Addendum 1 54-TJK-08-PR39943 (Questions and Answers).pdf
PDF 42 KB Posted
- Attached to
- 54-TJK-08-PR39943, CUSTODIAL OPERATIONS AND MAINTENANCE OF REST AREAS/VISITOR INFORMATION CENTERS
- Solicitation number
- 54-TJK-08-PR39943
- Issued by
- Richmond County, North Carolina
About this file
This addendum to the North Carolina Department of Transportation solicitation 54-TJK-08-PR39943 provides clarifications and answers to vendor questions regarding custodial operations and maintenance of rest areas and visitor information centers in Randolph County, Division 8. The scope of work encompasses janitorial and grounds maintenance services for northbound and southbound rest area facilities on Interstate 73/74 near Seagrove. The solicitation requires 16 paid attendant hours per site during winter months (7:00 AM to 10:00 PM with overlapping shifts) and includes twelve additional eight-hour shifts per site annually, totaling 192 contract hours. Bidders are encouraged to conduct their own site observations to determine specific quantities of restroom fixtures, building square footage, and cleanable areas. The written question deadline was September 23, 2026, with the solicitation opening scheduled for October 7, 2026 at 2:00 PM ET. The contract term runs for one year (January 1, 2027 through December 31, 2027) with renewal options for two additional one-year periods at the State's discretion, subject to a 2 percent price increase for extensions.
The previous contract amount was $349,886.52 annually. Consumption history provided includes annual averages of 1,500 rolls of paper towels, 14,000 rolls of toilet paper, 250 gallons of soap, 8,000 bags of liners, 170 gallons of all-purpose disinfectant, and 170 gallons of glass cleaner. Both sites contain two 8-yard capacity dumpsters with varying collection frequencies: garbage is collected twice weekly May through September and once weekly October through April, while recycling is collected twice monthly during summer and once monthly during winter. Supervisory hours are entirely additional to attendant hours, except for a maximum four-hour emergency substitution provision. Breaks and meals are paid, with employees required to schedule breaks separately when multiple staff are on duty. Roll-up garage storage facilities are available at both sites for emergency inventory storage of ten cases of paper towels per site.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 54-TJK-08-PR39943 Randolph I-73&74 (pair) Janitorial Proposal 2027.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
JOSH STEIN DANIEL H. JOHNSON
GOVERNOR SECRETARY
NCDOT Non-Mandatory Addendum Version Date: 1/2025
Page | 1
SOLICITATION ADDENDUM
THIS ADDENDUM DOES NOT NEED TO BE RETURNED.
1. The following are questions received about the Solicitation and the State’s response to those questions:
Question
Vendor Question State’s Response
1 The RFP states winter staffing is 7:00 AM – 10:00 PM, or 15 hours, but the two stated shifts overlap and total 16 paid hours. Should bidders price 15 or 16 attendant hours per site per winter day?
The bidders should price 16 attendant hours per site.
2 Are the twelve additional eight-hour shifts required per site, resulting in 192 total contract hours for the pair.
Yes, these shifts are required per site.
3 Please provide the current quantities and specifications for restroom fixtures, including toilets, urinals, sinks, soap dispensers, and toilet-paper dispensers at each site.
As specified on page 5, the Bidder is encouraged to make his/her own observations of the site.
4 Please provide the previous 12 months of paper towel, toilet paper, soap, liner, and chemical consumption, if available.
The following is an average per year:
Paper Towel: 1,500 rolls Toilet Paper: 14,000 rolls Soap: 250 gallons Liners: 8,000 bags All Purpose Disinfectant: 170 gallons Glass Cleaner: 170 gallons
Issuing Agency: Department of Transportation
Solicitation Number: 54-TJK-08-PR39943
Solicitation Description: Custodial Operations and Maintenance of Rest Areas/Visitor Information Centers – Division 8 – Randolph County
Solicitation Opening Date and Time: October 7, 2026, at 2:00 PM ET
Addendum Number: 1
Addendum Date: September 25, 2026
Procurement Specialist: Teddy Kapera
Solicitation Number:
Addendum Number:
NCDOT Non-Mandatory Addendum Version Date: 1/2025
Page | 2
Question
Vendor Question State’s Response
5 Please provide the current dumpster sizes, collection frequency, and average monthly waste and recycling volume.
On both sites, there are two dumpsters, one for garbage and one for recycling.
Current dumpster size: 5’ L x 6’ W ‘ 7’ H (8-yard capacity).
Collection frequency: May-September, garbage is collected twice/week, recycling twice/month.
October – April, garbage is collected once/week, recycling once/month.
6 Please clarify whether the supervisor’s 40 onsite hours are entirely additional to attendant hours and whether supervisory time may ever satisfy normal attendant staffing requirements outside the stated four-hour emergency substitution provision.
Per page 17, the supervisor may be allowed to work for one absent attendant for a maximum of four (4) hours, allowing time for a replacement attendant to report for work. The daily work schedule shall reflect the absent attendant and time worked by the supervisor. The Contractor’s attention is directed to time worked on a shift as attendant, this time shall not be considered as supervisory time.
7 Please provide the previous contract amount and any available compensation -reduction history.
Previous contract amount was $349,886.52.
8 Please clarify whether employees’ meals and breaks are paid and whether attendants may remain responsible for coverage during those periods.
Per page 16, the Contractor shall generate a designated break and meal schedule for all employees that shall be posted in the service room of each facility. At any time, there is more than one
(1) staff member scheduled for duty, breaks and meals shall be taken separately. The current contractor pays for breaks but requires employees to remain attentive if needed.
9 Please identify any known equipment, plumbing, dispenser, door, lighting or building repairs expected when the new contract begins.
Paper towel dispensers are currently being repaired, along with entrance doors.
10 Please confirm whether there is any available storage capacity limitation for the required ten-case-per-site paper towel emergency inventory and other supplies.
Yes, there are roll-up garage storage facilities at both sites.
11 What is the current contract value for this service annually?
$349,886.52.
12 Could you please confirm the total number of restrooms included in the scope of work and the total restroom square footage a cross both sites?
As specified on page 5, the Bidder is encouraged to make his/her own observations of the site.
13 What is the total square footage of all buildings covered under this contract across the Northbound and Southbound sites?
As specified on page 5, the Bidder is encouraged to make his/her own observations of the sites.
14 We refer to the above -referenced solicitation and would appreciate it if you could provide us with the complete cleanable square footage details, along with the value of the previous contract.
As specified on page 5, the Bidder is encouraged to make his/her own observations of the site.