This is an Addendum to Bidder Questions and Answers for the Michigan State Police RFP #190000002692 for Student Emergency Planning Kits. The procurement involves the assembly, storage, and shipment of emergency planning kits to schools on a yearly basis, with approximately 10,000 kits ordered annually over a three-year contract term. The total quote request is for 30,000 kits; however, these will not all be ordered upfront but rather distributed across yearly orders as schools receive them. The kits include drawstring bags (not insulated), plastic whistles (blank without logo or attachment requirements), and flashlights (also blank without logo requirements). The awarded contractor will be responsible for assembling and storing the kits, shipping them to schools specified in yearly orders, and returning any remaining kits to Michigan State Police following annual distributions.
The contractor must submit yearly invoices for payment only after all kits have been shipped for that contract year. The addendum clarifies key product specifications and ordering procedures that differ from the original RFP specifications, requiring bidders to reference the revised RFP documentation when submitting bids. No specific pricing terms, set-asides, incumbent information, or funding source details are provided in this addendum document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| STEP Kits RFP revised 07092019.docx | DOCX document | |
| STEP Kits RFP.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Student Emergency Planning Kits Michigan State Police
RFP #190000002692
Bidder Questions and Answers
ADDENDUM #1
Question #1:
The drawstring bags are to be insulated?
Answer #1:
No. The drawstring bags are not required to be insulted. The RFP specifications will be updated to reflect this change. Bidders must use the revised RFP when submitting their bid response.
Question #2:
The plastic whistles are blank and do you need an attachment?
Answer #2:
Whistles do not require a logo or attachment.
Question #3:
Flashlight blank or does it need a logo?
Answer #3:
Flashlights do not require a logo.
Question #4:
The quote requested is for 30,000 so does that mean all 30,000 will be ordered and paid for and then released as needed for 3 years?
Answer #4:
No. Orders will be placed yearly, approximately 10,000 kits per year. Awarded Contractor will be required to assemble, store, and ship the kits to the schools specified in the yearly order, and ship any remaining kits to MSP. After all kits have been shipped, the Awarded Contractor may submit the yearly invoice for payment.