Addendum 1~2.pdf
PDF 40 KB Posted
- Attached to
- Elkhorn WLA - Auburn tract cut and pile
- Solicitation number
- S-63500-00014533
- Issued by
- Baker County, Oregon
About this file
This document is Addendum #1 for a project involving the Bureau of Land Management (BLM) and Oregon Department of Fish and Wildlife (ODFW), outlining a specific project timeline. The addendum establishes a no-work window from December 1 through April 10 throughout the contract's duration to accommodate wildlife area winter closure. Key project deadlines include a BLM cut and potential pile deadline of November 30, 2026, and an ODFW cut and pile deadline of June 30, 2027. An attached map for ODFW project work areas is referenced, though not visible in this document image.
The addendum appears to be part of a larger contract or project management document, providing critical scheduling constraints related to seasonal wildlife habitat considerations. The specific work windows and deadlines suggest a land management or environmental restoration project that must carefully coordinate activities to minimize disruption to wildlife during sensitive winter months.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum #1
Timeline for Project
No-Work window Dec. 1 through April 10 through the life of the contract to accommodate the wildlife area winter closure.
BLM cut and potential pile deadline Nov. 30, 2026
ODFW cut and pile deadline June 30, 2027
Attached map for ODFW project work areas