This is Addendum One to a Request for Proposal issued by Colorado Parks and Wildlife's Southeast Regional Office for the design and construction of an equipment storage building at Flagler State Wildlife Area (Project DQ1: 2027*22 PMAA-5614, S26WSE-8326). The addendum clarifies that no additional structural drawings will be provided by CPW beyond the bid documents, which identify a pre-approved manufacturer as the design intent and minimum standard. Contractors may propose an "approved equal" alternate building but must submit sufficient information prior to bidding to obtain initial concurrence from the Project Manager. Contractors must submit completed bid schedules by 1:00 p.m. on August 7, 2026, with final questions due by 10:00 a.m. on August 4, 2026. Submissions should be directed to Shaun C. Gordon, RLA Design & Construction Project Manager, at shaun.gordon@state.co.us.
The Contractor is responsible for providing all engineered building drawings, foundation reactions, anchor-bolt plans, and any required revisions to the foundation design necessary for construction. Contractors proposing alternate buildings assume the risk that such alternates may not be approved or entertained. A bid tabulation and summary will be distributed to all bidders following the submission deadline.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2018 CPW GCs 071818 FINAL.pdf | ||
| Flagler Equipment Storage Building Plans 072026.pdf | ||
| BID DOCUMENTS 072026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Southeast Regional Office | 4255 Sinton Road | Colorado Springs, CO 80907
ADDENDUM ONE
July 29, 2026
Subject: Addendum Number One to: DQ1: 2027*22
PMAA-5614-Flagler SWA – Equipment Storage Building, S26WSE-8326
To Whom It May Concern:
The following items clarify or revise the language of the subject request for proposal and should be considered by all Proposer’s when submitting their proposal. Make sure to note receipt of this addendum on page 1 of the Bid Schedule. Announcements and answers to questions are in Bold type:
1. Could you please clarify whether additional structural drawings will be issued for bidding? If not, please confirm whether the selected building manufacturer and contractor are responsible for providing the engineered building drawings, foundation reactions, anchor-bolt plan, and any required revisions to the foundation design.?
No additional drawings will be supplied by CPW. While a pre-approved Manufacturer is identified in the bid documents identifying design intent and minimum standards, the design has been left open to what would be considered as “approved equal”. If a Contractor is planning on using an alternate building, they should submit enough information prior to bidding to obtain initial concurrence from the Project Manager. Otherwise, the Contractor will be taking their own chance if an alternate would be entertained or not.
The Contractor will be responsible for providing the engineered building drawings, foundation reactions, anchor-bolt plan, and any required revisions to the foundation design necessary for the construction of the building.
End of Addendum #1
Final questions are due by August 04, 2026 at 10am. Please make sure to have your completed Bid Schedules emailed to me by 1pm on August 07, 2026 at shaun.gordon@state.co.us . A bid tabulation/summary will be emailed to all bidders.
Thanks, Shaun C. Gordon, RLA Design & Construction Project Manager Colorado Parks and Wildlife Southeast Regional Office 4255 Sinton Road Colorado Springs, Colorado 80907 email: shaun.gordon@state.co.us mailto:shaun.gordon@state.co.us mailto:shaun.gordon@state.co.us