This Addendum #1 to Request for Quote 2026-100 is issued by the City of Groveland, Florida, for Native Plants Maintenance services. The addendum provides clarification on the scope of work covering five items for routine maintenance of native and hybrid landscaping at multiple downtown locations and public facilities. The contract period runs from July 6, 2026, through September 30, 2026, requiring one maintenance visit per week for twelve weeks. Vendors must provide pricing based on maintaining five separate landscape areas including Broad Street corridor plantings, flower baskets, a landscaped median, and a rain garden at North Lake David Park. The City reserves the right to award individual items, multiple items, or all five items as a single complete contract, though the stated intent is to award all items to one contractor. No specific bid response date, due date, or site visit information is provided in this addendum document, though vendors are encouraged to verify quantities and conditions through site visits. The contract is temporary in nature, focused exclusively on routine maintenance of existing conditions without initial restorative work or major repairs.

Pricing shall be provided as lump-sum quotes inclusive of all labor, equipment, materials, overhead, taxes, travel, and disposal costs delivered to the City of Groveland. The scope of work includes hand weeding, pruning, mowing as conditions warrant, debris removal, minor erosion stabilization, irrigation system monitoring and reporting only (with repairs excluded from base scope and requiring separate authorization), and removal of impediments to water flow. The City will provide replacement plants if directed, with minor planting labor included in the contractor's quoted price. Herbicide applications are permitted using lawful methods, though any required licenses and all product costs are the contractor's responsibility. Contractors are responsible for documenting and reporting third-party or weather-related damage but are not responsible for restoration; however, contractor-caused damage must be corrected at no additional cost. Maintenance standards require keeping sites neat and presentable with reasonable control of undesirable vegetation. Invoices shall be submitted monthly to the project representative, with copies to accountpayables@groveland-fl.gov. The addendum includes acknowledgment signature lines for bidder authorization.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

156 S. Lake Avenue • Groveland, FL 34736 • www.Groveland-FL.gov

RFQ 2026-100, Native Plants Maintenance

ADDENDUM # 1

QUESTIONS AND ANSWERS

1. The price sheet identifies 12 weekly service cycles between July 6, 2026, and September 30, 2026. Please confirm whether the City requires exactly 12 weekly service visits or one visit during every calendar week within that date range.

Answer: The City intends for vendors to provide one maintenance visit per week for the twelve (12) week period identified in the RFQ. Pricing shall be based on twelve (12) weekly service cycles for Items 1 through 3.

2. Please confirm the exact maintenance boundaries and approximate dimensions or square footage for each project location. Specifically:

a. Does Item 1 include both sides of Broad Street, center medians, turf areas, landscape beds, tree wells, and other landscaped areas within the corridor?

Answer: Vendors should base their pricing on maintaining the existing planted native landscape areas located within the identified corridor as shown on the RFQ exhibit. This solicitation is intended to maintain existing conditions only.

b. For Item 3, does the scope include only the single median area highlighted on the RFQ map, or are additional areas included?

Answer: Pricing shall be based on the landscaped median area identified on the RFQ exhibit.

c. Approximately how many flower baskets are included in Item 4?

Answer: Vendors are encouraged to verify quantities during a site visit. Pricing shall include maintenance of all existing flower baskets currently installed within the identified corridor.

d. Please confirm maintenance limits of the North Lake David Park rain garden.

Answer: Pricing shall be based on maintaining the existing rain garden planting area shown on the RFQ exhibit.

Adjacent areas not associated with the rain garden are not included unless specifically necessary to perform routine maintenance of the rain garden.

3. Will the City award all five items as one complete contract, or may individual items be awarded separately to different vendors?

Answer: The City reserves the right to award by individual item, multiple items, or in whole, whichever is determined to be in the City's best interest. However, the City intends to award all five items as one complete contract for the three month period.

4. Are vendors expected to perform an initial restorative or catch-up cleanup during the first service visit?

Answer: No. This temporary contract is intended to provide routine maintenance of existing conditions during the contract period. Pricing should be based on maintaining sites in their condition at the start of the contract and not on performing major restoration work.

Maintenance Standards and Existing Conditions

5. Please identify expected maintenance standards.

a. Required mowing height?

Answer: Mowing shall be performed as necessary to maintain a neat and presentable appearance consistent with routine municipal landscape maintenance practices.

b. Is mowing required every visit?

Answer: No. Maintenance activities should be performed as conditions warrant.

c. Acceptable weed threshold?

Answer: Sites shall be maintained to reasonably control undesirable vegetation and preserve the appearance and health of existing plantings.

d. Removal of debris?

