This document is Addendum No. 1 for RFP2025-005 issued by the City of Kissimmee, Florida, regarding the Modernization of City Hall Elevators. The addendum provides clarifications and answers to 14 specific questions about the elevator modernization project. Key details include the project involving two elevators, with a conversion to machine room-less (MRL) traction elevators, a project timeline of 28 weeks per elevator, and a budget of approximately $700,000. The addendum confirms compliance requirements with the 2019 Elevator code, specifies the need for 2-way voice and text communications, and requires a dedicated general contractor supervisor onsite throughout the entire project.

Additional project specifics include the current inoperability of one elevator due to limited parts availability, confirmation that the generator is connected to the elevators, and the requirement for stamped engineering design plans. Contact information is provided for the fire alarm vendor (Johnson Controls) and the mechanical engineer (Will Nafziger from SGM Engineering). The addendum also addresses technical details such as trench safety forms, engineering drawings, and elevator certificates, with instructions for proposers to acknowledge receipt of the addendum by completing the appropriate section in the RFQ and submitting the form with their proposal.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

May 6, 2025

Addendum No. 1

Project: Modernization of City Hall Elevators Bid No: RFP2025-005

TO ALL PROPOSERS:

The following items are clarifications, corrections, additions, deletions and / or revisions, which shall take precedence over the original documents.

Question 1: Please confirm that the installation of a new sump pump will not be part of the project being bid.

Answer: Confirmed, a new sump pump is not required

Question 2: Can you provide an “As Built” drawing for the wall and foundation around the chiller so that the placement of the trenched pipe and foundation slab for the new condensing unit can be confirmed.

Answer: As-built drawings are currently unavailable; however, the construction drawing documents are attached.

Question 3: Please provide contact information for the mandatory Fire Alarm System.

Answer: Fire Alarm Vendor

Robert J. Hansen Senior Commercial Account Executive Johnson Controls Building Solutions 📞📞 (772) 353-0518 (Cell) 📧📧 Robert.1.Hansen@JCI.com 🌐🌐 www.johnsoncontrols.com

Question 4: Some trenching is required. Do you have a trench safety form that the contractor should submit with their bid?

Answer: A trench safety form is required; however, the bidding contractor will provide their own.

Question 5: An Engineer will be required for the placement of the beams and tie into the hoistway for the MRL. Will stamped engineering design plans be required?

Answer: Yes, GC needs to supply the Drawings mailto:Robert.1.Hansen@JCI.com http://www.johnsoncontrols.com/

Question 6: Can the elevator subcontractor’s working foreman act as the supervision during periods when no other trade work is being performed or does the GC need to have a dedicated supervisor onsite during the entire project?

Answer: GC needs to have a dedicated supervisor onsite during the entire project

Question 7: The 2019 Elevator code requires 2-way voice, text communications in place of phone communications. Confirms that all Bidders must comply with ASME A17.1 2019.

Answer: Yes

Question 8: Which type of elevator will be used for the conversion?

Answer: machine room-less (MRL) traction elevator

Question 9: Why is the second elevator currently inoperable?

Answer: Parts are either limited or unavailable to keep the elevator in service.

Question 10: Is the generator connected to the elevators?

Answer: Yes

Question 11: What is the project timeline?

Answer: 28 Weeks per elevator

Question 12: What is the budget for this project?

Answer: Approximately $700,000

Question 13: Do you have the contact for the Mechanical Engineer?

Answer: Mechanical Engineer Will Nafziger Mechanical Engineer – SGM Engineering 📧📧 Williamn@sgmengineering.com 🌐🌐 www.sgmengineering.com 📍📍 5301 Waterford District Dr., Suite 750, Miami, FL 33126 📞📞 Office: (407) 767-5188, Ext. 814

Question 14: Can we retain the elevator certificates? (Michael you were going to confirm)

Answer: Yes. The certificate for Elevator 1 is attached. The certificate for Elevator 2 is posted inside the elevator cab and is available for inspection if needed. Please note that Elevator 2 is currently out of service.

mailto:Williamn@sgmengineering.com http://www.sgmengineering.com/

ACKNOWLEDGMENT OF ADDENDA:

1. The proposer shall acknowledge receipt of this addendum by completing the applicable section in the RFQ. The Proposer shall submit said Form with the proposal.

2. All other terms and conditions of the RFQ remain unchanged.

Brandon Durango Procurement Manager

ACKNOWLEDGMENT OF ADDENDA NO.(S) _________ (IF APPLICABLE)

(Signature)

COMPANY NAME _______________________________________

COMPANY ADDRESS _______________________________________

BY: _________________________ DATE:________________________

(signature)

_____________________________ EMAIL:_______________________

(typed name/title of signer)

File details come from the government source that posted it. Updated .