Addendum #2_10.21.2026.pdf
PDF 1 MB Posted
- Attached to
- WQIF Constructed Wetlands BMP
- Solicitation number
- IFB-128812
- Issued by
- York County, Virginia
About this file
This addendum to the Invitation for Bid for the WQIF Constructed Wetlands BMP project issued by the City of Waynesboro, Virginia, provides clarifications and supplemental information for the construction of a constructed wetlands best management practice and extended detention pond retrofit at Ridgeview Park. The project requires site clearing, earthwork, concrete work, drainage piping, soil preparation, erosion and sediment control, and plant installation, with a contract duration of 240 days for substantial completion and 270 days for final completion following the Notice to Proceed. Sealed bids are due by 2:00 p.m. on November 16, 2026, with public opening to follow at 503 West Main Street, Waynesboro, VA 22980. Site visits must be scheduled through Jennifer Allen-Key at Allen-KeyJL@ci.waynesboro.va.us. A non-mandatory pre-bid conference was held on October 19, 2026, at 10:00 a.m., with six general contractors in attendance, including LUCACI Inc., Valley Sitework, Harbor Civil & Marine, Premier Group Limited, and Triangle Contracting LLC. The contract will be awarded on a lump sum basis with bids remaining open for 60 days following bid opening.
The project requires a 5% bid bond and standard performance and labor/material payment bonds upon award. A 5% retainage is applied to all partial payments, with liquidated damages set at $250 per day for schedule delays. Bidders must hold a valid Virginia contractor's license and submit proof of authority to transact business in Virginia with their bids, along with an EJCDC C-410 Bid Form and a Bidder's Qualification Statement. Insurance requirements in Specifications C-700 and C-800, including Builder's Risk, override minimum IFB requirements. The site is located adjacent to an elementary school with standard working hours of 8:00 a.m. to 5:00 p.m. Monday through Friday, though flexibility exists for 7:00 a.m. to 4:00 p.m. or Saturday work with coordination. The contractor must secure the Construction General Permit (VAR10) and maintain a Stormwater Pollution Prevention Plan, construct temporary site fencing (but not permanent fencing), and is responsible for temporary electrical service and sanitary facilities. The site encompasses approximately 4,700 cubic yards of net cut (based on 1.12 fill factor and 1.00 cut factor), with articulated concrete blocks required to withstand 13 feet per second peak velocity. Tree removal is restricted April 1 through November 14 due to bat habitat concerns, and CADD drawings will be available only to the winning bidder.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 1.pdf | ||
| eVA - how to respond electronically.pdf | ||
| WQIF IFB FINAL_10.01.2026.pdf | ||
| Final Plan_Stamped.pdf | ||
| 250045_WQIF_SPEC_IFB.pdf | ||
| Business license application and instructions .pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
October 21, 2026
WQIF Constructed Wetlands BMP IFB
ADDENDUM #2
Question 1: What is the project contract duration/estimated number of days for substantial completion?
Answer 1: 240 days.
Question 2: Are there liquidated damages and if so, how much are they?
Answer 2: $250/day.
Question 3: Do the insurance requirements in the Specifications override the minimum insurance requirements in the IFB? Specifically, the Builder’s Risk required for the project?
Answer 3: The specifications, C-700 and C-800 override the minimum requirements in the IFB, which includes the Builder’s Risk requirement.
Question 4: Please confirm the EJCDC C-410 Bid Form (and noted requirement documents) is required with bid submission in addition to the IFB Bid Form and Bid Schedule?
Answer 4: Yes.
Question 5: Please confirm if there is a specific Bidder's Qualification Statement form required with the bid submission. The document was not provided in the bidding documents.
Answer 5: Posted to eVA with this addendum.
Question 6: The IFB Supplemental General Conditions 2.2.17 references the Agreement (Contract) in Exhibit A, which is not attached. Can this document be provided, and can contract times be provided?
Answer 6: The reference to Exhibit A should be disregarded.
Question 7: What is the retainage percent for the project?
Answer 7: 5%.
Question 8: Are CADD drawings available?
Answer 8: The drawings will be available to the winning bidder.
Question 9: Confirm the required block size, thickness, and cable requirements.
Answer 9: The specification is not provided to allow the contractor flexibility in the ACB system selection. The ACB must withstand 13 feet per second peak velocity and be opened celled.
Question 10: What is the cut/fill balance on the site?
Answer 10: The site is 4700 CY net cut (assuming 1.12 fill factor and 1.00 cut factor).
Question 11: Is there flexibility on the standard working time (8 AM to 5 PM)?
Answer 11: Yes, 7 AM to 4 PM is an option as is working on Saturdays. Other times may be possible through coordination with the City of Waynesboro. This site is adjacent to an elementary school, so the contractor should be careful to not impede traffic at the school.
