bid form included in this addendum.

20. Please confirm there is no Asphalt Paving included in this project, aside from any trench resurfacing of existing asphalt?

Correct. Asphalt will only be required for trench repair and no other asphalt paving is included in the project.

21. Does the contractor need to provide any project signage or photographic documentations as detailed in section 01 30 00?

Yes. Project signs shall be provided as specified in Specification Section 01 30 00 Item 1.4. Photographic documentation shall be provided as specified in Specification Section 01 30 00 Item 1.6

22. Plan sheet 001C205 note 15 references detail E (001C100) for details regarding a

Rip Rap channel, however that detail is not on that sheet or elsewhere in the project plans. Can you please provide that detail?

See Detail E below.

23. For the electrical and fiber conduit, would directional drilling be an acceptable method of installation in some or all areas?

Installation of electrical and fiber conduit shall be per the requirements included in Spec Section 31 23 33. See Item 3.2.D for reference.

24. For the handrail, is 2” pipe for the railing or 1.5” required?

The minimum nominal diameter is 1.5”, the maximum nominal diameter is 2”.

Size, spacing, etc. within these limits is determined according to the loading and geometric requirements of the building code as illustrated in the calculations to be submitted per the specifications.

25. For the handrail, the posts are called out to be sch. 80 of the same size as above.

The OD will be slightly larger than the top rail and mid rail. Does that matter?

Outside diameter would remain constant between Sch. 40 and Sch. 80 of the same nominal pipe size. If different nominal pipe sizes are used for handrail and posts, connection details and design should be considered in the shop drawings and calculations submittals per the specifications.

26. For the handrail, can you confirm that the railing drawings on C104 and C105 are drawn to scale of 1” =10’? When scaled roughly 68’ total for both sides. But the drawings show a post spacing of 3’ and when added up with the post spacing it’s more like 90 feet total.

The contract plans are drawn to scale but are not intended to reflect the final configuration of the handrail. The minimum length of handrail is determined by the locations along the walls where the exposed wall height is a maximum of 4ft. The 3ft post spacing shown on Sheet 000C105 is a maximum and post placement should consider exposed wall height, clearance to wall joints, and angles in the wall alignment. These considerations should be reflected in the shop drawings per the specifications.

27. For the base plate thickness, would 1/4" be acceptable?

Specifications require a minimum of 3/8”x6”x6” plate for mounting to concrete but must be designed to resist building code design loads and accommodate the designed anchorage system.

HDR Project No. 10193663 City of Ashland May 5, 2025

Ashland Creek WTP - Offsite Facilities Final Design

ALLOWANCES

01 21 00 - 1

SECTION 01 21 00

ALLOWANCES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Administrative and procedural requirements for:

a . Contingency allowances.

B. Related Requirements:

1. Include but are not necessarily limited to the following:

a . Section 01 26 00 - Contract Modification Procedures.

b. Section 01 29 73 - Schedule of Values.

c. Section 01 32 16 - Construction Progress Schedule.

1.2 REFERENCES

A. Terminology:

1. Terminology indicated below are not defined terms and are not indicated with initial capital letters, but when used in this section have the following meanings:

a . “Allowance authorization” or “authorization”, whether singular or plural, are Owner’s written and signed approval for using a specific allowance item, in a specific authorized amount, for a specific construction task or activity. Allowance authorizations include all associated attachments at the time of Owner’s signature and as delivered to

Contractor.

b. “Contingency allowance” is a stipulated amount included in the Contract Price, controlled by Owner, for Owner’s sole use to cover unanticipated costs and costs for

Work authorized by Owner that is not part of any other bid/pay item in the Contract.

1.3 ALLOWANCES – GENERAL

A. This Article applies to all allowance types and all authorized allowance Work performed in accordance with the Contract Documents.

B. All allowances in the Contract are Owner-controlled and for Owner’s sole use. Contractor has no right or entitlement to any allowance or part thereof without express, written authorization from Owner.

C. Authorization of Allowances:

1. Only Owner can authorize use of an allowance. No other entity, including Engineer, Resident Project Representative (RPR, if any), Owner’s Site Representative (OSR, if any), or others may authorize use of allowances in place of Owner.

2. Allowance Authorization Mechanism:

a. To be binding and enforceable, allowance authorizations must be in writing, signed by one of the Owner’s employees indicated immediately above.

b. Allowance authorization form is attached to this Section.

c. Allowance authorizations issued in accordance with the procedures set forth in this

Section, are binding and enforceable under the Contract, unless promptly contested in writing by Contractor in accordance with this Section.

d. Oral authorizations, authorizations without an appropriate signature, and authorizations not on the proper form, will not be binding or enforceable.

3. Allowance authorizations duly signed by Owner’s authorized person may be delivered to

Contractor by Engineer, RPR, OSR, or other Owner-authorized representative, and shall be binding and enforceable when so delivered (unless properly contested).

ALLOWANCES

01 21 00 - 2

4. Do not perform Work presumed for compensation under an allowance without first obtaining Owner’s allowance authorization.

