Addendum 1 - ABSD - Boilers & HW Pumps RFP Phase 3.pdf

PDF 303 KB Posted

Attached to
Boiler Phase 3 State and local contract opportunity
Solicitation number
RFQ ABS 260000000382 2
Issued by
Wayne County, Michigan

About this file

This is an addendum to a Request for Proposal issued by Anchor Bay School District for an Energy Savings Performance Contract focused on boiler and hot water pump upgrades in Phase 3. The RFP seeks proposals from contractors to upgrade boilers and hot water pump systems across the district's facilities. Bids are due at the district's Administrative Office no later than 1:00 PM local time on July 29, 2026. The original bidding documents were dated July 6, 2026, and this Addendum No. 1, issued on July 15, 2026, provides clarifications and modifications to those documents. All prospective bidders are required to acknowledge receipt of this addendum in the space provided on the Bid Form, with failure to do so potentially resulting in bid rejection.

Addendum No. 1 primarily updates the mechanical, electrical, and plumbing (MEP) drawings, specifically replacing the July 6, 2026 Construction Document set with revised drawings dated July 10, 2026 for Lottie Schmidt Elementary School, including updated drawings E-100 and E-500. Where any provisions in this addendum conflict with the original RFP bidding documents, the addendum requirements take precedence. The contracting entity is Centrix Energy, located in Sun Prairie, Wisconsin, which is identified as the project contact.

View the file

Other files for this state and local contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Anchor Bay School District – Energy Savings Performance Contract

Boiler & Hot Water Pump Upgrades - Request for Proposal – Phase 3 – Addendum No. 1

Centrix Energy 792 Lois Dr Sun Prairie, WI 53590

(817) 506-8303

July 15, 2026

TABLE OF CONTENTS

ADDENDUM NO. 1

OVERVIEW

MODIFICATIONS AND CLARIFICATIONS

ATTACHMENTS

Revised MEP Drawings – Addendum #1

ADDENDUM NO. 1

Project: Anchor Bay School District – Energy Savings Performance Contract

Boiler(s) & Hot Water Pump(s) Upgrades Phase 3 – Addendum 1

TO: All Prospective Bidders/Contractors

DATE: July 15, 2026

RE: Addendum No. 1 – Clarifications and Modifications

OVERVIEW

This Addendum No. 1 is incorporated into the original Bidding Documents dated July 6, 2026, for the above-referenced project. The purpose of this addendum is to clarify, revise, and/or supplement the bidding documents as noted below. As stated in the original RFP, bids are to be received at the district’s Administrative Office, no later than 1:00PM (local time) on July 29, 2026.

All bidders shall acknowledge receipt of this Addendum No. 1 in the space provided on the Bid Form. Failure to acknowledge receipt of this addendum may result in rejection of the bid.

Where any item in this addendum conflicts with the original Request for Proposal (RFP) bidding documents, the requirements of this addendum shall govern and take precedence.

MODIFICATIONS AND CLARIFICATIONS

1. Updated MEP drawings

a. Addendum #1 drawings (dated 07/10/2026) to replace 07/06/2026 CD Set drawings, specifically for the following school:

i. Lottie Schmidt Elementary School

1. Drawing E-100

2. Drawing E-500

ACKNOWLEDGEMENT – ADDENDUM NO. 1

All bidders must acknowledge receipt of this Addendum No. 1 by signing and returning this form with their bid submission, or by noting receipt of this addendum in the space provided on the Bid Form.

Company Name: _____________________________________________________________

Authorized Signature: __________________________________________________________

Printed Name: ________________________________________________________________

Date: ________________________________________________________________________

END OF ADDENDUM NO. 1

File details come from the government source that posted it. Updated .