ADDENDUM 1 - D0SHV00004.pdf

PDF 219 KB Posted

Attached to
New Fire Alarm System Installation in Orange and Rockland Counties
Solicitation number
2113199
Issued by
Orange County, Rockland County, Cheektowaga CDP, New York

About this file

This is an Addendum (Addendum 1) issued by the New York State Office for People With Developmental Disabilities (OPWDD) for Project No. D0SHV00004, dated October 9, 2024. The addendum addresses missing drawings for Grove IRA and Greycourt SOIRA facilities that were initially released on August 27, 2024. Specifically, two sheets were missing from each set of drawings: Fire Alarm Battery Calculations (FA-4) and Fire Alarm Details (FA-5). The addendum requires the replacement of original drawings with revised versions for both facilities.

The addendum also specifies the removal of Electrical Note 13 from Drawing No. FA-3 in both revised drawing sets, which previously called for "PROVIDE PHOTOELECTRIC TYPE DUCT SMOKE DETECTORS WITH REMOTE TEST STATIONS." The OPWDD Contract Management Unit, located at 26 Center Circle, Wassaic, NY, is managing this modification to the project documentation.

View the file

Other files

File Type Posted
Q&A Memo - D0SHV00004.pdf PDF
Drawings - Grove IRA Revised.pdf PDF
CR Bid Results D0SHV00004.pdf PDF
Final Project Manual D0SHV00004.pdf PDF
Drawings -Greycourt SOIRA Revised.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OPWDD Contract Management Unit | eny.nyc.li.contracthub@opwdd.ny.gov

26 Center Circle, Wassaic, NY 12592 │ TEL: 845-877-6821 x3122, FAX: 845-877-3004 │www.opwdd.ny.gov

KATHY HOCHUL

Governor

WILLOW BAER

Acting Commissioner

October 9, 2024

ADDENDUM to Project No: D0SHV00004

Addendum 1 :

It was determined that the drawings for Grove IRA and Greycourt SOIRA, that were initially released on August 27, 2024 with the Project Manual for Project D0SHV00004, were each missing two sheets – Fire Alarm Battery Calculations (FA-4) and Fire Alarm Details (FA-5). As a result, these drawings are being re-released.

• Remove the document Drawings – Grove and replace with Drawings – Grove IRA Revised

• Remove the document Drawings – Greycourt and replace with Drawings – Greycourt SOIRA Revised

In the revised drawings listed above for Project D0SHV00004:

• Drawings – Grove IRA Revised: Drawing No. FA-3; Remove “Electrical Note 13. PROVIDE

PHOTOELECTRIC TYPE DUCT SMOKE DETECTORS WITH REMOTE TEST STATIONS.”

• Drawings – Greycourt SOIRA Revised: Drawing No. FA-3; Remove “Electrical Note 13. PROVIDE

PHOTOELECTRIC TYPE DUCT SMOKE DETECTORS WITH REMOTE TEST STATIONS.”

Respectfully, Rebecca Whitaker CMS 2, Contract Management Unit OFFICE: (845) 877-6821 ext. 3704 | FAX: (845) 877-3004 designandconstruction@opwdd.ny.gov mailto:eny.nyc.li.comtracthub@opwdd.ny.gov mailto:designandconstruction@opwdd.ny.gov