5. Work presumed by Contractor to be under an allowance and performed without: (a) written authorization duly signed by Owner, or (b) Change Order, or (c) Work Change Directive, is not be eligible for payment.

D. Contract Times:

1. Allowance authorizations do not have any effect on, and do not change, the Contract Times.

The Contract Times can be changed only via a duly authorized Change Order.

2. Should the Work included in an allowance authorization adversely affect Contractor’s ability to comply with the Contract Times, promptly submit Change Proposal (including appropriate supporting documentation), in accordance with the Contract Documents, indicating the associated, specific, proposed effect on each of the Contract Times.

E. Payment for Work Under an Allowance Authorization:

1. Work duly authorized by Owner under an allowance is eligible for payment upon performance of the associated Work, in accordance with the Contract Documents and the associated allowance authorization.

2. When applying for payment for Work under an allowance authorization, the Application for

Payment shall include a copy of the associated allowance authorization(s) signed by Owner.

3. When requested by Owner or Engineer, amend the Schedule of Values to indicate Work authorized under contingency allowances or cash allowances.

F. Compensation for Bonds and Insurance:

1. Contractor is not eligible for compensation under an allowance, or for an increase in the

Contract Price, for costs associated with insurance, performance bond, payment bond , or warranty bond (when such bond is required by the Contract). Compensation for such costs is included elsewhere in the Contract Price, under other (non-allowance) bid/pay items.

G. Change Orders:

1. A Change Order is not required for authorization of an allowance that is already included in the Contract.

2. Prior to final payment, all allowances with funds remaining (not yet authorized) shall be reduced to the total amount authorized by Owner for that allowance item, via a Change Order.

1.4 CONTINGENCY ALLOWANCES

A. Provisions on contingency allowance(s) are set forth in the General Conditions, as m ay be modified by the Supplementary Conditions, and in this Section.

B. Owner may authorize use of all or part of a contingency allowance included in the Contract for Work not otherwise covered under one or more other bid/pay items already in the Contract.

C. Procedure for Using Contingency Allowances:

1. Prior to Work being authorized under a contingency allowance, Contractor shall submit complete Change Proposal for the associated Work, in accordance with the Contract

Documents.

2. Compensation proposed via the Change Proposal for the contemplated allowance Work shall be complete and sufficient for the entire scope of the contemplated allowance Work, unless expressly indicated otherwise in the Change Proposal or an associated, Owner- or Engineer-issued Proposal Request.

3. Compensation eligible under a contingency allowance includes:

a . Materials and equipment furnished to Owner or incorporated into the Work; labor;

construction equipment and machinery; services, incidentals, and related costs, in accordance with the Contract Documents’ provisions for Contract modifications.

b. Overhead and profit for the associated Work, for Contractor and Subcontractors.

c. Other costs and expense mutually agreeable to Owner and Contractor.

ALLOWANCES

01 21 00 - 3

4. Excluded are costs not mutually agreeable to the parties and costs excluded in accordance with Article 1.3 of this Section.

5. Should Change Proposal indicate, and Owner accept that, change in the Contract Times is necessary, Owner (or Engineer, on Owner’s behalf) will issue an appropriate Change Order for signature by the parties, upon mutual agreement to the changed Contract Times.

6. Upon receipt of contingency allowance authorization, when Contractor does not reject or disagree with the authorization, Contractor shall sign allowance authorization form indicating acceptance and return signed form to Owner and Engineer within two days of receipt.

7. Commence performing the allowance Work promptly upon receipt of allowance authorization.

8. Application for Payment for the associated Work may be made in accordance with Article

1.3 of this Section and the Contract’s provisions governing progress payments.

PART 2 - PRODUCTS - (NOT USED)

PART 3 - EXECUTION

3.1 ATTACHMENTS

A. The following, bound after this Specifications Section’s “End of Section” designation, are part of this Specifications Section:

1. Forms:

a . Allowance Authorization Form, (one page).

END OF SECTION

ALLOWANCES

01 21 00 - 4

ALLOWANCE AUTHORIZATION

Project: Authorization Number:

From:

To: Date:

Engineer Project No.:

Re: Contract For:

Contractor is authorized to perform the following item(s) of Work and to be eligible to apply for payment under the designated Contract allowance(s) indicated below for the amount indicated below for each item:

1. [Allowance Title] / [Title of Change]:

This instrument is not a Change Order and does not modify the Contract Price, nor does it modify the

Contract Times.

Original Allowance ..................................................................................................................... $

Allowance Expenditures prior to this Authorization ................................................................ $

Allowance Balance prior to this Authorization......................................................................... $

Allowance will be decreased by this Authorization.................................................................. $

New Allowance Balance............................................................................................................. $

RECOMMENDED BY OWNER APPROVAL

HDR

Engineer Owner

By Date By Date

CONTRACTOR ACCEPTANCE

Contractor

By Date

☐ Attachments

Copies: ☐ Owner ☐ Contractor ☐ Consultants ☐ ☐ ☐ ☐ File