This is Addendum #1 to an Invitation to Bid issued by the Morgan County Board of Commissioners for TPO roof replacement at the Public Safety Complex located at 1380 Monticello Road, Madison, Georgia. The scope of work includes replacement of the TPO membrane system, installation of 12-inch high-density recovery board across the entire roof, replacement of approximately 38 skylights (4-foot by 4-foot nominal), replacement of insulation (approximately 8,458 board feet based on infrared scan), drainage improvements including enhanced crickets and sumps, replacement of expansion joints, walk pad replacement plus an additional 50 feet, lightning protection system work, HVAC unit curb wrapping, and a five-year maintenance agreement. Sealed bids were due Wednesday, April 1st, 2026, at 11:00 AM at the Morgan County Board of Commissioners meeting hall. Only contractors who attended one of two pre-bid meetings are eligible to submit bids. Award is anticipated within two weeks of bid opening, subject to approval by the Board of Commissioners. The contract term includes completion of construction and five years of maintenance services.

Pricing for the project is confidential and not disclosed by Morgan County. The insulation replacement is a unit price item payable per board foot, with the 8,458 board feet considered an approximation; actual quantities are based on exposed conditions and subject to board approval. Additional insulation replacement beyond 8,500 board feet is compensated at the same unit price. The bid must include all labor, materials, disposal, temporary dry-in measures, tool inventory control is not currently required but may be mandated at the Sheriff's discretion, and dumpsters are permitted on site. The project is not subject to Davis-Bacon or prevailing wage requirements. Work is restricted to Monday through Friday and Saturday mornings (8:00 AM to 4:00 PM), with all Morgan County holidays and adjacent Fridays excluded. The contractor must be certified by the TPO membrane manufacturer and must provide shop drawing details for approval prior to installation of critical elements including skylights, expansion joints, flashing, and lightning protection components.

View the file

Other files

File Type Posted
RFQ 2026 Morgan Co PSC Roof Replacement.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MORGAN COUNTY PUBLIC SAFETY COMPLEX ROOF REPLACEMENT

Morgan County Board of Commissioners

Addendum #1

Morgan County will accept sealed bids in response to this Invitation to Bid. This Invitation to Bid is subject to the instructions, conditions, specifications, addenda, and other elements, included herein and those incorporated by reference.

ISSUE DATE: March 32rd, 2026

BID TITLE: RFP MORGAN COUNTY PUBLIC SAFETY COMPLEX ROOF REPLACEMENT

CONTACT: Aaron Wadley, Engineer

TELEPHONE: 404-326-4522

E-MAIL ADDRESS: aaron@tv-eng.com

BID OPENING: Wednesday April 1st, 11:00 AM

LOCATION: Morgan County Board of Commissioners Upstairs Commission Meeting Hall 150 E. Washington St

Madison, GA. 30650

Questions

Q1 Is it the entire facility located at 1380 Monticello Rd Madison, GA 30650?

A1 Please refer to the highlighted portion of the roof in the Scope and Description of Work labeled Subject Roof.

Q2 Also are there any plans and specs for the project? If so could you please send them to us for review?

A2 All specifications are included in the RFP and subsequent addenda.

Q3 What is the estimated construction budget?

A3 Morgan County does not disclose budget in an open bid.

Q4 Since we already went out once to look at the roof. Do we need to attend again ??

A4 All requirements of this RFP must be met as described in the document. Only those who attended the pre-bid for this RFP are eligible.

Q5 Who is the required manufacturer for the TPO membrane?

A5 Any manufacturer that meets the specifications is eligible.

Q6 JM allows leaving existing TPO in place, if cut into 10'x10' squares, and install new coverboard and TPO over the existing. Is this something the county would consider?

A6 Existing TPO must be removed per the scope.

Q7 When do you anticipate award? And start? How many days to complete?

A7 Award is anticipated within two weeks of bid opening, but is subject to change based on a vote by the Board of commissioners. Refer to the contract section 3: Time for Performance.

Q8 Who will be responsible for interior cleanup, if any is required?

A8 They are multiple HVAC units with coolant lines that appear to be the source of leaks, how should we handle these?

Q9 How will the contractor get access into the fenced areas, if necessary?

