Addendum 01 for-52-IFB-1782151456-MLE-Heather Gray T-Shirts-Scotland Sewing Plant.docx

DOCX document 99 KB Posted

Attached to
Heather Gray T-Shirts-Scotland Sewing Plant
Solicitation number
Doc1782151471
Issued by
Stanly County, Lasker Town, North Carolina

About this file

This Addendum 01 document modifies the Invitation for Bid (IFB) solicitation issued by the North Carolina Department of Adult Correction for heather gray t-shirts to be supplied to the Scotland Sewing Plant in Laurinburg, North Carolina. The solicitation seeks competitive bids for nine sizes of heather gray t-shirts (Medium through 5X-Large) with an estimated annual quantity of 936,848 units, ordered on an as-needed basis throughout the year. Vendors must submit eighteen sample units (two of each size) prior to the bid opening on December 18, 2025 at 2:00 PM, with written questions required by November 18, 2025 at 10:00 AM and state responses issued by November 20, 2025 at 1:00 PM. The addendum clarifies that delivery must occur within four weeks of purchase order issuance to the Scotland Sewing Plant at 22385 McGirts Bridge Road, Laurinburg, NC 28353, with vendors required to call to schedule delivery appointments. The contract term is one year with pricing remaining firm for the contract period, and the solicitation indicates an ongoing, release-based contract structure with orders based on Department of Adult Correction inventory needs.

The addendum addresses vendor inquiries regarding fabric composition, confirming specifications require 4.75 oz fabric with 40% Polyester, 50% Cotton, and 10% Black Polyester in jersey knit construction with tubular design and no side seams. Previous pricing for comparable t-shirts ranged from $2.20 to $2.45 each. Vendors may propose their own production and delivery lead times but must confirm compliance with stated specifications; however, if a vendor cannot meet the four-week delivery requirement, they may propose alternative timelines for state consideration. The state requires vendors to maintain five percent of annual quantity in U.S. inventory at all times and mandates that all shirts include only a heat-pressed label with no additional imprinting or labeling, as any further printing will be performed by the state. Manufacturing location, whether domestic or offshore, remains at vendor discretion. Samples must be submitted before bid opening or vendors will be disqualified, and no additional time extensions for sample production will be granted. All other terms and conditions from the original solicitation remain unchanged.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION NUMBER: Error! Reference source not found.

ADDENDUM NUMBER: Error! Reference source not found.

SOLCITATION ADDENDUM

Issuing Agency:
NCDAC
Solicitation Number:
52-IFB-1782151456-MLE
Solicitation Description:
Heather Gray T-Shirts-Scotland Sewing Plant
Solicitation Opening Date and Time:
December 18, 2025 at 2:00 PM
Addendum Number:
01
Addendum Date:
November 20, 2025
Purchasing Agent:
Lorraine Middleton

FAILURE TO RETURN THIS ADDENDUM MAY SUBJECT YOUR RESPONSE TO REJECTION.

1. The Solicitation is hereby modified as follows:

Modification #
Solicitation Section
Current Solicitation Language
Updated Solicitation Language

1. The following are questions received about the Solicitation and the State’s response to those questions:

Question #
Document Section
Vendor Question
State’s Response
Number of orders? Please could you provide some estimates for number of orders expected to be placed annually and the approximate quantity per order?
Orders are based on DAC needs. We will only order what is required for Inventory.

Estimates for 2025 MD – 27,720 Each LG – 40,000 Each XL – 89,840 Each 2X – 89,200 Each 3X – 15,000 Each 4X – 15,000 Each 5X – 15,000 Each

Previous Price. Could you share the previous price paid for the T-shirts?
$2.20 - $2.45 Each
Are the sides expected to be stitched or is it tubular construction?
Tubular Construction/ No side seam

May we propose our own production and delivery lead times within the bid response, or must we strictly meet the four-week delivery requirement as written on bid?

They ask for the time stated but you put down what you time is.

Where Can we receive a physical fabric sample by sending a prepaid shipping label to the contact listed?

Yes, you will need to send a pre-paid USPS mailing label so I can send you a sample of the T-shirt.

