About this file
This document is an addendum to a Request for Information (RFI11736) issued by the South Dakota Department of Labor and Regulation (SDDLR) for a modernized Professional Licensing, Inspection, and Permitting System for a variety of Boards and Commissions under its purview. The addendum notifies vendors of an amended timeline, with the deadline for vendor inquiries extended to November 1, 2024, and the RFI response/submission due date pushed back to November 29, 2024. The purpose of the RFI is to gather information on industry approaches and solutions to develop, operate, and support this modernized licensing system, which may be used to develop a future request for proposal.
The addendum does not provide any additional details on pricing, set-asides, incumbents, funding sources, or other salient information beyond the timeline changes. Vendors were instructed to submit any questions to the designated email addresses, and those providing clear, concise information may be invited to make optional oral presentations to the state staff.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 1 -RFI Document.pdf | ||
| RFI Document.pdf | ||
| Response to Offeror Questions document.pdf | ||
| RFI Document.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Notification of Amended Timeframe and Schedule to RFI11736
Friday, November 8, 2024
Vendor Enquirers to RFI11736:
The purpose of this notification is to provide you with an update to the Timeframe and Schedule for RFI11736 that was originally issued October 21, 2024.
Due to the number of responses to RFI11736, SDDLR Board and Commissions Licensing, Inspection, Audit, and Permitting System, and the volume of questions submitted by vendors, DLR exercises its right to amend the Timeframe and Scheduling table found on page six of the RFI. The new schedule, as amended, will read:
Milestone Date
RFI Release Date October 21, 2024
Deadline for Vendor Enquiries November 1, 2024 11:59 p.m. CDT
State Response to Vendor Enquiries November 14, 2024 (date amended)
RFI Response/Submission Due Date November 29, 2024 11:59 p.m. CST (date amended)
Vendor Presentations (optional) TBD
This timeframe provides vendors with an additional two-weeks to submit an RFI submission from the original version’s date. All other conditions of the RFI remain in effect.