About this file
This document is an addendum to a Request for Proposal (RFP) issued by the Division of Capital Asset Management and Maintenance (DCAMM) for Specification Writer Services. The revised procurement calendar extends the deadline for submitting questions to April 11, 2016, with answers to be posted on April 13, 2016. The submission deadline has been extended to April 22, 2016 at 2:00 PM DST. Additionally, the due dates for key deliverables have been revised, with updated Standard Specifications for Chapter 149 and Chapter 149A projects due by August 31, 2016, and all other deliverables due by October 14, 2016.
The RFP seeks experienced specification writer/consultants specialized in construction project specifications development, preparation, and writing. The contract will be awarded to the successful proposer, with a work plan to be submitted within two weeks of meeting with DCAMM representatives. The work plan must illustrate the sequence for completion of all tasks and deliverables within the revised timeline.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFR DCP1611 AD3_Spec Writer Services_REVISED 20160322.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Proposal (RFP)
SPECIFICATION WRITER SERVICES
Document Number: DCP1611 AD3
Addendum 1 March 22, 2016
The attention of interested Proposers submitting proposals for RFR DCP1611 AD3 is called to the following:
1. Revision of Section 2 Estimated Procurement Calendar
The submission dates for questions, DCAMM response to questions, and submission deadline have been revised and extended.
The revised Estimated Procurement Calendar is provided below:
EVENT DATE
Solicitation Posted on COMMBUYS
Original RFR issuance February 29, 2016
Revised RFR issuance March 22, 2016
Open date for submission of questions via
COMMBUYS
March 22, 2016
Deadline - Close for submission of questions via
COMMBUYS
April 11, 2016
5:00 PM DST
Posting of Answers to Questions on COMMBUYS (Estimated)
April 13, 2016
Solicitation: Close date / submission deadline NOTE: All submissions must be posted in COMMBUYS by the date/time identified
April 22, 2016
2:00 PM DST
2. Revision of due dates for Deliverables
The due dates for key Deliverables (Section 3.1 paragraph 3 Deliverables: Work Plan) have been revised as noted:
• updated Standard Specifications for Ch. 149 and Ch. 149A projects was July 22, 2016 changed to August 31, 2016
• all other deliverables was September 30, 2016 changed to October 14, 2016
The revised section is as follows:
Work Plan - Within two weeks of meeting with DCAMM representatives submit a work plan illustrating a sequence for completion of all tasks and deliverables within the following dates: Updated Standard Specifications for Ch. 149 and Ch.
149A projects by August 31, 2016; all other deliverables to be completed by October 14, 2016. The work plan shall assume 3 weeks turn-around for DCAMM’s review comments.