Addendum 1 Powell 003.pdf
PDF 106 KB Posted
- Solicitation number
- RFP 785 2300000173 2
- Issued by
- Rowan County, Kentucky
About this file
This is Addendum No. 1 to Request for Proposal RFP-141-23 issued by the Commonwealth of Kentucky Department for Facilities and Support Services, Division of Engineering and Contract Administration, in conjunction with the Energy and Environment Cabinet, Division of Oil and Gas. The addendum addresses well plugging and reclamation services for the KASTOW program in Powell County #003. The project is part of the 6th round of RFPs, which includes eight packages across multiple counties (Lawrence #003, Clinton #001, Lee #002, Metcalfe #001, Muhlenberg #002, Powell #003, Russell #001, and Union #002). Contractors awarded under this solicitation will have two years (24 months) to plug and seed the wells, followed by an additional one-year period to establish vegetation.
The addendum clarifies key operational and payment terms for bidders. Class A Cement is the standard Kentucky Division of Oil and Gas requirement, with variations permitted only in special cases such as H2S wells. Invoices may be submitted on a per-well basis once plugging and seeding are completed, with payment issued upon receipt of all required documentation and approval. Performance bonds are valid for two years following the final payment date. These clarifications ensure contractors understand cement specifications, invoice procedures, bond requirements, and project completion timelines prior to bid submission.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF KENTUCKY
DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES
DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION
REQUEST FOR PROPOSAL: RFP-141-23
FOR: KASTOW – POWELL COUNTY #003
Energy & Environment Cabinet Division of Oil and Gas
DATE: November 8, 2022
ADDENDUM NO. One (1)
BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING
UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.
Item 1: Attached to this addendum is the list of questions and answers.
END OF ADDENDUM
REQUEST FOR PROPOSAL: RFP-141-23
For: KASTOW – POWELL COUNTY #003
Energy & Environment Cabinet Division of Oil and Gas
Kristi Sharp, Strategic Procurement Branch Manager Division of Engineering and Contract Administration
KASTOW
RFP's
Kentucky Energy and Environment Cabinet
Addendum No. 1
QUESTION: RESPONSE:
1. What type of cement is required in the plugging procedure. Is it
Portland Type 1/2 Class A Cement or is a blended cement such as 50/50 Paz (50% Portland Type 1/2 and 50% fly ash) acceptable?
Lawrence
#002
Class A Cement is the standard KDOG requirement, variation can be approved only in special cases (e.g.
H2S well).
2. Once well has been plugged and reclaimed, can that particular well be invoiced? Will state pay invoices as wells are plugged or will it be after all work is completed and reclaimed?
Lawrence
#002
Yes, once the well has been plugged and seeded, an invoice may be submitted. Invoices will be paid per well as long as all required documents are submitted and approved.
3. What is the timeframe for the release of the bond once the work is completed?
Lawrence
#002
The bond shall be good for two (2) years following the date on which the final payment is made.
4. Once bid is awarded, what is timeframe for completion? Lawrence
#002 and all packages in
6th round
In the 6 th round of RFPs (Lawrence #003, Clinton
#001, Lee #002, Metcalfe #001, Muhlenberg #002, Powell #003, Russell #001 and Union #002), contractors have two (2) years (24 months) to plug and seed the wells and another year to establish vegetation.