ADA-Remediation-Vendors-Sample-Document-2025.pdf
PDF 3 MB Posted
- Attached to
- ADA Remediation Services
- Solicitation number
- 26-B-31JD
- Issued by
- Volusia County, Florida
About this file
This document is a Capital Project Schedule for the County of Volusia, Florida, dated August 6, 2019 (revised July 31, 2019), providing a comprehensive third quarter update on multiple capital improvement projects across various county departments and service areas. The schedule outlines project status, timelines, and cost estimates for numerous initiatives spanning Business Services, Community Services, Daytona Beach International Airport, Ocean Center, Public Protection, Public Works, and Sheriff's Office divisions. Projects detailed include facility construction and renovations (New Court/Central Services Warehouse, Elections Warehouse, Hope Place Library Services Facility), infrastructure improvements (800 MHz Radio System, Taxiway November Rehabilitation, water and wastewater treatment facility upgrades), park and recreational area developments (Lemon Bluff Park, Shell Harbor Park, Edwin W. Peck Sr. Park, Dahlia Ave. Park), and security system upgrades at the Branch Jail/Corrections Facility. The document employs a Gantt chart format to display project phases including land acquisition, design/permitting, and bid and construction phases across fiscal years 2016/17 through 2021/22, with specific quarterly timelines and completion dates for each initiative.
Funding sources for these projects are drawn from multiple county accounts and external grants, including Court/Central Services Warehouse funds (368-930-4190-6200), Elections Warehouse funds (367-930-4180), General Fund accounts (305-930-4605, 305-930-4606), Community Development Block Grants, ECHO grants, FIND grants, Beach Capital funds, and city budgets contributing to countywide initiatives such as the 800 MHz Radio System with an estimated total cost of $26.6 million. Notable completed projects include the New Court/Central Services Warehouse (substantial completion May 24, 2019), Hope Place Library Services Facility (completed May 16, 2019 with ribbon cutting June 19, 2019), Fire Station 36 Renovations, and several Public Works projects. Several projects experienced schedule adjustments and cost increases due to factors including permit requirements, design modifications, inclement weather, material delays, and scope expansions. The document also contains supplementary information regarding the Emergency Medical Administration division's budget for fiscal years 2022-23 and 2023-24, including personnel, operating expenses, and system-wide operational metrics.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ADA_Remediation_Services.pdf | ||
| 26-B-31JD,_Insurance_Requirements,_ADA_Remediation_Services.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CAPITAL PROJECT
SCHEDULE
August 6, 2019
Revised 7/31/19
CPS 3rd Quarter Update Executive Summary Page 1
Volusia County Capital Project Schedule Executive Summary
3rd Quarter Update – August 6, 2019 Business Services
• New Court/Central Services Warehouse – Project Complete.
• New Elections Warehouse – Acquisition timeline adjusted to finish 2nd FY 19/20. Design timeline will begin 2nd Qtr. FY 19/20 and finish 1st Qtr. FY 20/21, construction will follow in 2nd Qtr. FY 20/21 and will finish 1st FY 21/22.
• Countywide 800 MHz Radio System – o Phase II –Development of microwave and radio system RFP scope of work near completion with planned release in July 2019.
Community Services
• Hope Place Library Services Facility – Total project cost increased to $1,066,658. Project has been completed; Ribbon cutting was held June 19, 2019.
• Lemon Bluff Park –Project scope has been changed to include restoration of the seawall, dockage, construction of a boat launch, floating canoe/kayak launch, fishing area, pavilions (2), parking and sidewalks. Design timeline has been extended to 4th Qtr. FY 18/19 as County Council provided direction on conceptual plan to maximize parking on the West side of Lemon Bluff Road.
Construction timeline has been adjusted to reflect scope change. Construction will begin 1st Qtr.
FY 19/20 and finish 4th Qtr. FY 19/20. Project cost has increased to $1,640,852.
