Addendum 03 ARFQ DEP26-089 Lewis Co. Group B South Well Plugging Package.pdf

PDF 225 KB Posted

Attached to
Lewis Co. Group B - South Well Plugging Package
Solicitation number
ARFQ 0313 DEP2600000089 4
Issued by
Lewis County, West Virginia

About this file

This is Addendum 3 to a Request for Quotation (ARFQ) issued by the West Virginia Division of Environmental Protection (DEP) for the Lewis County Group B - South Well Plugging Package (Solicitation Number ARFQ DEP2600000089). The addendum was issued on April 21, 2021, to distribute additional documentation and vendor questions with responses to the contractor community. The addendum addresses two critical site-specific inquiries regarding well API# 47-041-00648: clarification on wetland protection requirements and confirmation of property access and landowner coordination needs. The Agency confirmed that while the West Virginia Division of Natural Resources identified a sensitive wetland habitat within the 200-foot action area buffer, the National Wetland Inventory mapping determined negligible overlap occurring only at the very edge of the buffer for adjacent well access on the opposite side of the road. Erosion and sediment controls will be implemented as standard mitigation measures, with matting boards recommended if wet soil conditions are encountered during construction activities.

The addendum clarifies that both the well access and wellsite for API# 47-041-00648 are located solely on parcel #21-01-005L-0005-0000, eliminating the need for additional landowner coordination or permission from adjacent properties. Vendors are required to acknowledge receipt of all addenda issued for this solicitation by completing and submitting an Addendum Acknowledgement Form with their bid proposal; failure to acknowledge addenda may result in bid disqualification. All terms, conditions, and provisions of the original Agency Solicitation remain in full force and effect except as modified by this addendum. The document emphasizes that only information issued in writing and officially added to specifications through addenda is binding, and verbal representations made during discussions with state personnel are not binding.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The Purpose of this addendum is to modify the solicitation identified as (“Agency Solicitation”) to reflect the change(s) identified and described below.

Applicable Addendum Category:

[ ] Modify bid opening date and time

[ ] Modify specification of product or service being sought

[ ] Attachment of vendor questions and responses

[ ] Attachment of pre-bid sign-in sheet

[ ] Correction of error

[ ] Other

Description of Modification to Solicitation:

This Addendum issued to publish and distribute the attached documentation to the vendor community.

Additional Documentation: Documentation related to this Addendum (if any) has been included herewith as Attachment A and is specifically incorporated herein by reference.

Terms and Conditions:

1. All provision of the Agency Solicitation and other addenda not modified herein shall remain in full force and effect.

2. Vendor should acknowledge receipt of all addenda issued for this Agency Solicitation by completing an Addendum Acknowledgement, a copy of which is included herewith. Failure to acknowledge addenda may result in bid disqualification. The addendum acknowledgement should be submitted with the bid to expedite document processing.

SOLICITATION NUMBER – ______________

Addendum Number: ____

ADDENDUM 3 ARFQ DEP2600000089 Lewis Co. Group B - South Well Plugging Package

ADDENDUM 3

ARFQ DEP2600000089

Lewis Co. Group B - South Well Plugging Package

Q1: On API# 47-041-00648 it was mentioned that the well is right next to a wetland. Is there any protection needed for this site (absorbant booms, mats, etc?)?

A1: West Virginia Division of Natural Resources (WVDNR’s) review indicated a sensitive wetland habitat overlaps the proposed project's 200-foot action area buffer. The Agency reviewed the National Wetland Inventory's (NWI’s) wetland mapper tool and determined that this wetland and the 200-foot buffer for this well and access do not overlap at all; the negligible overlap occurs at the very edge of the 200-foot buffer area for the proposed access of another well, on the opposite side of the road from that well. It is extremely unlikely the proposed activities will cross into the wetland boundary, as the activities will occur mainly near the road.

Erosion and Sediment (E&S) controls will be utilized to mitigate any potential impacts on the wetland area. Should the contractor encounter wet soil conditions, matting boards are recommended.

Q2. On API# 47-041-00648 it was mentioned that the route to the well site might run through an adjacent property, can the owner confirm if we need additional landowner coordination?

A2. The Agency's review of parcel boundaries indicates that the access and the wellsite occur solely on parcel #21-01-005L-0005-0000.

Revised 04/21/2021

ADDENDUM ACKNOWLEDGEMENT FORM

SOLICITATION NO.:

Instructions: Please acknowledge receipt of all addenda issued with this solicitation by completing this addendum acknowledgment form. Check the box next to each addendum received and sign below. Failure to acknowledge addenda may result in bid disqualification.

Acknowledgment: I hereby acknowledge receipt of the following addenda and have made the necessary revisions to my proposal, plans and/or specification, etc.

Addendum Numbers Received:

(Check the box next to each addendum received)

[ ] Addendum No. 1 [ ] Addendum No. 6

[ ] Addendum No. 2 [ ] Addendum No. 7

[ ] Addendum No. 3 [ ] Addendum No. 8

[ ] Addendum No. 4 [ ] Addendum No. 9

[ ] Addendum No. 5 [ ] Addendum No. 10

I understand that failure to confirm the receipt of addenda may be cause for rejection of this bid.

I further understand that any verbal representation made or assumed to be made during any oral discussion held between Vendor’s representatives and any state personnel is not binding. Only the information issued in writing and added to the specifications by an official addendum is binding.

Company

Authorized Signature

Date

NOTE: This addendum acknowledgement should be submitted with the bid to expedite document processing.

Addendum # 1.pdf
Addendum Acknowledgement Form.pdf
Addendum Number: 3
Check Box1: Off
Check Box2: Off
Check Box3: Yes
Check Box4: Off
Check Box5: Off
Check Box6: Off
Text7: Addendum No. 3 is issued to publish and distribute the attached information to the Vendor community.

1 .To Publish vendor questions and responses

No Other Changes

Company_2:
Date_2:
Check Box38: Off
Check Box40: Off
Check Box41: Off
Check Box42: Off
Check Box43: Off
Check Box44: Off
Check Box45: Off
Check Box46: Off
Check Box47: Off
Check Box48: Off
SOLICITATION NUMBER: ARFQ DEP2600000089

File details come from the government source that posted it. Updated .