This is Addendum 1 to a Request for Quotation (RFQ) issued by the West Virginia Department of Tourism for bat exclusion work at the Culture Center (ARFQ TOR2700000007). The addendum addresses eight questions submitted by prospective proposers and clarifies solicitation requirements. An optional site visit is scheduled for November 23, 2026, at 11:00 AM at the West Virginia Culture Center, 1900 Kanawha Boulevard East, Charleston, WV 25305, with check-in at the Culture Center. Attendance at the site visit is not required to submit a bid, and vendors remain responsible for field-verifying all quantities and openings as specified in Exhibit B. Written answers to all questions will be posted by November 19, 2026, at 4:00 PM ET on wvOASIS and the West Virginia Tourism website. This addendum must be acknowledged and submitted with the bid to avoid disqualification.
The addendum clarifies that subcontracting is permitted, provided the prime contractor remains responsible for the entire contract and all subcontractors are named in the bid and comply with applicable licensing requirements, including West Virginia Division of Natural Resources Wildlife Damage Control Agent licenses where required by W.Va. Code 20-2-50a and 58 CSR 41. The prime contractor must hold a West Virginia contractor's license if the work falls under W.Va. Code 30-42-3(d), which applies to alterations, repairs, or improvements to buildings where the cost is $25,000 or more for commercial work. A named subcontractor's experience and technical qualifications may satisfy requirements in Sections 3.1.4 through 3.1.6. Payment is made in arrears on proper invoices for satisfactorily completed and accepted services, with the total bid paid in one payment after final acceptance; the State does not pay in advance. Vendors are required to acknowledge receipt of all addenda, as failure to do so may result in bid disqualification.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUOTATION
WEST VIRGINIA DEPARTMENT OF TOURISM
CULTURE CENTER - BAT EXCLUSION
ARFQ TOR2700000007
Addendum One - Agency Response to Questions
This Addendum is issued to clarify and supplement the original Request for Quotations (RFQ). The questions below were submitted in writing by prospectiveproposers,andtheresponsesareprovidedto ensure consistent interpretation of the solicitation.
Responses to written questions shall become part of the RFQ and be binding upon proposers. All proposers are responsible for reviewing this Addendum and incorporating the clarificationshereininto their proposals.
Except as expressly modified by this Addendum, all terms, conditions, and requirements of the RFQ remain unchanged and in full force and effect.
Question 1 IhadafewquestionsinregardstotheQuoteRequestontheBatExclusionattheCultureCenterifyou could give me a call, please
Agency Answer:
Thankyouforyourinterestinthissolicitation.Totreatallbiddersequally,theAgencyanswersquestions inwritingandshareseveryanswerwithallvendors.Answerstothequestionsreceivedwillbepostedin wvOASIS and at https://wvtourism.com/purchasing/ by November 19, 2026, at 4:00 pm ET. Please review that addendum before you submit your bid.
Question 2 Will vendors be allowed to do an inspection prior to submitting the bid?
Agency Answer:
TheAgencywillholdanoptionalsitevisitattheWestVirginiaCultureCenter,1900KanawhaBoulevard East,Charleston,WV25305,onNovember23,2026, at11:00AM.AttendeesshouldcheckinatCulture Center.Attendanceisnotrequiredtobid.Statementsmadeduringthevisitdonotchangethesolicitation;
onlyawrittenaddendumdoes.Vendorsremainresponsibleforfield-verifyingallquantitiesandopenings, as Exhibit B requires.
Question 3 Wouldanon-siteinspectionbepermitted?Ifso,pleaseletusknowtheavailabledateandtime,check-in location, and any attendee information or forms required for access.
Agency Answer:
TheAgencywillholdanoptionalsitevisitattheWestVirginiaCultureCenter,1900KanawhaBoulevard East,Charleston,WV25305,onNovember23,2026, at11:00AM.AttendeesshouldcheckinatCulture Center.Attendanceisnotrequiredtobid.Statementsmadeduringthevisitdonotchangethesolicitation;
onlyawrittenaddendumdoes.Vendorsremainresponsibleforfield-verifyingallquantitiesandopenings, as Exhibit B requires.