Question 12: Is construction fence required around the perimeter of the site?
Answer 12: Yes.
Question 13: Is permanent fence required around the perimeter of the site?
Answer 13: No.
Question 14: ECJDC C-800 SC-5.03.F. references Landfill Gas Collection System drawings. Are these drawings relevant to this project, and if so, can these drawings be provided to bidders for review?
Answer 14: No, these drawings are not relevant to this project and will not be provided.
Question 15: Do site visits need to be scheduled with the City?
Answer 15: Site visits must be scheduled through Jennifer Allen-Key, Allen- KeyJL@ci.waynesboro.va.us
Question 16: Does the contractor need to secure environmental permitting?
Answer 16: The contractor needs to obtain the Construction General Permit (VAR10) and maintain the Stormwater Pollution Prevention Plan (SWPPP).
mailto:Allen-KeyJL@ci.waynesboro.va.us mailto:Allen-KeyJL@ci.waynesboro.va.us
Proof Of Authority To Transact Business In Virginia
THIS FORM MUST BE SUBMITTED WITH YOUR BID. FAILURE TO INCLUDE THIS
FORM MAY RESULT IN REJECTION OF YOUR BID
Pursuant to Virginia Code §2.2-4311.2, a Bidder organized or authorized to transact business in the Commonwealth pursuant to Title 13.1 or Title 50 of the Code of Virginia shall include in its bid the identification number issued to it by the State
Corporation Commission (“SCC”). Any Bidder that is not required to be authorized to transact business in the Commonwealth as a foreign business entity under Title 13.1 or Title 50 of the Code of Virginia or as otherwise required by law shall attach to this form a statement describing why the Bidder is not required to be so authorized. Any Bidder described herein that fails to provide the required information shall not receive an award unless a waiver of this requirement is granted by the SCC.
If this quote for goods or services is accepted by the City of Waynesboro, Virginia, the undersigned agrees that the requirements of the Code of Virginia Section 2.2-4311.2 have been met.
Please complete the following by checking the appropriate line that applies and providing the requested information.
A._____ Bidder is a Virginia business entity organized and authorized to transact business in Virginia by the SCC and such vendor’s Identification Number issued to it by the SCC is: __________________
B._____ Bidder is an out-of-state (foreign) business entity that is authorized to transact business in Virginia by the SCC and such vendor’s Identification Number issued to it by the SCC is __________________
C._____ Bidder has applied for, but has not yet received, an Identification Number from the SCC and requests that it be granted an extension of five calendar days to provide its Identification Number to the City’s Purchasing Division.
D._____ Bidder does not have an Identification Number issued to it by the SCC and is not required to be authorized to transact business in Virginia in accordance with Section(s) of the Code of Virginia and the reasons stated on the attached document(s).
Please attach additional sheets if you need to explain why such Bidder is not required to be authorized to transact business in Virginia.
Legal Name of Company (as registered to do business and in agreement with IRS FEIN/TIN designation letter)
Legal Name of Authorized Representative for Bidder
Title of Authorized Representative for Bidder
Signature of Authorized Representative for Bidder Date
100% Employee-Owned | wileywilson.com
127 Nationwide Drive | Lynchburg, VA 24502 | 434.947.1901
Pre-Bid Conference Agenda
PROJECT: WQIF Constructed Wetlands BMP
OWNER: City of Waynesboro
LOCATION: 941 Fir St, Waynesboro, VA 22980
DATE/TIME: October 19, 2026 at 10:00 am.
PURPOSE: Non-mandatory Pre-Bid Conference for Referenced Project
OWNER’S REP: Jennifer Allen-Key, Stormwater Program Manager
A/E FIRM: Gus Hollberg, PE, Wiley|Wilson
RECORD OF ATTENDEES: See attached attendee list.
Drawings, Specifications and Invitation for Bid documents are available in electronic format and are available through eVA download and on the City’s website.
Agenda discussion
INVITATION FOR BID
• Sealed Bids received by 2:00 p.m. on November 16, 2026 at the address listed in
IFB (not 941 Fir St). Bidders may also complete electronic bid submission via the eVA system as directed in Article 13.
• At that time the bids will be publicly opened and read in the Council chambers at
503 West Main St Waynesboro, VA 22980.
INSTRUCTIONS TO BIDDERS
• Conditions at the site. We will head to the site after the meeting. If prospective bidders wish to visit the areas of the proposed work, they should contact Jennifer
Allen-Key, Allen-KeyJL@ci.waynesboro.va.us
• No oral explanation in regard to the meaning of the drawings and specifications will be made and no oral instructions will be given prior to the award of contract.
Contractor’s seeking clarification of the bidding documents shall refer to the
Invitation for Bid.