• Shell Harbor Park – Project scope has been changed, project will include construction of the boat ramp and floating dock, restroom, pavilion, boardwalk and paved parking (33 boat trailer capable & 2 ADA spaces).
• Highbridge Park Restrooms– Total project cost increased to $292,519. Project has been completed.
• Marine Discovery Center Trail – Design timeline has been extended to finish 4th Qtr. FY 18/19 due to new location of trailhead.
• Hope Place Recreational Area – Council approved playground purchase on April 16, 2019 and approval for basketball court contract on July 2, 2019. Construction timeline has been extended to 4th Qtr. FY 18/19.
Daytona Beach International Airport
• Taxiway November Rehabilitation – o Bid schedule C construction is underway.
o Project cost has increased to $39,647,444 due to the addition of two change orders for schedule C. Change orders to include an aircrafted rated manhole cover and additional excavation and other elements required by a change in the St. Johns River Management permit.
o Halifax paving Construction contract CO #2 Schedule C will be presented to County Council July 16, 2019.
CPS 3rd Quarter Update Executive Summary Page 2 o Council approval of RS&H CA/RPR and AVCO Post Design (Bid Schedule D) will be presented August 6, 2019.
• DAB Terminal – o Parking Lot Improvements – Total project cost decreased to $5,699,692, reflecting estimated consultant’s cost. Design timeline has been extended to 1st Qtr. FY 19/20.
Construction timeline has been adjusted to start 2nd Qtr. FY 19/20 and finish 4th Qtr. 19/20 as additional time is needed due to revised project scope and fee.
o Terminal Renovations – Project cost has been adjusted to $14,442,881. Award of contract for CM/GC, Part B received April 16, 2019. Notice to proceed was issued on May 5, 2019.
Ocean Center
• Roof Repair – Project complete.
• Main Marque Replacement – Painting of concrete and electrical work is underway. Construction timeline has been extended to 4th Qtr. FY 18/19.
• Retrofit Lighting to LED in Arena, Exhibit Hall and Parking Garage– Staff has met with TLC
Engineering, project design is underway. Construction for this project has been moved to FY 19/20.
• Replace Arena Roof – Design timeline has been extended to 4th Qtr. FY 18/19 due to redesign of flashing details.
• Parking Garage – o Lighting – Construction of this project has been moved to FY 19/20. Total project cost has increased to $216,000.
o Deck & Drainage Restoration – Structural engineer has completed their study. Staff is awaiting results and completed design by ARC.
Public Protection
• Volusia County Branch Jail/Correction Facility Network Infrastructure Upgrade – Project construction has been extended to 1st Qtr. FY 19/20. Project extended to allow cable contractor to work with inmate phone system vendor (expected to be in place by August) and video visitation vendor (expected to be in place by October). Total project cost increased to $764,382.
• Volusia County Branch Jail/Corrections Facility Security and Telecommunications System Upgrade
– Design for Phase I is underway; project cost has increased to $ 8,516,660.
• Volusia County Branch Jail/Correction Facility Operations System Upgrade – Contract negotiations began during 2nd Qtr. FY 18/19. Project cost adjusted to $ 1,098,000. The Inmate Phone and Video visitation is funded by contractor and repaid with revenue generated by the system. There is no upfront county cost.
• Volusia County Branch Jail, Phase 3 Roof Replacement – Construction is underway, construction timeline has been delayed to 4th Qtr. FY 18/19 due to metal fabrication.
• Fire Station 36 Renovations – Project cost increased to $959,000, due to additional change order.
Construction has been finished. Project complete.
Q1 = October - December Q2 = January - March Q3 = April - June Q4 = July - September
Land Acquisition Phase
Design/Permitting Phase
Bid & Construction Phase
Activity Overlap
♦ Schedule Adjustment
Project Complete
BS = Business Services CS = Community Services DAB = Daytona Beach Intl Airport OC = Ocean Center PP = Public Protection PW = Public Works SO = Sheriff's Office
Department Legend
Master Capital Project Schedule
August 2019 Update
Please refer to individual project sheets for details and information.