Question 4 Istheprimecontractorpermittedtoutilizequalifiedandlicensedsubcontractorstoperformtheentiretyof the fieldwork while retaining responsibility for contract management and quality assurance?
Agency Answer:
The solicitation does not prohibit subcontracting. Thevendorthatsignsthebidremainsresponsiblefor performing the entire contract, including work its subcontractors perform. Before a subcontractor performs any work, the vendor must notify itthatitmustcomplywithapplicablelawsandbelicensed and in good standing. Each individual who performs wildlife damage control work must hold a West Virginia Division of Natural Resources Wildlife Damage Control Agent license when W. Va. Code §20-2-50a and 58 CSR 41 require one. Vendors that will use subcontractors should name each subcontractor and the work it will perform in their bid.
Question 5 Can the experience and technical qualifications of our proposed subcontractor satisfy therequirements outlined in Sections 3.1.4 through 3.1.6?
Agency Answer:
Yes, if the subcontractor is named in the bid and will perform the work the requirement covers. For Sections3.1.4through3.1.6,"Vendor"includesasubcontractoridentifiedinthebidthatwillperformthe work to which the requirement applies. The vendor remains responsible for all work under the contract.
Question 6 IstheprimecontractorrequiredtoholdaWestVirginiacontractor'slicenseifthefieldworkisperformed by appropriately licensed subcontractors?
Agency Answer:
The specifications do not list a West Virginia contractor license as a mandatory requirement, buteach vendor must comply with West Virginialicensinglaw.UnderW.Va.Code§30-42-6(a),nopersonmay engage in contracting or submit a bid to perform work as a contractor without a license issued under Article 42, and a firm may not engage in contracting unless one of its officersholdsalicense.W.Va.
Code §30-42-3(d) definesacontractortoincludeapersonwhosubmitsabidtoalter,repairorimprove any building where the cost of the undertaking is $25,000 or more for commercial work. Becausethe requirement applies to the firm that submits the bid, a licensed subcontractor doesnotsatisfyitforan unlicensed prime when the work falls within Article 42. Vendors unsurewhethertheirworkrequiresa license should contact the West Virginia Contractor Licensing Board before bidding.
Question 7 Would it be possible to coordinate a site visit with our proposed subcontractor before the submission deadline?
Agency Answer:
TheAgencywillholdanoptionalsitevisitattheWestVirginiaCultureCenter,1900KanawhaBoulevard East,Charleston,WV25305,onNovember23,2026, at11:00AM.AttendeesshouldcheckinatCulture Center.Attendanceisnotrequiredtobid.Statementsmadeduringthevisitdonotchangethesolicitation;
onlyawrittenaddendumdoes.Vendorsremainresponsibleforfield-verifyingallquantitiesandopenings, as Exhibit B requires.
Question 8 Will progress payments be permitted for completed and accepted phases of the project?
Agency Answer:
Payment ismadeinarrears,onaproperinvoice,forservicessatisfactorilycompletedandaccepted,and finalpaymentissubjecttofinalacceptanceofthework.TheStatedoesnotpayinadvance.TheAgency will pay the Total Bid in one payment after final acceptance under §12.5.
Instructions: Please acknowledge receipt of all addenda issued with this solicitation by completing this addendum acknowledgment form.
Failure to acknowledge addenda may result in bid disqualification.
● Addendum 1 -Agency Answers to Vendor Questions
I understand that failure to confirm the receipt of addenda may be cause for rejection of this bid. I further understand that any verbal representation made or assumed to be made during any oral discussion held between Vendor’s representatives and any state personnel is not binding. Only the information issued in writing and added to the specifications by an official addendum is binding.
Company
Authorized Signature
Date
NOTE: This addendum acknowledgment shall be submitted with the bid to expedite document processing.