A9 The contractor will schedule work weekly with the engineer and chief deputy. In the event of an emergency all project principals will have a list of emergency contacts.

Q10 What are work hours? Days?

Morgan County Board of Commissioners

A10 Refer to the contract section 3: Time for Performance.

Q11 Will all tools need to be inventoried before and after each work shift?

A11

The County is not requiring it at this time. However, the Sheriff has security control of the site and can require additional measures, such as inventory of tools and equipment at his discretion. At no time is there anticipated to be contact between inmates and workers.

Q12 Will dumpsters be allowed to be kept on site during construction?

A12 Yes

Q13 Is this project subject to any Davis bacon or prevailing wages? Certified payroll?

A13 No

Q14 Does the walk pad need only to form a pathway around it or leading to other units i.e., do you want the new walk pad to Recreate the existing pathway?

A14 Walk pad will be replaced in kind plus an additional 50'

Q15 I am unable to attend either pre-bid meeting but would like to bid on this project. Can a third meeting be organized?

A15 No, only contractors who attended one of the two pre-bids will be eligible.

Q16 Existing Roof System and Manufacturer: What manufacturer installed the adjacent roof system that was completed within the last 12 months?

A16 Please refer to the existing roof warranty in the RFP package.

Q17 Existing Roof System and Manufacturer: Can the engineer confirm the exact membrane system currently installed (manufacturer, membrane type, attachment method)?

A17 No. The County does not have these records.

Q18 Existing Roof System and Manufacturer: Will the county require the new work to be installed by a manufacturer-certified installer of the same system?

A18 The contractor will be required to be certified by the manufacturer they use.

Q19 Existing Roof System and Manufacturer: Please provide the existing manufacturer warranty documentation referenced in the RFQ.

Morgan County Board of Commissioners

A19 The warranty for the adjacent roof was included.

Q20 Warranty Continuity Requirements: Does the manufacturer require that the same contractor who installed the adjacent roof perform the tie-in work, or can any certified installer perform the work?

A20 The contractor will replace the expansion joint in full and make a time in approved by their own manufacturer that does not violate the terms of the warranty on the adjacent roof.

Q21 Warranty Continuity Requirements: Has the manufacturer already been consulted regarding tie-in details between the existing roof and the new system?

A21 Yes, but each manufacturer has their own details and requirements. The Contractor will need to submit a detail approved by their manufacturer for approval.

Q22 Warranty Continuity Requirements: Will the manufacturer require a pre-construction inspection prior to work beginning?

A22 The County is not aware of this requirement. The contractor will be required to provide a warranty for their scope of work per the scope and may not perform work that would void or harm the warranty on the adjacent roof.

Q23 Insulation Replacement Scope: The RFQ indicates approximately 8,458 board feet of potential insulation replacement identified via IR scan. Can the IR scan report be provided for review?

A23 This quantity should be considered an approximation of potential replacement. Actual quantity will be based on exposed condition and is subject to approval for payment by the board foot. A report is not available at this time.

Q24 Insulation Replacement Scope: Does the insulation replacement quantity include multiple insulation layers or only the top layer?

A24 It includes all insulation necessary but is based on a 2" depth. Actual quantity will be based on exposed condition and is subject to approval for payment by the board foot.

Q25 Insulation Replacement Scope: If insulation replacement exceeds the 8,500 BF allowance, will additional replacement be compensated at the same unit price per board foot?

A25 Yes. Actual quantity will be based on exposed condition and is subject to approval for payment by the board foot. Contractor is not guaranteed 8,500 BF of replacement.

Q26 Drainage Improvements: The scope references enhancing crickets and establishing sumps at drains. Should bidders assume tapered insulation modifications are included in the base bid?

A26 Yes, but additional insulation required to make the taper modifications will be paid by the board foot.

Morgan County Board of Commissioners

Q27 Drainage Improvements: Is there a minimum slope requirement for the corrected drainage areas beyond the 1⁄2” per 12 noted in the RFQ?

A27 Contractor should meet all requirements in the scope and necessary for the manufacturer to warranty the work.