WQIF Constructed Wetlands BMP 19 October 2026 City of Waynesboro Page 2 of 4
• A Bid Bond of 5% is REQUIRED as stated in the Project Manual. Successful bidder will be required to submit a Standard Performance Bond & Standard Labor and
Material Payment Bond acceptable in form and content to the City.
• Preparation and Submission of Bids: Bidders must have a valid Virginia Contractor
License Number to qualify as a bidder.
• Receipt of Bids: Factors to consider so your bid is on time include:
Bid Officer must have bids in hand by date and time or they will be marked late and shall not be considered.
Pre-bid Questions
• All questions must be emailed and received by 2:00 p.m. EST on October 26, 2026.
Via email to Jennifer Allen-Key, Allen-KeyJL@ci.waynesboro.va.us Include “City of
Waynesboro – WQIF Constructed Wetlands BMP – Prebid Question” in the email subject. No oral explanations regarding the meaning of the drawings or specifications will be provided prior to bidding.
• Responses will be available on eVA by 5:00 p.m. EST, November 2, 2026 to all pre-bid questions in the form of an Addendum.
Bid Form
• The contract shall be awarded on a lump sum basis.
• The Bid Form shall be filled out completely, signed by the responsible parties and dated.
Retainage
• In making partial payments, five percent (5%) shall be retained until final acceptance of all work covered by the contract.
REVIEW SPECIFICATION DIVISIONS
• Bidders shall carefully review all of the technical sections of the project manual.
• Access to work is limited to the work schedule of the facility which is 8:00 a.m. to
5:00 p.m. Monday through Friday. Exceptions to the schedule may be considered with a 48-hour notice to the City by the contractor.
• Temporary construction facilities will be allowed within the limits of disturbance.
• Potable water is available adjacent to the site. Coordinate usage of the fire hydrant with the City of Waynesboro and provide backflow protection.
City of Waynesboro Page 3 of 4
• Temporary electrical service will not be provided by the owner and shall be the responsibility of the contractor.
• Sanitary facilities shall be furnished by the Contractor.
• The project earthwork is unclassified and there is no allowance for rock excavation including trenching.
GENERAL REVIEW OF DRAWINGS AND PROJECT
• Site access o No defined laydown; coordinate with City of Waynesboro and/or adjacent property owners
• Time of year restriction (bats) for tree removal o Restricted April 1 – November 14
• Two BMPs
• Site phasing
• Articulated concrete block o Follow manufacturer’s recommendations for sizing and installation o 13 fps peak velocity @ 690 CFS
• Planting stabilization – time of year recommendations
• Geotechnical report o Neither rock nor karst features anticipated
SCHEDULE
• The work will be substantially complete within 240 days after the date when the
Contract Times commence and completed and ready for final payment within 270 days after the date when the Contract Times commence to run.
QUESTION AND ANSWER PERIOD
• Responses to questions that may impact the scope of work and /or a bid price proposal will be made in an Addendum to the Bidding Documents. Responses that only involve finding information that is already in the Bidding Documents may be made verbally during this Q&A period.
• An addendum will be issued that will include these meeting minutes, any Pre-Bid questions, and a copy of the attendee sign-in sheet.
City of Waynesboro Page 4 of 4
QUESTIONS ADDRESSED DURING THIS MEETING
Notes:
Addressed the pre-bid questions received thus far. Those questions and their answers are included in this Addendum.
End of Pre-Bid Conference Notes
LIST OF PRE-BID CONFERENCE ATTENDEES
City of Waynesboro
WQIF Constructed Wetlands BMP
October 19, 2026, 10:00 am
OSS-04, REV 08-2009
Company Name: LUCACI Inc. General Contractor ( x ) Subcontractor ( ) Supplier ( )
Address:
Telephone Number: Fax Number:
Attendee Name: Adelin Lucaci Email: work@lucaciinc.com
Company Name: Valley Sitework General Contractor ( x ) Subcontractor ( ) Supplier ( )
Attendee Name: ___Daniel Showalter_____________ Email: daniel@valsitework.com
Company Name: Harbor Civil & Marine General Contractor ( x ) Subcontractor ( ) Supplier ( )
Attendee Name: Tim Hall Email: thall@harborcivilmarine.com
Company Name: Premier Group Limited General Contractor ( x ) Subcontractor ( ) Supplier ( )
Attendee Name: Kara Shanks Email: kshanks@premiergroupltd.com
Company Name: Triangle Contracting L.L.C General Contractor ( x ) Subcontractor ( ) Supplier ( )
Attendee Name: Christopher Nevins Email: cnevins@trianglecontracting.com
Company Name: Premier Group Limited General Contractor ( x ) Subcontractor ( ) Supplier ( )
Attendee Name: Stacy Baker Email: stacy@premiergroupltd.com +
File details come from the government source that posted it. Updated .