*New Projects are in Bold **Completed Projects are in Italics. Refer to back of binder for Q3 and older Note: Large projects utilizing CMGC method will overlap Eng/Design with Const
Fiscal Quarters
Phase Legend
M
AS
TE
R
CA
PI
TA
L
PR
O
JE
CT
S
CH
ED
U
LE
SO
RT
ED
B Y
PR
O
JE
CT
N U
M
BE
R (P
ID
*N ew
P ro je ct s a re in B ol d
Co m pl et ed
P ro je ct s a re in It al ic s.
R ef er to b ac k of b in de r f or
Q an d ol de r N ot e:
L ar ge p ro je ct s u til izi ng C
M G
C m et ho d w ill o ve rla p En g/ De si gn w ith
C on st
Pa ge
FY
8/
Q
U pd at e Re vi se d
Le ge nd
La
A cq ui sit io n
PI
D
Pr oj ec t N am e
Di st ric t
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
C om pl et e
FY
9/
De sig n/ P er m itt in g Bi d
C on st ru ct io n Ac tiv ity
O ve rla p
Sc he du le
Ad ju st m en t
FY
1/
FY
0/
Co ns tr uc tio n
Fu nd in g
Ap pr ov ed b y
Co un ci l
FY
6/
FY
7/
FY
8/
PP
-D O
C-
Br an ch Ja il Ro of R ep la ce m en t P ro je ct -P ha se
/1
/2
PP
-D
O C-
Br an ch
Ja il/
Co rr ec tio n Fa ci lit y N et w or k
In fr as tr uc tu re U pg ra de
/1
/2
PP
-D
O C-
Br an ch
Ja il/
Co rr ec tio n Fa ci lit y Se cu rit y an d Te le co m m un ic at io ns
9/ 4/
PP
-D
O C-
Br an ch
Ja il/
Co rr ec tio n Fa ci lit y O pe ra tio ns
S ys te m s U pg ra de
/1 /2
PP
-D
O C-
Br an ch
Ja il
Ro of
R ep la ce m en t P ro je ct
- P ha se
/1 /2
PP
-F
R-
Fi re
S ta tio n
O st ee n Re no va tio n
/1 /2
PW
-C O
S-
Ar go sy P ar k
- 1
O ce an sh or e Bl vd
O rm on d-by -t he -S ea
/1
/2
PW
-C
O S-
Su n
S ur f P ar k
- 7
N
. A tla nt ic
A ve
Da yt on a Be ac h
/1 /2
PW
-C O
S-
Ca rd in al
A ve nu e
O ff-be ac h Pa rk in g
- 6
S
. A tla nt ic
A ve
O rm on d be ac h
/1 /2
PW
-C
O S-
Pl az a
Be ac h Ra m p
Pu bl ic A cc es s I m pr ov em en ts
4/ 3/
PW
-C
O S-th A ve nu e O ff- Be ac h
Pa rk in g
B ea ch
A cc es s
/2 /2
*P W
-C O
S-
Ed w in W
. P ec k, S r.
Pa rk (3
S.
A tla nt ic A ve
Da yt on a
Be ac h Sh or es
/5
/2
*P W
-C O
S-
Da hl ia A ve . P ar k
(3
S.
