This document is Addendum 1 for the South Beaches Lift Stations Rehabilitation project issued by Brevard County Purchasing Services, located in Viera, Florida. The addendum clarifies the project timeline for rehabilitating four specific lift stations (B-14, B-18, S-18 & S-29) with a total contract duration of ninety (90) days from the Notice to Proceed (NTP). The project has a substantial completion deadline of sixty (60) days from NTP, with final completion required thirty (30) days after substantial completion. The bid opening is scheduled for Friday, November 01, 2024, at 10:00 AM, and bidders are required to acknowledge receipt of this addendum in their bid submission.
The addendum addresses a specific question regarding the project completion timeline, confirming that the 90-day total contract time and associated milestones apply to all four lift stations collectively, not per individual station. No specific pricing, funding sources, or detailed rehabilitation scope are discussed in this document. The primary purpose is to provide clarity on the project timeline and ensure potential bidders understand the overall contract expectations before submitting their bids.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Purchasing Services 2725 Judge Fran Jamieson Way
Building C, Room 303 Viera, Florida 32940
South Beaches Lift Stations B-14, B-18, S-18 & S-29 Rehabilitation B-7-25-14
October 14, 2024
ADDENDUM 1
TO ALL PROSPECTIVE BIDDERS
This is an Addendum to and shall be considered as part of the original bid package for the above-mentioned bid. Please acknowledge receipt of Addendum 1 in the space provided on the Price Sheet located in the solicitation. Bidders are requested to acknowledge receipt of this addendum with their bid.
PLEASE NOTE CLARIFICATION FOR DEADLINE FOR COMPLETION LOCATED ON PAGE 11 IN
THE SPECIFICATION:
Question 1: Specifications for this project states Deadline for Completion states 60 days from NTP. 30 for substantial and 30 for final completion. Is that per lift station or for all four?
Answer 1: Total contract time is ninety (90) days form the Notice to Proceed (NTP). Substantial Completion sixty (60) days from NTP. Final completion thirty (30) days from Substantial Completion.
This timeline is for all four lift stations not per lift station.
Please note that the bid opening date will remain Friday, November 01, 2024 @ 10:00 AM.
Sincerely, Mary Bowers Purchasing Manager