Addendum #1- Martinuk Pipe Drop @ ENSP- P-026-241-010.pdf

PDF 65 KB Posted

Attached to
MARTINUK EROSION STABILIZATION @ ELK NECK STATE FOREST
Solicitation number
BPM042550
Issued by
Cecil County, Elkridge CDP, Maryland

About this file

This document is an Addendum to the MARTINUK EROSION STABILIZATION @ ELK NECK STATE FOREST project, a state contract opportunity issued by the State of Maryland for Cecil County and Elkridge CDP. The Addendum modifies the Scope of Work to include cutting to grade five trees, clearing small brush and brambles, and providing specific quantities of cut and fill for the swale, pipe installation, berm, and gully. The project consists of installing a grade stabilization structure with a pipe drop at the Elk Neck State Forest.

The Addendum provides additional details and specifications for the scope of work, including the types and sizes of trees to be cut, the areas to be cleared, and the quantities of cut and fill material required. No other significant changes to the contract requirements are noted.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum # 1

Project Number P-026-241-010

Martinuk Erosion Stabilization

Elk Neck State Forest

Page IV-1, A. Scope. 2.e., f., g. :

ADD: e. Cut to grade the following five trees to be marked at the pre-bid conference: Two (2) 18” (d) Pine Oaks, One (1) 14” (d) American Beech, One (1) 22” (d) Cottonwood, One (1) 12” (d) Maple Tree.

f. Clear all small brush and brambles in the LOD.

g. Install the approximate quantities of cut and fill: Cut – 100 CY for the swale and 670 CY for the Pipe Installation. Fill – 89 CY at the berm and 200 CY for the gully.

Page IV-5, G. Method of Work. 2. Specific c, d, e:

ADD: c. Cut to grade the following five trees to be marked at the pre-bid conference: Two (2) 18” (d) Pine Oaks, One (1) 14” (d) American Beech, One (1) 22” (d) Cottonwood, One (1) 12” (d) Maple Tree.

d. Clear all small brush and brambles in the LOD.

e. Install the approximate quantities of cut and fill: Cut – 100 CY for the swale and 670 CY for the Pipe Installation. Fill – 89 CY at the berm and 200 CY for the gully.

--END OF ADDENDUM--