This document is Addendum No. 1 to the Construction Bid for the N. Higgins Lake State Park - TS Building project, file number 19104.BDW, issued by the Michigan Department of Technology, Management and Budget (DTMB) State Facilities Administration Design and Construction Division. The addendum includes the pre-bid meeting attendance sheets from the March 21, 2022, meeting and notes that the existing toilet shower building includes a water heater that the DNR staff plan to remove prior to demolition, which the contractor shall allow for prior to building demolition activities.
The related state and local contract opportunity is for the North Higgins Lake SP Toilet Shower Bldg. project, located in Roscommon County, Michigan. The bid opening date is April 6, 2022, and bidders are instructed to submit all questions via email to Bruce Watkins, rather than through the SIGMA VSS system. Bidders are also advised of COVID-19 precautions, which may require mask-wearing, and are instructed to notify the Office of Design and Construction if they experience any issues with the SIGMA VSS system.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0414 (Rev 12/17)
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
CONSTRUCTION BID ADDENDUM NO. 1
This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.
TO:
ALL BIDDERS
DATE ISSUED
3/24/2022
PROJECT NAME
N. Higgins Lake State Park – TS Building
FILE NUMBER
19104.BDW
PROFESSIONAL
NFE Engineers
PROJECT DIRECTOR
Bruce Watkins
BID OPENING DATE:
4/6/2022
ADDENDUM ITEMS: (attach additional sheets and drawings if required)
1. Pre-bid meeting attendance sheets from the March 21, 2022, meeting are attached herein.
2. The existing toilet shower building includes a water heater that DNR staff plan to remove prior to demolition. This removal will be completed no later than noon on September 8th. Contractor shall allow for this removal prior to building demolition activities.
ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.
Steve Sutton
PROFESSIONAL: DATE: 3/24/2022
APPROVED BY:
PROJECT DIRECTOR: Bruce Watkins DATE: 3/24/2022