Addendum 1 25_012_075.pdf

PDF 120 KB Posted

Attached to
HVAC and Roofing Replacement for Brooks Elementary School (IFB 25-012-075)
Solicitation number
PE-65615-NONST-2025-000000043
Issued by
Dodge County, Georgia

About this file

This document is an Addendum to the Invitation for Bids (IFB) for the Brooks Elementary School Reroofing & HVAC Replacement project in Fayette County, Georgia. The project involves the reroofing and HVAC system replacement at the Brooks Elementary School. The addendum modifies the original bid documents, including changing the bid due date from October 16, 2024 to October 30, 2024, deleting the Preliminary Construction Schedule section, and revising the Bid Form. The construction schedule provides specific dates for key project milestones, such as the start of work on May 27, 2025, Substantial Completion of the reroofing and HVAC work by November 21, 2025, and Final Completion by December 5, 2025.

The Bid Form includes a Base Bid amount and Unit Prices for potential changes to the work, such as steel roof deck remediation, deck refinishing, deck refastening, and repair of cementitious or lightweight concrete decks. The document also includes a $200,000 Contingency Allowance to be included in the Base Bid. Bidders must acknowledge receipt of this Addendum on the Bid Form, and failure to do so may result in disqualification.

View the file

Other files

File Type Posted
IFB 25_012_075.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BROOKS ELEMENTARY SCHOOL REROOFING

& HVAC REPLACEMENT ADDENDUM ONE

BRPH ARCHITECTS-ENGINEERS, INC.

C08154.002.00 page 1

10-8-24

This Addendum is hereby made a part of the Contract Documents on the subject work as though originally included therein. The following clarifications, amendments, additions, deletions and/or modifications to the Specifications and Drawings change the original documents only in the manner and the extent stated. The bidder shall take care to coordinate modifications herein with all trades and disciplines related to the work. The Bidder shall acknowledge receipt of this Addendum on the Bid Form by Addendum number. Failure to do so may subject Bidder to disqualification.

PART I - PERTAINING TO THE PROJECT MANUAL

I-A. Section 00 11 16 – Invitation to Bid:

1. Change date of receipt of bid from “16 October 2024” to “30 October 2024”.

I-B. Section 00 31 13 – Preliminary Construction Schedule: Delete this section in its entirety and attached Section 00 31 13 – Preliminary Construction Schedule, page 1 last revised 10-08-24.

I-C. Section 00 41 13 – Bid Form: Delete page 00 41 13 -1 in its entirety and add attached page 00 41 13 -1 last revised 10-08-24.

End of Addendum One

& HVAC REPLACEMENT PRELIMINARY CONSTRUCTION SCHEDULE

BRPH ARCHITECTS-ENGINEERS, INC

C08154.002.00 00 31 13 - 1

09-17-24

Revised 10-08-24

SECTION 00 31 13 – PRELIMINARY CONSTRUCTION SCHEDULE

A. Description: A Construction Schedule for the project is provided herein. This schedule includes specific dates shown in Items 1 through 14. Dates for Items 1 through 3 may be considered preliminary until such time as Item No. 5 "Contract Award" is made.

1. If all dates for Items 1 through 5 are maintained, then the dates for Items 6 through 14 become a fixed Construction Schedule.

2. If any dates of Items 1 through 5 slide forward, then all subsequent dates, except Item 10, shall move forward by the same number of days that Item 5 misses its presently noted schedule.

3. The schedule dates for the project shall be strictly adhered to and are the last acceptable dates unless they are modified by mutual consent of the Owner and the Contractor by written change order. All dates indicate 11:59 PM unless otherwise stipulated.

B. Schedule:

1. Advertisement Date: .................................................. 17 September 2024

2. Issuance of Bidding Documents: .................................. 17 September 2024

3. Deadline for Submission of Prior Approvals:....... 2117 October 2024, 4:00 PM

4. Deadline for Submission of Bidders Questions: ... 2339 October 2024, 4:00 PM

5. Bid Date & Time:........................................... 30 16 October 2024, 2:00 PM

6. Notice of Award and Contract Agreement Date: 19 November22 October 2024

7. Receipt of Bond and Insurance: ..................... 22 November28 October 2024

8. Notice to Proceed and Start of Contract Time: . 22 November28 October 2024

9. Pre-Construction Conference: ................................. 13 May 2025, 11:00 AM

10. Begin Work at Site: .............................................................. 27 May 2025

11. Substantial Completion (Excluding Multi-Zone HVAC Units): ...... 22 July 2025

12. Substantial Completion (Multi-Zones Units): ................... 21 November 2025

13. Delivery of Final Documents ......................................... 22 November 2025

14. Final Completion ........................................................... 5 December 2025

END OF SECTION 00 31 13

& HVAC REPLACEMENT BID FORM

BRPH ARCHITECTS-ENGINEERS, INC

C08154.002.00 00 41 13 - 1 09-17-24 Revised 10-08-24

SECTION 00 41 13 - BID FORM

DATE: 3016 October 2024

TIME: 2:00 PM

Fayette County School District 210 Stonewall Avenue Fayetteville, Georgia 30214

Gentlemen:

1. Having carefully examined the Contract Documents entitled “Brooks Elementary

School – Reroofing & HVAC Replacement" last revised 16 September 2024, all as prepared by BRPH Architects-Engineers, Inc., Atlanta, Georgia and Addenda No(s)_____, as well as the premises and conditions affecting the work, the undersigned proposes to furnish all service, labor and materials called for by them for the entire work, in accordance with said Documents, for the sum of:

_______________________________________ Dollars ($ ) which sum is hereafter called the "Base Bid."

2. Unit Price: For changing quantities of work items from those indicated by the Contract Documents upon written instructions from the Architect, the undersigned further proposes the following unit prices shall prevail:

Roof Substrate Remediation Related:

Description Included

Quantity Unit

Cost Included

Allowance

Steel Roof Deck: 25 Sheets X $/Sheet = $

Refinish Existing Deck: 500 SF X $/SF = $

Refasten Existing Steel Deck

1,000 Locations X $/Location = $

Repair Cementitious or Lightweight Concrete Decks:

50 Bags X $/Bag = $

Total Unit-Price Allowances to be included in Base Bid: $

Contingency Allowance: $ 200,000.00

Total Allowances to be included in Base Bid: $

a. The above unit prices shall include all labor, materials, and incidentals, but shall not include overhead and profit, to cover finish work of the several kinds called for. Changes shall be processed in accordance with the Contract for Construction and the Conditions of the Contract.

3. For and in consideration of the sum of $1.00, the receipt of which is hereby acknowledged, the undersigned agrees that this bid may not be revoked or withdrawn after the time set for the opening of bids but will remain open for acceptance for a period of forty-five days following such time.