Addendum 1 22335.pdf
PDF 252 KB Posted
- Solicitation number
- RFP - 171 - 220000003043
- Issued by
- Huron County, Holly Village, Michigan
About this file
This document is an Addendum to a Request for Proposal (RFP) for professional services issued by the Michigan Department of Technology, Management and Budget (DTMB) for the DNR Parks & Recreation Seven Lakes State Park ARPA Electric, Paving and Shelter Improvements project. The addendum provides clarifications and modifications to the original RFP, including details on the removal and replacement of two existing pavilions, the retention of the existing bathroom building, and the option for pre-manufactured pavilions. It also specifies the inclusion of new electrical outlets, grills, and ADA accessibility for the pavilions, as well as the assumption of new road paving for the park's campsites and parking lots. The proposal due date is October 6, 2022.
The contract opportunity involves improvements to the Seven Lakes State Park located in Huron County and Holly Village, Michigan. The project is funded through the American Rescue Plan Act (ARPA) and will include electrical, paving, and shelter upgrades. Pricing terms, set asides, and other specific financial details are not provided in this addendum.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0414 RFP (Rev 2/22)
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
REQUEST FOR PROPOSAL
ADDENDUM NO. 1
This form identifies an Addendum to a Request for Proposal for Professional Services, and incorporates interpretations or clarifications, modifications, and other information into the Request for Proposals.
Addenda will be numbered by the Project Director and distributed through SIGMA Vendor VSS as an attachment.
TO:
ALL PROPOSERS
DATE ISSUED
September 22, 2022
PROJECT NAME
DNR Parks & Recreation Seven Lakes State Park ARPA Electric, Paving and Shelter Improvements
FILE NUMBER
751/22335.SAA
PROJECT DIRECTOR
Sheryl Ananich, AIA
PROPOSAL DUE DATE:
October 6, 2022
ADDENDUM ITEMS: (attach additional sheets and drawings if required)
1. Mandatory Pre-Proposal meeting attendance is attached.
2. The 2 existing pavilions will be removed and replaced as part of the scope of work.
3. The existing bathroom building will remain (no work).
4. The existing pavilion sizes are adequate with 10 tables under each. This will seat approximately 125 occupants.
5. The new pavilions can be pre-manufactured. The size, location and configuration can be changed if needed.
6. The existing concrete under the pavilions can be re-worked to support the new configuration.
7. Electrical outlets are needed under the pavilions but no lighting is needed.
8. Provide 2 new grills for each new pavilion.
9. Provide ADA accessibility to each pavilion and grill.
10. Paving - We will assume the park will receive all new road paving for the purposes of this proposal, including campground pads and parking lots, but not including boat launch.
11. Electrical - We will assume 20% of campsites will receive 50 amp pedestals – locations TBD
APPROVED BY:
PROJECT DIRECTOR DATE
9-22-22
File details come from the government source that posted it. Updated .