About this file
This is an Addendum #1 for the Michigan Department of Transportation (MDOT) North Region Office Roof and Dormer Window Replacement project located at 1088 M-32 East in Gaylord, Michigan. The project involves replacing the roof shingles, dormer windows, and associated drywall, with work to be completed on a lump sum basis. The addendum, issued on October 15, 2025, provides clarifications about the project, including that replacement shingles do not need to be one-for-one replacements and must be specified in section 07311 2.02 or an approved equal. A 2-year watertight workmanship warranty is required, and all old flashing must be removed and replaced to ensure a watertight system.
The bid includes an allowance amount of $15,000.00 and provides a schedule for potential additional work, such as replacing 4x8 plywood for damaged roof sheeting and removing and replacing water-damaged drywall. The project documents include a meeting attendance record from October 8, 2025, at 11:00 AM, with representatives from various construction and roofing companies present. The bid schedule allows for unit pricing and contingent change order prices, with the owner reserving the right to negotiate these prices before incorporating them into the final contract documents.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM #1
Project Name: North Region Office Roof and Dormer Window Replacement Issuance Date: October 15, 2025 Project Location: MDOT North Region Office/ 1088 M-32 East, Gaylord, MI 49735 MDOT Project Number: F000887CON DTMB400 File Number: 591/25369.AGY
This addendum is issued to inform bidders of changes, clarifications, and additions to the drawings and/or specifications. Provide all labor, materials, equipment, services, and supervision as necessary to complete the work stated herein. All costs associated with the work in this addendum shall be included in the bid price and are considered part of the contract. All work shall be in accordance with the original bid documents and the information indicated below:
Specifications:
1. Base Bid Schedule
See updated bid schedule on page 3.
2. Schedule of Unit Prices or Contingent Change Order Prices
See updated schedules for unit prices or contingent change order prices on page 4.
3. Division 092900 – Gypsum Board
3. Materials. 1.1. Insert quantity of (10) 4x8 sheets of gypsum board.
Q and A:
Q: Do the replacement shingles need to be a one for one replacement of the current architectural shingles?
A: No, they do not. The new replacement shingles will be as specified in section 07311 2.02 “Acceptable Manufacturer” or approved equal. Region staff will choose the color during post-bid submittal period.
Approved equal must be approved 7 days prior to bid opening date.
Q: What length of watertight workmanship warranty will need to be provided?
A: We want 2 years of watertight workmanship warranty as specified in 00700 5.1 “Roof Warranty”.
Q: What product warranty do we want?
A: Both specified products have limited lifetime warranties.
Q: Does the flashing need to be replaced?
A: Yes, please remove all old flashing and install new flashing to ensure watertight system is achieved.
ACKNOWLEDGE RECEIPT OF ADDENDUM ON BID SUMMARY
Bidding and Contract Document (R 03/25) V2 Project Name: North Region Office Roof Replacement File No. 591/25369.AGY
BID SCHEDULE
Base Bid Schedule - The Bidder will complete the Work and accept as full payment, for the Work items listed, the following Unit Prices and/or Item Bid Prices, as applicable:
Base Bid Item No.
Bid Quantity
Description
Unit Price
Item Bid Price
1. 1. Labor, material, equipment and related services for a new shingled roofing system, dormer windows and drywall
Lump Sum
ALLOWANCE AMOUNT Lump Sum $15,000.00
TOTAL (This amount should equal the Base Bid amount on the Bid Summary Form) $
Base Bid (Sum of Item Bid Prices for all Base Bid Items):
__________________________________________________________________ Dollars $__________________________ (use words) (in figures)
Bidding and Contract Document (R 03/25) V2 Project Name: North Region Office Roof Replacement File No. 591/25369.AGY
Schedule of Alternates - The Bidder will complete (or deduct from the Contract) the parts of the Work designated by the Alternates that follow and accept in full payment (or allow in full credit) for those parts of the Work the following Item Bid Prices:
Alternate Item No.
Bid
Item Bid
The Bidder further acknowledges and agrees that the separate prices bid on this “Schedule of Alternates,” where they are applicable and deemed acceptable by the Owner, will be used if incorporated into the Contract when the Owner issues the Notice of Award.
Schedule of Unit Prices or Contingent Change Order Prices - The Bidder shall use this “Schedule” to quote unit prices identified in the bid documents or propose other contingent Change Order prices. The proposed Unit Prices or contingent Change Order prices set forth in this schedule, at the sole discretion of the Owner, may, or may not be incorporated into the Contract Documents. The Owner reserves the right to negotiate Unit Prices or contingent Change Order prices set forth herein prior to their possible incorporation into the Contract Documents.
Item No. Bid
Item Bid Price
1 4x8 Plywood for damaged roof sheeting
Per Sq Ft
2 Remove and replace water damaged drywall. 4x8 ft sheets
Per Sq Ft