Q28 Recovery Board Requirement: The RFQ specifies installation of a 1⁄2" high-density recovery board. Is this to be installed across the entire roof area or only in areas where insulation is replaced?

A28 The entire roof.

Q29 Skylight Replacement: The RFQ includes replacement of 38 skylights (nominal 4' x 4').

Are shop drawings or specifications available for the existing skylight curbs?

A29 Building drawings are not available.

Q30 Skylight Replacement: Are bidders required to provide new curbs, or are existing curbs assumed to remain?

A30

Existing curbs are expected to remain. However, the contractor must make all modifications or enhancements required by both the manufacturer of the skylights and TPO to obtain warranty certificates. If there is corrosion or damage requiring replacement or rebuild, this would be out of scope.

Q31 Skylight Replacement: Should skylight replacements be included under the roof manufacturer warranty?

A31 Each may have their own warranty as long as both are active and do not compete.

Q32 Security and Work Area Restrictions: Can the engineer clarify working hour restrictions for areas located over inmate recreation spaces?

A32

The work will generally be scheduled a week ahead of time and inmates will be moved to an unimpacted cell block. While expected to be isolated occasions, if multiple cell blocks must be impacted at one time, an abbreviated schedule will be required. This will be dictated by Sheriff’s Office at that time.

Q33 Security and Work Area Restrictions: Will the county provide security personnel or escorts when work occurs near secured areas?

A33 Contractors are not expected to come into contact with inmates and secured area access will be very limited with a representative of the Sheriff's Office present.

Q34 Lightning Protection: Is the lightning protection system currently UL certified?

A34 We do not have this information. Everything touched by this scope of work must follow the RFP scope.

Morgan County Board of Commissioners

Q35 Lightning Protection: Is a UL-certified lightning protection contractor required for removal and reinstallation?

A35 All requirements of the scope and special provision must be adhered to.

Q36 Construction Logistics: Are there designated staging areas for materials and dumpsters on site?

A36 Yes. There is a fenced staging area and an unfenced staging area.

Q37 Construction Logistics: Are there weight restrictions for equipment or crane access around the facility?

A37 Equipment should be kept within reason for a project of this size and should not cause damages to facilities There are not set weight limits.

Q38 Bid Pricing Clarifications: The bid tabulation form lists insulation replacement as a unit price item. Should bidders include all labor, disposal, and replacement materials within the board foot unit price?

A38 Price should include all work required to perform the stated scope of work.

Q39 Bid Pricing Clarifications: Are temporary dry-in measures expected to be included in the base bid?

A39 Yes. At no time can the contractor expose any interior spaces to the elements outside of the active work. Contractor will be held responsible for damage caused by insufficient temporary dry-in.

Q40 Maintenance Agreement: The RFQ references a 5-year maintenance agreement.

Should this be included in the base bid or listed separately?

A40 All work and incidentals necessary to complete the full scope of work should be included in the bid price whether specifically stated or not.

Q41 Schedule: Is there an anticipated Notice to Proceed date?

A41 It is anticipated to be within two weeks of bid opening but subject to a vote by the Board of Commissioners.

Q42 Schedule: Are there any seasonal or operational restrictions that could affect project scheduling?

A42

All Morgan County staff holidays and Weekends immediately adjacent to County holidays are restricted, to include Friday. The Sheriff may restrict work at any time for any reason. Work will only be permitted on Saturday from 8 AM to 4 PM. No work will be permitted on Sunday. Additional restrictions may apply depending on the roof location work is performed.

Morgan County Board of Commissioners

Q43 Will all gutters, downspouts and leader heads be replaced?

A43 As long as they are in good shape they will not be replaced. Leaders heads should be refinished on the interior and resealed. Gutters and downspouts in the access building on the roof will be replaced in kind.

Q44 Can we get details on the flashing below the insulated panels on the roof access structure?

A44 TPO will fully wrap just below the insulated panels and counter flashing will be installed. Please provide a shop drawing detail prior to installation.

Q45 Will the HVAC units need to be lifted?

A45 No, full TPO wrap of all exposed curb will be required but units will not need to be moved. Details must be provided prior to install for approval.

Q46 There are two expansion joints, can we get details on replacement?