Answer: Yes. All litter, weeds, branches, trimmings, and other debris generated during maintenance activities shall be removed and legally disposed of by the contractor.

6. Does the City have an existing plant inventory or approved plant list?

Answer: No plant inventory will be provided. Contractors shall maintain existing plant materials currently installed at each location.

Irrigation Inspection and Repair

7. Is the contractor responsible for repairs or only monitoring and reporting?

Answer: As stated in the RFQ, the contractor's responsibility is limited to monitoring irrigation conditions and reporting deficiencies to the City. Irrigation repairs are not included in the base scope.

8. How many irrigation systems, controllers, or zones serve the sites?

Answer: This information is not available for bidding purposes. Contractors shall base pricing on the inspection and reporting requirements identified in the RFQ.

9. Are any irrigation systems currently known to be non-operational?

Answer: No representations are made regarding current irrigation conditions. The contractor's responsibility is limited to observation and reporting.

10. Is a wet check required?

Answer: No. Routine visual inspection and reporting are required. Operational testing is not part of the base scope.

11. If wet checks are required, what frequency is expected?

Answer: Not applicable.

12. Will the contractor be provided access to controllers or enclosures?

Answer: Access will only be provided if deemed necessary by the City. Routine maintenance under this contract does not require controller operation.

13. What should be included when reporting irrigation deficiencies?

Answer: Location, description of observed issue, photographs if available, and any recommendations for City review.

14. If repairs are requested, how will those be compensated?

Answer: Any irrigation repair work beyond inspection and reporting would require separate City authorization and is not included in the base contract price.

Replacement Plants, Damage, Turf, and Erosion

15a. Will the City provide replacement plants?

Answer: Yes. As stated in the RFQ, the City will provide replacement plants if replacement planting is directed by the City.

15b. Is planting labor included?

Answer: Minor replacement planting labor associated with City-furnished plants shall be included in the quoted price.

15c. Can the City estimate replacement quantities?

Answer: No estimate is available. This contract is intended primarily for routine maintenance of existing installations.

16. Is the contractor responsible for damage caused by third parties, weather, or City operations?

Answer: No. The contractor shall document and report such damage to the City. Restoration of third-party damage is not included in the base scope.

17. Please define erosion repair.

Answer: Minor hand repair and stabilization activities associated with routine landscape maintenance may be performed as needed. Major erosion repair, grading, reconstruction, or material replacement is not included.

18. Is contractor-caused damage the contractor's responsibility?

Answer: Yes. Damage resulting from the contractor's operations shall be corrected by the contractor at no additional cost to the City.

Herbicide and Chemical Applications

19. Is herbicide required?

Answer: No specific herbicide application program is required. Contractors may utilize lawful and appropriate maintenance methods to control undesirable vegetation.

20. If herbicide is used:

a. Required licenses?

Answer: Any required licenses or certifications must comply with applicable federal, state, and local requirements.

b. May licensed subcontractors perform this work?

Answer: Yes.

c. Will the City provide products?

Answer: No. Any products used shall be included in the contractor's pricing.

d. Approved product list?

Answer: No.

Water Flow and BMP Maintenance

21. Please define removal of impediments to water flow.

Answer: The term refers to the removal of litter, vegetation, and minor obstructions that can reasonably be addressed through routine maintenance activities.

22. Will substantial sediment removal or reconstruction be compensated separately?

Answer: Yes. Major repairs, reconstruction, excavation, or similar work are not included in the base scope and would require separate authorization.

FDOT Right-of-Way and Traffic Control

23a. Who obtains FDOT permissions?

Answer: Contractors shall be responsible for complying with all applicable regulations associated with their operations.

23b. Is FDOT TTC training sufficient?

Answer: Contractors shall determine and provide any traffic control measures, training, permits, or approvals required by applicable regulations and conditions.

23c. Restricted work hours?

Answer: No.

Scheduling, Reporting, and Payment

24. What if weather or emergencies delay service?

Answer: The contractor shall coordinate reasonable rescheduling with the City to ensure required maintenance is completed.

25. What documentation is required?

Answer: At a minimum, the contractor shall provide a summary of work performed and report any observed deficiencies requiring City attention.

26. Who will be the City's project contact?

Answer: The City will identify a project representative upon award.

27. How should invoices be submitted?

Answer: Invoices shall be submitted monthly for work completed during the billing period to the project representative which will be identified upon award. A copy can be submitted to accountpayables@groveland-fl.gov.

Acknowledgment is hereby made of Addendum #1 to project RFQ 2026-100, Native Plants Maintenance

Bidder Signature Date Bidder Printed Name Company Name

File details come from the government source that posted it. Updated .