This Addendum 1 to an Abbreviated Request for Quotes (ARFQ) issued by the Texas Department of Transportation (TxDOT) modifies the original solicitation for Traffic Control Products under solicitation number TPK27-10. The addendum addresses traffic control equipment and related products necessary for roadway safety operations. The amendment provides clarifications, modifications, and additional requirements to the original RFQ specifications. Specific response deadlines and submission procedures are outlined within the addendum to ensure compliance with TxDOT procurement processes.
The addendum serves to update pricing terms, product specifications, or administrative requirements established in the original solicitation. Bidders are required to acknowledge receipt of this addendum and incorporate all modifications into their quotes. The document ensures that all prospective vendors are operating under identical, updated requirements and specifications for the traffic control products being procured by TxDOT.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
S – Addendum Number:
The Purpose of this addendum is to modify the solicitation identified as (“Agency Solicitation”) to reflect the change(s) identified and described below.
Applicable Addendum Category:
[ ] Modify bid opening date and time
[ ] Modify specification of product or service being sought
[ ] Attachment of vendor questions and responses
[ ] Attachment of pre-bid sign-in sheet
[ ] Correction of error
[ ] Other
Description of Modification to Solicitation:
This Addendum issued to publish and distribute the attached documentation to the vendor community.
Additional Documentation: Documentation related to this Addendum (if any) has been included herewith as Attachment A and is specifically incorporated herein by reference.
Terms and Conditions:
1. All provision of the Agency Solicitation and other addenda not modified herein shall remain in full force and effect.
2. Vendor should acknowledge receipt of all addenda issued for this Agency Solicitation by completing an Addendum Acknowledgement, a copy of which is included herewith. Failure to acknowledge addenda may result in bid disqualification. The addendum acknowledgement should be submitted with the bid to expedite document processing.
ARFQ TPK27*10
To supply answers to questions submitted by potential vendors.
Revised 04/21/2021
ADDENDUM ACKNOWLEDGEMENT FORM
SOLICITATION NO.:
Instructions: Please acknowledge receipt of all addenda issued with this solicitation by completing this addendum acknowledgment form. Check the box next to each addendum received and sign below. Failure to acknowledge addenda may result in bid disqualification.
Acknowledgment: I hereby acknowledge receipt of the following addenda and have made the necessary revisions to my proposal, plans and/or specification, etc.
Addendum Numbers Received:
(Check the box next to each addendum received)
[ ] Addendum No. 1 [ ] Addendum No. 6 [ ] Addendum No. 2 [ ] Addendum No. 7 [ ] Addendum No. 3 [ ] Addendum No. 8 [ ] Addendum No. 4 [ ] Addendum No. 9 [ ] Addendum No. 5 [ ] Addendum No. 10
I understand that failure to confirm the receipt of addenda may be cause for rejection of this bid.
I further understand that any verbal representation made or assumed to be made during any oral discussion held between Vendor’s representatives and any state personnel is not binding. Only the information issued in writing and added to the specifications by an official addendum is binding.
Company
Authorized Signature
Date
NOTE: This addendum acknowledgement should be submitted with the bid to expedite document processing.
AFRQ TPK27*10
ARFQ TPK27*10 ADDENDUM 1
The following questions were received in regards to ARFQ TPK27*10 (Traffic Control Products for WVPA).
Question 1. Is direct shipment from a manufacturer or distributor to WVPA’s designated locations acceptable, provided all contractual requirements are met?
Answer to Question 1. Yes, we can receive shipments directly from the manufacturer, however if there are any errors in the product received against what was ordered, it will be the vendor’s sole responsibility to have it corrected.
Question 2. Are the estimated quantities representative of annual purchasing volume?
Answer to Question 2. Yes estimated quantities are representative, but the awarded vendor must supply the actual quantities needed whether more or less than the estimate.
Question 3. What are typical quantities and frequency of individual purchase orders?
Answer to Question 3. The estimated quantities are the estimates on each commodity line in wvOASIS. The frequency of purchase orders is either monthly or bi-monthly.
Question 4. Can you provide the previous contract award, incumbent vendor, bid tabulation and historical purchase volume if available?
Answer to Question 4. This is not available, this is a new contract.
Question 5. Should the quoted unit prices remain the same across all required color combinations for each respective line item?
Answer to Question 5. Yes, the unit prices must remain the same for each color combination for each respective line item.
Question 6. What are WVPA’s standard payment terms following delivery and invoice acceptance?
Answer to Question 6. Refer to Section 5.5 in the specifications “Vendor shall accept payment in accordance with the payment procedures of the WVPA. In this case, vendor must submit an invoice to purchasing@wvturnpike.co m after all products have been delivered and invoicing follows delivery of products under the applicable order. If unable to email the invoice it can be mailed to the Accounts Payable Department at 3310 Piedmont Rd. Charleston, WV 25306