Summary: Addendum #1 to AR 2026-001, Disaster Debris Monitoring Services
This document is Addendum #1 to a Request for Proposal issued by the City of Groveland, Florida, for Disaster Debris Monitoring Services (AR 2026-001). The City is establishing its first competitive solicitation for debris monitoring services to ensure qualified resources are available following debris-generating events and to support compliance with procurement and Federal Emergency Management Agency (FEMA) reimbursement requirements. The solicitation requires the successful bidder to assign a project manager responsible for overseeing all debris contractors and teams, coordinating daily briefings, scheduling work for debris team members, monitoring contractor progress, assisting with public concerns, conducting safety inspections, ensuring contract compliance by subcontractors, and managing the FEMA reimbursement process. The service area encompasses the incorporated limits of the City of Groveland. The contract will commence following City approval and execution, with an anticipated initial three-year term and two optional one-year renewal periods at the City's discretion. The anticipated award date has not been specified in the solicitation materials.
No incumbent contractor exists for these services, as this represents the City's first solicitation for debris monitoring. The solicitation does not guarantee minimum quantities of work or minimum payments; services will be utilized on an as-needed basis. Neither bid bonds nor performance and payment bonds are required. Bidders must submit pricing using the required Pricing Schedule provided with the solicitation and identify any exceptions or deviations on the Statement of Compliance and Exceptions form. Bidders are evaluated based on factors identified in the solicitation, with bidder location not serving as an evaluation criterion. All bidders must comply with response time requirements and qualification standards specified in the Scope of Work. The addendum must be returned with all bid responses.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum_2__Date_Extension.pdf | ||
| AR_2026001_Debris_Monitoring_Services_Final_07222026.pdf | ||
| Exhibit_B_Pricing_Schedule_AR_2026001_Final_07222026.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
156 S. Lake Avenue • Groveland, FL 34736 • www.Groveland-FL.gov
Coraly Velez Procurement Manager
(352) 429-2141
Coraly.Vazquez@groveland-fl.gov
AR 2026-001, Disaster Debris Monitoring Services
ADDENDUM #1
July 23, 2026 Bidders are hereby notified that this addendum shall be made a part of the above-named Request for Proposal and agreement documents. The items listed below are issued to add, modify, and/or clarify the solicitation document and agreement documents. The items shall have the same force and effect as the original bidding and agreement documents, and cost involved shall be included in the bid pricing. Bids, to be submitted, shall confirm with the addition and revision listed herein. Return this sheet with your bid response.
QUESTIONS AND ANSWERS
Question 1: Has the current contract gone full term?
Answer 1: Not applicable. This is the City's first solicitation for Debris Monitoring Services. There is no current or previous contract for these services.
Question 2. Have all options to extend the current contract been exercised?
Answer 2. Not applicable. This is the first solicitation and subsequent contract; therefore, no renewal or extension options have been exercised.
Question 3. Who is the incumbent, and how long has the incumbent been providing the requested services?
Answer 3. There is no incumbent contractor. This is the first solicitation and resulting contract for these services.
Question 4. To what extent will the location of the bidder's proposed location or headquarters have a bearing on any award?
Answer 4. The solicitation does not establish bidder location as an evaluation criterion. Award will be made to the responsive and responsible bidder determined to be most advantageous to the City based on the evaluation factors identified in the solicitation.
Question 5. What is the maximum number of hours post-event before work must commence?
Answer 5. Bidders shall comply with the response time requirements identified in the Scope of Work. The solicitation does not establish a separate maximum number of hours outside those requirements.
Question 6. What is the total size or geographic scope of the service area?
Answer 6. The service area consists of the incorporated limits of the City of Groveland as described in the Scope of Work.
Question 7. What is the total mileage of roads within the scope of the service area?
Answer 7. The solicitation does not provide total roadway mileage. Bidders should base their proposals on the requirements contained in the solicitation documents.
Question 8. Are any specific professional credentials required to qualify for the contract?
Answer 8. Bidders must meet the qualifications and experience requirements specified in the solicitation and submit all required qualification documentation. No additional professional credential beyond those identified in the solicitation is required.
Question 9. Will the resulting contract include a guaranteed minimum payment to the vendor?
Answer 9. No. The solicitation does not guarantee a minimum quantity of work or minimum payment. Services will be utilized on an as-needed basis.
Question 10. Are there any superseding prior agreements that may impact this contract?
Answer 10. No. This is the first solicitation and resulting contract for Debris Monitoring Services; therefore, no prior agreements apply.
Question 11. When/what was the most recent event that precipitated the activation of the existing or previous contract?
Answer 11. Not applicable. There is no previous or existing contract.
Question 12. Approximately how many cubic yards of debris were collected from the most recent event?
Answer 12. No data is available. This is the first solicitation and no previous contract history exists.
Question 13. What estimated or actual dollars were paid to the incumbent(s) after the most recent event Answer 13. No data is available because there is no incumbent and no previous contract.
Question 14. How many times have the incumbent's services been utilized in the previous five years?
Answer 14. None. There is no incumbent contractor.
Question 15. If there was a previous solicitation for these services, what was its title, number, release date, and due date?
Answer 15. There has been no previous solicitation for these services. This is the City's first solicitation for Debris
Monitoring Services.
Question 16. Why has this bid been released at this time?
Answer 16. The City is establishing a competitively procured debris monitoring contract to ensure qualified services are available when needed following debris-generating events and to support compliance with applicable procurement and FEMA reimbursement requirements.
Question 17. When is the anticipated contract start date?
Answer 17. The contract will begin following City approval and execution of the agreement. The solicitation anticipates an initial three-year term with two one-year renewal options at the City's discretion.
Question 18. When is the anticipated award date?
Answer 18. The anticipated award date has not been specified in the solicitation. Award will occur following evaluation, recommendation, and approval in accordance with the City's procurement process.
Question 19. Can you please provide greater details regarding your bid bond and/or performance bond requirements?
Answer 19. As stated on the Solicitation Cover Page, Bid Bond: Not Applicable and Payment & Performance Bond:
Not Applicable. Therefore, neither is required for this solicitation.
Question 20. Are bidders permitted to deviate in any way from the pricing format?
Answer 20. Bidders shall submit pricing using the required Pricing Schedule included with the solicitation. Any exceptions or deviations must be identified on the Statement of Compliance and Exceptions form. The City will evaluate any exceptions in accordance with the solicitation requirements.
Question 21. Please describe your level of satisfaction with your current or recent vendor(s), if applicable.
Answer 21. Not applicable. This is the City's first solicitation and resulting contract for Debris Monitoring Services;
therefore, there is no current or recent vendor to evaluate.
Acknowledgment is hereby made of Addendum #1 to project AR 2026-001, Disaster Debris Monitoring Services
Bidder Signature Date Bidder Printed Name Company Name
File details come from the government source that posted it. Updated .