Addendum_1.pdf
PDF 5 MB Posted
- Solicitation number
- 0000037333
- Issued by
- Amador County, Huntington Beach City, California
About this file
This is an addendum issued by the California Department of Corrections and Rehabilitation (CDCR) Division of Administrative Services regarding Quote Request (QR) Number C5613045-D for Asphalt Concrete Paving Services at Mule Creek State Prison. The addendum revises the original QR package and updates the bid submission deadline to December 18, 2025, by 11:00 AM. The project involves asphalt concrete paving work including approximately 160 linear feet of 42-inch trench patches, 28 linear feet of 36-inch trench patches, 206 linear feet of 36-inch trench patches, 72 linear feet of 36-inch trench patches, and 325 linear feet of 42-inch trench patches for the Multi-Service Facility, administrative roadway, and parking areas. The contractor shall provide all labor, supervision, equipment, tools, insurance, materials, supplies, travel, permits, licenses, bonds, taxes, and other necessary items. The addendum includes revised plans with updated highlighting of patch locations and a Letter of Inquiry (LOI) Questions and Answers document addressing bidder inquiries.
The project is restricted to Small Business (SB) bidders only. Key clarifications from the LOI include confirmation that no bid bond is required prior to award, though two original signed Payment Bonds are required after award as specified in the Special Terms and Conditions for Public Works. The contractor is not responsible for existing asphalt removal, as pavement has already been removed and base preparation will be completed by the Correctional Construction Mentorship Program (CCM), with the contractor only responsible for asphalt installation per specifications. Additional clarifications confirm that TB tests and live scanning of personnel are not required, paving fabric is not required, and all bids must be emailed directly to Monique Stephens at Monique.Stephens@cdcr.ca.gov. Compensation will be based on service rates specified on Exhibit B-1, the Public Works Rate Sheet.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit_B-1.xlsx | XLSX spreadsheet | |
| Exhibit_A-1.pdf | ||
| C5613045-D.pdf | ||
| Exhibit_A-3.pdf | ||
| Exhibit_A-2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF CALIFORNIA — DEPARTMENT OF CORRECTIONS AND REHABILITATION GAVIN NEWSOM, GOVERNOR
DIVISION OF ADMINISTRATIVE SERVICES
OFFICE OF BUSINESS SERVICES
9838 Old Placerville Road Suite B-2
Sacramento, CA 95827
December 2, 2025
TO: PROSPECTIVE BIDDER
RE: INVITATION FOR BID (QR) NUMBER C5613045-D
SERVICE: ASPHALT CONCRETE PAVING
The Quote Request (QR) package has been revised and a new QR package is enclosed.
You may view or download a copy of the revised QR document(s) by accessing the California State Contracts Register (CSCR) at https://caleprocure.ca.gov/event/5225/0000037333.
The following corrections have been made to the QR:
A. Quote Request has been revised and replaced with Quote Request, Addendum 1 to update bid submission date (pg.2)
B. Plans have been provided in response to the bidder's questions.
C. Letters of Inquiry (LOI) Questions and Answers have been provided in response to the bidder’s questions.
The deadline for submission of your bid is December 18, 2025 by 11:00 AM.
If you submit a new bid, your first bid will be returned unopened. However, if you have already submitted a bid and you do not submit a new bid, your current bid shall remain in our files, unopened, until the new bid opening date.
We regret any inconvenience this may have caused. If you have any questions or need assistance from this office, please do not hesitate to contact me at Monique.Stephens@cdcr.ca.gov.
Sincerely, Monique Stephens Monique Stephens Contract Analyst Institution Contracts Section Contracts Management Branch https://caleprocure.ca.gov/event/5225/0000037333 mailto:Monique.Stephens@cdcr.ca.gov
NO MANS LAND
Highlight is an approx total of 160 lf. of 42" trench patch fmdpsu Highlight fmdpsu Pencil fmdpsu Highlight fmdpsu Highlight fmdpsu Highlight
Highlight is an approx. total of 28 lf. of 36" trench patch rodney.whitmore Sticky Note 2' X 12' cut rodney.whitmore Sticky Note 2' X 12' cut
206 lf. of 36" trench patch rodney.whitmore Sticky Note 2' X 15' cut rodney.whitmore Sticky Note 2' X 105' cut rodney.whitmore Sticky Note 2' X 15 cut rodney.whitmore Sticky Note 2' X 12' cut rodney.whitmore Sticky Note 2' X 15' cut rodney.whitmore Sticky Note 2' X 15' cut rodney.whitmore Sticky Note 2' X 15' cut
72 lf. of 36" trench patch
Area 2
Highlight is part of the 325 lf.
of 42" trench patch for the MSF, Admin road way and parking fmdpsu Highlight fmdpsu Highlight fmdpsu Highlight fmdpsu Highlight fmdpsu Highlight
Area 2
Highlight is part of the 325 lf. of 42" trench patch for MSF, Adnin roadway and parking fmdpsu Highlight fmdpsu Highlight
Area 1
14 X 23 area
14 X 22 area
Highlight is part of the 325 lf. of 42" Trench patch for MSF,admin roadway and parking
TBB Bid Number C5613045-D California Department of Corrections and Rehabilitation (CDCR) Addendum 1 Letter of Inquiry (LOI): Questions and Answers
1. Please confirm the QR form, certifications, and Exhibit B-1 is not due tomorrow at 2pm per page 2 item 2 of the QR form.
Answer: Correct, All QR bids are due 12/18/2025 by 11:00 am. This has been corrected on the attached revised Quote Request Form.
2. Please confirm no bid bond is required prior to award. After award a payment and performance bond is required.
Answer: Correct, no bid bond is required prior to award. Two (2) original signed “Payment Bonds” are required after award. (Refer to Exhibit D, Special Terms and Conditions for Public Works)
3. Can the total square footage be shared?
Answer: Yes, square footage measurements are located on pg. 1 of the Scope of Work under Contractors Responsibilities.
4. Can the highlights on all drawings be updated so we can see the total number of patch locations on L-100, L-104, L-105, & L-106?
Answer: Yes, updated plans have been included which show the areas highlighted
5. If the contractor is responsible for existing asphalt removal, how will it be stockpiled by CDCR?
Answer: No, the contractor is not responsible for the existing asphalt removal.
Pavement has been removed, CCM will install the base to achieve sub grade, the Contractor is only required to install asphalt per specifications.
TBB Bid Number C5613045-D California Department of Corrections and Rehabilitation (CDCR) Addendum 1
6. Will TB tests be required for crew members/management personnel onsite?
Answer: No, TB tests will not be required.
7. Is live scanning on personnel required?
Answer: No, live scanning is not required.
8. Will paving fabric be required for any of the work? It is noted in the specifications, but I do not see it being needed for any of the work.
Answer: No, paving fabric is not required. The asphalt is required to be installed per specifications. See SOW #2 Contractors responsibility paragraph 4.
9. Please confirm proposals are to be emailed and not uploaded to another website.
Answer: Yes, all Quote Request (QR) bids are to be emailed directly to Monique Stephens at Monique.Stephens@cdcr.ca.gov by the submission due date.
mailto:Monique.Stephens@cdcr.ca.gov