Lorraine.Middleton@dac.nc.gov

Will the quantities listed be issued as a single purchase order, or will this be an ongoing, release-based contract throughout the year?

They will order on an as needed basis.

Please confirm whether the 18 samples must be submitted before bid opening or if samples may be submitted afterward for approval?
Samples must be sent in before the bid opens on December 18, 2025 @ 2:00 pm
Will the quantities listed be issued as a single purchase order, or will this be an ongoing or release-based contract throughout the year?
This will be ongoing throughout the year.
Does the price quote need to be firm for entire contract period of three years, or only for 180 days?
The price quote needs to be for 1 year.
If a vendor cannot maintain 5%of the annual quantity in the U.S. inventory at all times, may we propose our own MOQ and stocking pan for consideration?
The vendor has to be able to maintain 5% of the annal quantity in the US.
Does the quantity 936,848 units is for three-year term or one year quantity?
This is a yearly estimate.
Are the shirts blank or will there be any required imprinting or labeling beyond the heat-pressed tag?
We just need you to have the heated label pressed in the shirt (Picture has been attached to the bid. Any printing will be done by us.
Clarification The written specification requires 4.75 oz fabric with 40% Polyester / 50% Cotton / 10% Black Polyester, but the picture provided under Section 4.10 shows a 50/50 blend label. Please confirm which fabric composition we must quote and supply:40% Polyester / 50% Cotton / 10% Black Polyesteror50% Cotton / 50% Polyester.
Fiber Content: 40% Polyester, 50% Cotton, 10% Black Polyester/jersey knit

**The 10% Black Poly is what makes the Heather Color**

Is the preference to have the t-shirts Made in the USA which allow for quicker turnaround times and product availability or does the state simply want the least expensive option that meets the technical specifications as listed in section 5.1 and 5.2 but means an offshore production and longer lead times that will exceed the 4 weeks as stated in section 4.5?

This is at vendors discretion.

4.4 it states "vendor shall deliver FOB to any requested location within the State of NC," but in section 4.5, it specifically states the delivery location is the "NC Department of Adult Correction... Attn: Sharon Jones" If there are multiple NC delivery locations without designated people like Sharon Jones, how will an appointment be scheduled and how will vendor ensure acknowledgement of Lab Test Reports and Flammability Compliance was received? Clarify if it will be a single delivery location.

Sewing Plant 22385 McGirts Bridge Road Laurinburg, NC 28353 must call to schedule a delivery appointment.

DELIVERY It's stated, "The delivery should be received within four (4) weeks of issuance of purchase order." How is the state basing this time frame given offshore production will likely be closer to 60-80 days depending on the production facility location and means of transportation to the CONUS? Or, given the state has a 4 week delivery time frame, does this mean the t-Shirts must be Made in the USA? For this paragraph "For completion by Vendor: Delivery will be made from ___________________________________4-week_ (city, state) within _____ consecutive calendar days after receipt of purchase order. Promptness of delivery may be used as a factor in the award criteria." is the State affording the vendor the opportunity to "dictate" its delivery times based on the manufacturing location and lead times? 4.10 APPROVED PRODUCT LABELS Deliveries

Specification needs to be followed, vendor will need to comply

Will additional time be given to produce samples if needed

No, if the samples are not received the vendor will be disqualified.

Check ONLY ONE of the following options and return one properly executed copy of this Addendum prior to the Solicitation opening time and date.

☐ A response was submitted prior to this Addendum. An updated response has been submitted to address the changes resulting from this Addendum.

☐ A response was submitted prior to this Addendum. NO CHANGES have resulted from this Addendum.

☐ A response was not submitted prior to this Addendum. ANY CHANGES resulting from this Addendum are included in our response.

ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME

________________________________________________________________________
Authorized SignatureDate
________________________________________________________________________
Printed NameTitle

North Carolina Solicitation Addendum Version Date: 11/2021 Page | 1

North Carolina Solicitation Addendum Version Date: 11/2021 Page | 1 image1.png

File details come from the government source that posted it. Updated .