A46 All expansion joints must be fully replaced per manufacturer directions. This should include upper and lower TPO layer and backer rod. Details must be provided for approval prior to installation.

Q47 There are multiple HVAC units with coolant lines that appear to be the source of leaks, how should we handle these?

A47 All coolant lines and roof penetrations will be resealed per manufacturer requirements. Coolant lines should receive a two piece custom shepherds hook cover that allows rain water to run off. Openings should be fully sealed.

Q48 Can we have an example of what is being required for lightning protection?

A48 This work was performed as part of the base scope on the previous roof replacement.

The letter of findings is attached, as an example.

Atlanta Lightning Protection • 159 River Mill Drive Ball Ground, GA • atlantalightning.com

LIGHTNING PROTECTION SYSTEM – LETTER OF FINDINGS

CERTIFICATION # 20250616M

June 16, 2025

CERTIFICATE HOLDER:

PROJECT:

Morgan County Public Safety Complex Tenant Roof Replacement

1380 Monticello Rd

Madison, GA 30650

This letter is to certify that the LIGHTNING PROTECTION SYSTEM reinstalled by Atlanta Lightning

Protection on the address listed above is found to be compliant with installation requirements as set forth by the

Underwriter’s Laboratories, Inc., UL 96A latest edition.

The scope of work area was limited to the flat roof area, East of the expansion joint consisting of approximately

56,400 sq ft. All other roof areas have been excluded from the scope of work and LPS system inspection. The existing ground system has been utilized, and all rooftop conductors have been reattached to the seven existing grounding locations. No work has been completed under the roof deck.

Class I aluminum conductor, lightning rods and roof penetrations are in good condition at this time. Lightning protection components were added to one rooftop unit on the West portion of the roof to provide adequate protection for the entire roof area. All other rooftop equipment has been inspected and is properly protected.

Please note that the lightning protection system installer holds no responsibility for the warranty of the roof system or any portion of the lightning protection system installed by others.

Any changes made to the lightning protection system and/or structure may compromise the integrity of the lightning protection system.

Inspection Completed By:

Chad Rubelsky

Atlanta Lightning Protection

159 River Mill Drive

Ball Ground, GA 30107

(404) 794-7500

Adam Smith

Adam Smith – LPI Master Installer Designer 1578

Morgan County Safety Complex Brand Vaughn Lumber Building

Legend

1380 Monticello Rd

100 ft N

N Image © 2024 Airbus

Image © 2024 Airbus

Image © 2024 Airbus bayle Polylength Measurement 995'-8 1/2" bayle Polylength Measurement 93'-9 3/4" bayle Polylength Measurement 81'-4" bayle Polylength Measurement 121'-1/4" bayle Polylength Measurement 183'-7 1/4" bayle Polylength Measurement 44'-8 3/4" bayle Polylength Measurement 42'-11" bayle Polylength Measurement 50'-10 1/4" bayle Polylength Measurement 100'-11 1/2" bayle Polylength Measurement 39'-10" bayle Polylength Measurement 177'-8" bayle Polylength Measurement 190'-1 1/4" bayle Polylength Measurement 47'-7 1/4" bayle Polylength Measurement 6'-9 1/2" bayle Polylength Measurement 8'-1 1/4" bayle Polylength Measurement 42'-5" bayle Polylength Measurement 86'-2 3/4" bayle Polylength Measurement 42'-5 1/2" bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Count Measurement bayle Text Box

ADDED LP TO THIS RTU

bayle Polylength Measurement 43'-8 3/4" bayle Polylength Measurement 6'-9 1/4" bayle Rectangle bayle Rectangle bayle Rectangle bayle Rectangle bayle Rectangle bayle Rectangle bayle Rectangle bayle Text Box Roof Penetration & Grounding bayle Text Box Roof Penetration & Grounding bayle Text Box Roof Penetration & Grounding bayle Text Box Roof Penetration & Grounding bayle Text Box Roof Penetration & Grounding bayle Text Box Roof Penetration & Grounding bayle Text Box Roof Penetration & Grounding bayle Ellipse bayle Ellipse bayle Ellipse bayle Ellipse bayle Ellipse bayle Ellipse bayle Ellipse

File details come from the government source that posted it. Updated .