Addendum 1 751-26612.MAA.pdf

PDF 216 KB Posted

Attached to
751/26612. MAA; Various Dams - Engineering Studies
Solicitation number
RFP 171 270000000169 2
Issued by
Presque Isle County, Michigan

About this file

This Addendum No. 1 is issued by the Michigan Department of Technology, Management and Budget (DTMB), State Facilities Administration Design and Construction Division, on behalf of the DNR Fisheries Division for engineering services related to two dam projects. The DNR is requesting a Phase 100 Engineering Study to evaluate removal, repair, and rebuild alternatives for Tomahawk Creek Dam in Presque Isle County and Hoister Lake Dam in Gladwin County. The study must investigate the pros and cons of each alternative, develop cost estimates, and provide engineering recommendations aligned with the Fisheries Division's operational and management goals. Following Phase 100 completion, the DNR will request cost proposals for Phase 300-700 services encompassing engineering plan development and construction administration. The Phase 100 Study must include full topographic surveys of embankments, inlet structures, downstream longitudinal profiles, and representative cross-sections. For Tomahawk Dam, surveys must document elevations at the boat launch facility to correlate water levels with pool elevations and infrastructure impacts. The proposal due date is December 3, 2026, at 2:00 p.m., with responses required through the SIGMA VSS portal. Firms are encouraged to combine technical and cost proposals into a single attachment with each dam broken out by phase and totaled, followed by a grand total for both dams.

Proposers must submit the total cost for all phases as the bid amount, with attachments not exceeding 25 megabytes. Key clarifications address sedimentation management per Eagle Dam Safety guidelines, the Tomahawk dam's closed bottom draw system with seepage-only water flow, videoing of corrugated metal pipes on both dams to assess useful life expectancy, and the requirement for full drawdown capability on both dams for maintenance purposes. The Hoister project must preserve bottom draw for trout while minimizing warm water discharge downstream, and the study must remain unbiased with accurate cost estimates given the planned removal of Trout Lake Dam. Critical unknowns requiring consultant investigation include the status of subsidence at the Hoister Dam crest noted in a 1988 inspection, the existence of any current low spots in the crest, and whether further inspections have documented changes. Consultants must verify the accuracy, extent, and dates of existing topographic data from EGLE dam safety inspection reports, as only data shown on existing plans and inspection reports is available from the Michigan DNR.

View the file

Other files

File Type Posted
Project Statement 26612.pdf PDF
Billable Rate 26612.pdf PDF
SAMPLE Billable Rate Contract (Rev 04-25).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 RFP (Rev 2/22)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration Design and Construction Division

REQUEST FOR PROPOSAL

ADDENDUM NO. 01

This form identifies an Addendum to a Request for Proposal for Professional Services, and incorporates interpretations or clarifications, modifications, and other information into the Request for Proposals. Addenda will be numbered by the Project Director and distributed through SIGMA Vendor VSS as an attachment.

TO:

ALL PROPOSERS

DATE ISSUED

11/13/2026

PROJECT NAME

Tomahawk Dam – Presque Isle and Hoister Dam, Gladwin Co.

FILE NUMBER

751/26612.MAA

PROJECT DIRECTOR

• Maria Alvaro, RA , LEED AP

PROPOSAL DUE DATE:

December 3, 2026 @ 2:00pm

REWRITTEN PROJECT DESCRIPTION/SERVICES REQUESTED:

DNR Fisheries is requesting a Phase 100 Engineering Study on Tomahawk Creek Dam, Presque Isle County (T33N, R02E, S27) and Hoister Lake Dam, Gladwin County (T20N, R02W, S.8&9). The purpose of this study is to evaluate the removal, repair, and rebuild alternatives for each dam. The study should investigate the pros and cons of each alternative, develop cost estimates for each alternative, and provide an engineering recommendation based on the operational and management goals of Fisheries Division. Following the successful completion of the Phase 100 Study, the DNR is requesting cost proposals for Phase 300-700 services for the Development of Engineering plans and construction administration services for the selected alternative.

The Phase 100 Study should include full topographic survey of the embankment and inlet structure and include downstream longitudinal profile and at least one representative bank full cross section.

For Tomahawk Creek Dam, the topographic survey should include elevation information for the boat launch including elevations at the bottom of the concrete launch ramp, top of concrete launch ramp and for the limits of the asphalt paved parking lot and entrance drive. The purpose of this survey is to correlate water levels for varying levels of pool elevations versus existing infrastructure at the boating access site. Any proposed outcome of the dam should consider impacts to the boating access site.

Please NOTE:

• Proposal responses MUST be uploaded to SIGMA VSS.

https://sigma.michigan.gov/webapp/PRDVSS1X1/Advantage4

• Please enter the total cost for all phases as the bid amount.

• Firms are encouraged to combine their technical and cost proposals into one (1) attachment for proposal submission, with each dam broken out by Phase and totaled, then a grand total of both dams.

• Please remember that attachments can be no larger than 25mb.

http://www.buy4michigan.com/ https://sigma.michigan.gov/webapp/PRDVSS1X1/Advantage4

751.26612 Tomahawk and Hoister Damn Clarifications and Questions

1. Sedimentation Management per Eagle Dam Safety 315

2. Tomahawk – existing bottom draw system is anticipated to be fully closed. The assumption is that all water flowing through the dam is from seepage.

3. Two existing dam safety bills have currently been passed by the House and Senate, but they are different. As these bills become resolved, the consultant shall ensure that any applicable regulatory impacts in incorporated in their documents,

4. Tomahawk and Hoister - Video corrugated metal pipes on both dams for useful life expectancy.

Video of Tomahawk is expected only for principal conduct; bottom draw conduit is assumed to be inaccessible.

5. Tomahawk and Hoister -Must be able to do a full draw down on both dams for maintenance.

6. Hoister – preserve bottom draw for Trout. Not sure if it is working. Must minimize warm water discharge downstream.

7. Hoister – No evidence elevation change.

8. Hoister - Trout Lake Dam is being removed; therefore, The study of Hoister must be non-biased and must have accurate cost estimates and clear delineation of advantages and disadvantages of each option.

9. What topographic data is available at each site from MI DNR? Only data shown on existing plans and EGLE dam safety inspection reports.

10. What is the extent, accuracy, and date of these surveys? Information on plans must be verified by consultant.

11. Does MI DNR anticipate the need for an initial topographic survey to proceed with the Phase 100 study. Yes.

12. Was the subsidence at the Hoister Dam crest over the outlet works noted in the 1988 inspection ever repaired? Unknown

13. Is there still a low spot in the crest at Hoister Dam? Unknown

14. Have further inspections Hoister of this location noted any changes to this subsidence?

Unknown

APPROVED BY: Maria Alvaro, Eric Cadeau, Doug Schultz

PROJECT DIRECTOR : Maria Alvaro DATE: 11/13/2026

File details come from the government source that posted it. Updated .