This is a Construction Bid Addendum No. 1 issued by the Michigan Department of Technology, Management and Budget (DTMB), State Facilities Administration, Design and Construction Division for the Saginaw Correctional Facility (SRF) Warehouse Concrete Repair project. The project involves concrete repair work with a 60-day completion timeline, anticipated to be finished by mid-November 2025. The bid opening is scheduled for 8/20/2025, and the project requires adherence to specific conditions including work hours from 7:00 a.m. to 4:00 p.m. Monday through Friday, prevailing wage requirements, and specific site conditions such as hydrovac use in expansion areas and removal of 2-feet of asphalt on the north side to create a smooth edge for new concrete pouring.

Key project details include liquidated damages of $500 per day, no permit requirements (though SESC measures must be followed), and specific insurance and contractor preferences such as builder's risk insurance and qualified disabled veteran contractor preference. Material testing will be provided through the PSC's contract, and hydroseed can be used for site restoration. Bidders are required to submit LEO state project registrations and an unsigned blank asbestos attestation page with their bid, even if the project does not involve asbestos abatement. The project will involve concrete removal from the site and requires 100% on-site contractor supervision throughout the work period.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 (Rev 12/17)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration Design and Construction Division

CONSTRUCTION BID ADDENDUM NO. 1

This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.

TO:

ALL BIDDERS

DATE ISSUED

8/14/2025

PROJECT NAME

Saginaw Correctional Facility (SRF), Warehouse Concrete Repair

FILE NUMBER

472/25271.CTS

PROFESSIONAL

Beckett & Raeder, Inc.

PROJECT DIRECTOR

Chris Schanbeck

BID OPENING DATE:

8/20/2025

ADDENDUM ITEMS:

Pre-Bid Walk-Through Notes:

1. Contractor has 60 days to complete the work, anticipated completion date is mid-November.

2. Liquidated damages are $500/day.

3. No permits required, however, contractor to adhere to SESC measures shown on the drawings.

4. Prevailing wage requirements apply and are attached to this addendum.

5. Work hours 7:00 a.m. to 4:00 p.m., Monday through Friday. Work outside those hours and days requires special permission.

6. Material testing shall be provided through the PSC’s contract – not the contractor.

7. Qualified disabled veteran contractor preference applies.

8. The contractor is required to provide Builder’s Risk insurance.

9. Hydrovac to be used in areas of expansion – this cost shall be included in Add Alternative #1.

10. Hydroseed can be used.

11. Concrete will need to be removed from the site.

12. Bidder shall assume that 2-feet of asphalt will need to be cut and removed (north side) to create a smooth edge to pour the new concrete.

This new 2-foot gap would be concrete.

Sign-In Sheets:

13. Pre-Bid Sign-In Sheet from the mandatory walk-through is attached.

ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.

PROFESSIONAL: Kristofer Enlow, P.E., Beckett & Raeder, Inc. DATE: 8/14/2025