A tla nt ic
A ve
Da yt on a Be ac h
Sh or es
/5 /2
PW
-D
TT
-6
Th or nb y
Pa rk
W at er Q ua lit y Im pr ov em en t P ro je ct
8/
/2
PW
-E
N G-
Te nt h St re et
M yr tle to U
S
5/
7/
PW
-E
N G-
Ho w la nd
B lv d
- P ro vi de nc e Bl vd to
E lk ca m
B lv d
8/ 4/
PW
-E
N G-
-1 Ve te ra n' s M em or ia l B rid ge
5/
7/
PW
-E
N G-
O ra ng e
Ca m p Rd
M
LK
B lv d to I-
8/ 4/
PW
-E N
G-
-2
Sp rin g to
S pr in g
Ph as e 3A
De tr oi t T er ra ce to D on al d E
Sm ith
B lv d
4/ 6/
PW
-E
N G-
-3 Sp rin g to S pr in g Ph as e
3B
Ro b
Su lli va n
Pa rk to D irk se n Dr
/U S1
7-
4/
6/
PW
-E N
G-
Tu rn bu ll Ba y Br id ge
R ep la ce m en t
1/ 7/
PW
-E
N G-
W es t P ar k Av e 3-
La ne
W id en in g
- O ld M iss io n Rd to M as se y Ra nc h
Rd
5/
/2
PW
-E N
G-
Do yl e
Ro ad
P av ed S ho ul de rs
Lu sh L n to
C ou rt la nd B lv d
5/
1/
PW
-E
N G-
W ill ia m so n
Bl vd
LP
GA
B lv d to S tr ic kl an d Ra ng e
Rd
3/ 6/
PW
-M
SC
-1
M ar in e
Sc ie nc e
Ce nt er R en ov at io n
9/
/2
PW
-R
B-
Pu bl ic W or ks
N or th ea st S er vi ce s F ac ili ty
/3 0/
PW
-S W
-2 To m ok a Fa rm s S ou th w es t F ac ili ty
O pe ra tio ns
C en te r B ui ld in g
/1 /2
Pu bl ic P ro te ct io n
Pu bl ic W or ks
Page 2 of Gantt chart
M
AS
TE
R
CA
PI
TA
L
PR
O
JE
CT
S
CH
ED
U
LE
SO
RT
ED
B Y
PR
O
JE
CT
N U
M
BE
R (P
ID
*N ew
P ro je ct s a re in B ol d
Co m pl et ed
P ro je ct s a re in It al ic s.
R ef er to b ac k of b in de r f or
Q an d ol de r N ot e:
L ar ge p ro je ct s u til izi ng C
M G
C m et ho d w ill o ve rla p En g/ De si gn w ith
C on st
Pa ge
FY
8/
Q
U pd at e Re vi se d
Le ge
La
A cq ui sit io n
PI
D
Pr oj ec t N am e
Di st ric t
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
C om pl et e
FY
9/
De sig n/ P er m itt in g Bi d
C on st ru ct io n Ac tiv ity
O ve rla p
Sc he du le
Ad ju st m en t
FY
1/
FY
0/
Co ns tr uc tio n
Fu nd in g
Ap pr ov ed b y
Co un ci l
FY
6/
FY
7/
FY
8/
PW
-S
W -4
Ci tiz en s C on ve ni en ce Im pr ov em en t - H ou se ho ld
H az ar do us W as te
D ro p
/1
/2
PW
-S
W -5
To m ok a
Fa rm s R d
La nd fil l -
C la ss I
La nd fil l E xp an sio n
/1 /2
PW
-T E-
Pl ym ou th A ve
S to ne S t - N ew
P ol e De sig n
/1 /2
PW
-T E-
M as on
A ve
Ji m m y An n
- C on ve rs io n to
M as t A rm
S ig na l
/1 /2
PW
-T
E-
Pi on ee r T ra il
E nt er pr ise
A ve nu e in N ew S m yr na B ea ch to m as t a rm
/1
/2
PW
-T E-
Sa xo n
Bo ul ev ar d
M ar ke t P la ce in O ra ng e Ci ty to m as t a rm
/1
/2
PW
-W
RU
-5
De lto na N or th
W at er T re at m en t F ac ili ty
U pg ra de s
/1
/2
PW
-W
RU
-6 Ha lif ax
W as te w at er
T re at m en t F ac ili ty R eh ab ili ta tio n
/1 /2
PW
-W
RU
-8
Ad va nc ed
M et er In fr as tr uc tu re
(A M
I)
/1
/2
*P W
-W
RU
-9 G le n
Ab be y Su bd iv is io n Re cl ai m ed
W at er M ai n
Ex te ns io n
/1
3/
SO
-5
N ew S he rif f's E vi de nc e
St or ag e
B ui ld in g
F or en sic s L ab
5/
/2
Sh er iff 's
O ff ic e
Page 3 of Gantt chart
FY 18/19 Q3 Update Project Complete
BS-CES-1
Site: New Court/ Central Services Warehouse - Indian Lake Road, adjacent to Facilities Services.
