Addendum_1.pdf
PDF 174 KB Posted
- Solicitation number
- RFQ-171-180000000503-2
- Issued by
- Delta County, Fruitport Village, Michigan
About this file
This is Addendum No. 1 issued by U.P. Engineers & Architects, Inc. for the Michigan Department of Natural Resources Escanaba Parks & Recreation Division's Cold Storage Building & Building Addition project in Gladstone, Michigan, dated April 20, 2018. The addendum modifies the original plans and specifications for construction work on two buildings, with a mandatory sign-in requirement and coordination needed with Law Enforcement Staff for building addition access. Work schedule parameters allow up to 10-hour workdays starting no earlier than 7 am unless approved by DNR Park & Rec staff, and both buildings can be worked on simultaneously.
The addendum stipulates a $3,000 electrical power company allowance must be included in the contractor's lump sum price for utility company line extension. It also specifies that the electrical service meter location should be positioned to the left side of the proposed garage door. The attached meeting attendance record from April 9, 2018, shows various contractors and representatives from companies including DTMB, construction firms, electrical contractors, and concrete companies who attended the mandatory meeting.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BidSum.pdf | ||
| Plans.pdf | ||
| Advertisement.pdf | ||
| Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
100 Portage Street Houghton, MI 49931
906-482-4810 • 800-562-7684 • Fax: 906-482-9799
Offices also in:
Iron Mountain
Ishpeming Marinette
Sault Ste Marie
U.P. Engineers & Architects, Inc. www.UPEA.com
ADDENDUM NO. 1
File No.751/17108.RAA Index No. 52010
Michigan Department of Natural Resouces Escanaba Parks & Rec Division
Cold Storage Building & Building Addition Gladstone, Michigan
This ADDENDUM NO. 1, issued on April 20, 2018 is to clarify, modify and/or change the original plans and specifications issued by U.P. Engineers & Architects, Inc. and is hereby made a part of the bidding documents.
Bidders are required to acknowledge receipt of this ADDENDUM NO. 1 on the appropriate place on the Bid Form.
A. General
1. The Mandatory sign in sheet is attached.
2. Both buildings can be worked on at the same time.
3. Building addition work will require one week notice for access from Law
Enforcement Staff.
4. Work schedule can be up to ten (10) hours, but not starting prior to 7 am or approved through DNR Park & Rec staff.
5. Provide an electrical power company allowance of $3,000 in your lump sum price for utility company line extension.
6. Electrical service meter location shall be to the left side of the proposed garage door.
END OF ADDENDUM NO. 1