About this file

This document is an addendum to a Request for Qualifications (RFQ) issued by the City of Fairburn, Georgia for Construction Management At-Risk Services. The addendum provides clarification on the project delivery method, which states that the project will employ the services of a Design Professional and a Commissioning Agent, in addition to a Construction Manager/General Contractor (CM/GC). The addendum also confirms that the Commissioning Agent will be hired by the Designer, while the third-party inspector will be hired by the City of Fairburn.

The RFQ seeks qualified firms or individuals to provide Construction Management At-Risk Services for the City of Fairburn, located in Fulton County, Georgia. The scope of services and project details are provided in the original RFQ document. The addendum does not include any information on pricing terms, set-asides, incumbents, funding requirements, or sources.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

City of Fairburn

RFQ 24-011 Construction Management at Risk Services

Addendum #1

This addendum supersedes and supplements all portions of the bidding documents and becomes part of the contract documents for the above-referenced project.

Where any item called for in the specifications or indicated on the drawings is supplemented hereby, the original requirements shall remain in effect.

Where any original item is amended, voided or superseded hereby, the provision of such item not so specifically amended, voided or superseded shall remain in effect.

Clarification of Bidder Questions:

1. Will you be providing a form to fill out the requested pricing for each phase, along with estimates and allowances pricing if needed? Yes, if needed this will provided, attached is the current space summary information.

2. The project delivery method states that the Project will be construction management at-risk/general contractor (CM/GC), and, at a minimum, will employ the services of a Design Professional and a Commissioning Agent, in addition to the services of a CM/GC. Could you please clarify this statement? Typically, the Commissioning Agent is hired by the Designer. Is the General Contractor responsible for hiring a third-party inspector?

Commissioning Agent will by hired by the Designer. The third-party inspector will be hired by the City of Fairburn.