This document is Addendum No. 1 for the City of Kissimmee's Request for Qualifications (RFQ2025-001) for Architectural & Engineering Design Services for an Emergency Operations Center (EOC) Building and Prefabricated Parking Garage. The addendum addresses two key questions from potential proposers: first, confirming that firms located more than 60 miles from the city can submit proposals, and second, clarifying that Section VIII should be followed for proposal requirements. The document provides an acknowledgment form for proposers to complete and submit with their proposal, ensuring they have received and understood the addendum.
The addendum does not introduce significant changes to the original RFQ and maintains that all other terms and conditions remain unchanged. Signed by Brandon Durango, the Procurement Manager, this document serves to provide clarity and guidance to potential proposers in the ongoing procurement process for the architectural and engineering design services project. The addendum is dated February 11, 2025, and is part of the city's solicitation for professional services to design a new 15,000-square-foot EOC building and a parking garage with approximately 250 spaces.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
February 11, 2025
Addendum No. 1
Project: Emergency Operations Center (EOC) Building and Prefabricated Parking Garage Architectural & Engineering Design Services Bid No: RFQ2025-001
TO ALL PROPOSERS:
The following items are clarifications, corrections, additions, deletions and / or revisions, which shall take precedence over the original documents.
Question: H2M is in receipt of the City’s RFQ #RFQ2025-001 for Emergency Operations
Center (EOC) Building and Prefabricated Parking Garage Architectural & Engineering Design Services. Would the City be willing to consider prospective firms located more than 60 miles from the City?
Answer: Yes.
Question: Section V. provide the proposal content for organization of the proposal submittals. However, section VIII provided different proposal requirements. Which section, for proposal requirements, are we to follow?
Answer: Please following section VIII. Proposal Requirement
A. ACKNOWLEDGMENT OF ADDENDA:
1. The proposer shall acknowledge receipt of this addendum by completing the applicable section in the RFQ. The Proposer shall submit said Form with the proposal.
2. All other terms and conditions of the RFQ remain unchanged.
Brandon Durango Procurement Manager
ACKNOWLEDGMENT OF ADDENDA NO.(S) _________ (IF APPLICABLE)
(Signature)
COMPANY NAME _______________________________________
COMPANY ADDRESS _______________________________________
BY: _________________________ DATE:________________________