This document is an Addendum to a bid for the 6th Street at Bank Street Parking Lot project in Griffin, Georgia. The scope of work involves rehabilitating the parking lot, including completing full-depth reclamation (FDR) and installing new curb and gutter to frame the parking spaces, row-end planting areas, and a center island with planting. The street side of the parking lot will also receive curb and gutter. All milled materials will remain the property of the City of Griffin, and the contractor will need to coordinate the dumping location. There are overhead power lines and two poles on-site, and the contractor is responsible for coordinating with Griffin Electric to remove and replace the light poles during construction.
The contract opportunity is being issued by Spalding County, Georgia. Pricing terms, set-asides, incumbent information, funding requirements, and other salient details are not provided in the given documentation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 24_008 _ Sign In Sheet.pdf | ||
| 24_008 _ 6th Street _ Pre_Bid Sign in Sheet.pdf | ||
| Addendum 2 bid _ 24_008 _ 6th at bank st park.docx | DOCX document | |
| Addendum 3 bid _ 24_008 _ 6th at bank st park.docx | DOCX document | |
| NOIA (Notice of Intent to Award)_ 6th Street .pdf | ||
| 6th St _ Bank St_ Parking Lot Bid.docx | DOCX document | |
| 6th Street Parking Lot _ Bid Results.xlsx | XLSX spreadsheet | |
| 24_008 Bid Results.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum #1 6th Street at Bank St Parking Lot Bid # 24-008
Good afternoon, Sherri, quick question on the 6th St lot bid. I didn’t see anything with barrier gate arms. Did I miss it? Thanks, and let me know if you would like any gated or gateless solutions.
There will be no barrier gate arms, or gates on parking lot