About this file

This document is an Addendum to Project No. D0SHV00004 issued by the Office for People With Developmental Disabilities (OPWDD) Contract Management Unit, Design and Construction, on behalf of the Hudson Valley DDSOO. The addendum states that the drawings for the Grove IRA and Greycourt SOIRA projects were missing two sheets, which are now being re-released. The revised drawings remove Electrical Note 13 related to duct smoke detectors.

The underlying state and local contract opportunity is for the installation of new fire alarm systems at 97 Thiells-Mt Ivy Rd, Pomona, NY 10970 and 55 Greycourt Rd, Chester, NY 10918, located in Orange and Rockland Counties, New York. Interested contractors must submit bids prior to the October 22, 2024 deadline. Mandatory site visits are scheduled for September 11 and 12, 2024. The selected low bidder will be responsible for providing various pre-award submittals. Prevailing wages will apply, and there are no set-aside or subcontracting goals specified.

View the file

Other files

File Type Posted
Final Project Manual D0SHV00004.pdf PDF
Drawings - Grove.pdf PDF
Q&A Memo - D0SHV00004.pdf PDF
Drawings -Greycourt.pdf PDF
Drawings -Greycourt SOIRA Revised.pdf PDF
Drawings - Grove IRA Revised.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OPWDD Contract Management Unit | eny.nyc.li.contracthub@opwdd.ny.gov

26 Center Circle, Wassaic, NY 12592 │ TEL: 845-877-6821 x3122, FAX: 845-877-3004 │www.opwdd.ny.gov

KATHY HOCHUL

Governor

WILLOW BAER

Acting Commissioner

October 9, 2024

ADDENDUM to Project No: D0SHV00004

Addendum 1 :

It was determined that the drawings for Grove IRA and Greycourt SOIRA, that were initially released on August 27, 2024 with the Project Manual for Project D0SHV00004, were each missing two sheets – Fire Alarm Battery Calculations (FA-4) and Fire Alarm Details (FA-5). As a result, these drawings are being re-released.

• Remove the document Drawings – Grove and replace with Drawings – Grove IRA Revised

• Remove the document Drawings – Greycourt and replace with Drawings – Greycourt SOIRA Revised

In the revised drawings listed above for Project D0SHV00004:

• Drawings – Grove IRA Revised: Drawing No. FA-3; Remove “Electrical Note 13. PROVIDE

PHOTOELECTRIC TYPE DUCT SMOKE DETECTORS WITH REMOTE TEST STATIONS.”

• Drawings – Greycourt SOIRA Revised: Drawing No. FA-3; Remove “Electrical Note 13. PROVIDE

PHOTOELECTRIC TYPE DUCT SMOKE DETECTORS WITH REMOTE TEST STATIONS.”