Acquisition: Location currently owned by Volusia County.
Project Scope: Construct new building and related improvements at another property.
Warehouse to provide secure storage of documents, materials, supplies and equipment. Includes integrated security system, building automation and climate control for court records.
Design Timeline: Start: 1st Qtr. – FY 16/17 Finish: 3rd Qtr. – FY 17/18
Project Cost: $ 3,400,000
Funding Sources: $ 3,400,000 Court/Central Services Warehouse (368-930-4190-6200)
Council Actions: 10 year capital improvement plan approved by council 3rd Qtr. FY 14/15 Architectural Design Firm (Schenkel Shultz) Selection on April 6, 2017.
Architectural Design Firm approved SOW & Fee on September 7, 2017.
CM/GC Firm Selection (Wharton-Smith) on August 7, 2017.
CM/GC Part A (pre-construction) SOW & Fee on December 21, 2017.
CM/GC Part B (Construction) GMP August 7, 2018.
Construction Timeline: Start: 4th Qtr. – FY 16/17
Finish: 3rd Qtr. – FY 18/19
Project Status: Advertisement of request for qualifications for design Consultant on 12/04/16.
Request for Qualifications closed on 1/26/17.
First meeting with design Consultant to discuss Scope of Work (SOW) on 4/14/17.
Received final SOW & Fee proposal from design Consultant and Sent to Purchasing on 8/1/17.
Advertisement of request for qualifications for CM/GC 7/2/17 Request for qualifications for CM/GC closed on 08/03/17
Design finalized Permitting in progress GMP finalized Groundbreaking projected for late September /early October 2018 Construction underway and on schedule Substantial Completion date: 5/24/2019
Project Adjustment: Project Completed.
BS-CES-1 (Continued)
FY 18/19 Q3 Update Revised 062419
BS-CES-2
Site: New Elections Warehouse
Acquisition: Site TBD
Acquisition Timeline: Start: 1st Qtr. - FY 18/19 Finish: 2nd Qtr. - FY 19/20
Project Scope: New building on new site to include warehouse space, staff work areas, shipping/ loading area, improved security, safety, energy efficiency and related site improvements.
Design Timeline: Start: 2nd Qtr. - FY 19/20 Finish: 1st Qtr. - FY 20/21
Project Cost: $ 5,900,000
Funding Sources: $ 6,500,000 Elections Warehouse (367-930-4180)
Council Actions: 1. 10-year capital improvement plan approved by council 3rd Qtr. FY 14/15
Construction Timeline: Start: 2nd Qtr. - FY 20/21
Finish: 1st Qtr. - FY 21/22
Project Status: Investigating site locations with discussions involving the Supervisor of Elections and management.
Project Adjustment: NA
See pic below: Demand exceeds building capacity at existing elections warehouse
FY 18/19 Q3 Update Revised 053019
BS-IT-1
Site: Countywide - 800 MHz Radio System Backbone and Radios
Acquisition: 800 MHz Public Safety Radio System was implemented in 1993
Project Scope: Planning, design, and implementation of modern P25 Phase II 800 MHz public safety radio system. The existing 800 MHz radio system, which includes the microwave system, was implemented in 1993. The equipment and technology has reached end-of-life and will be upgraded/replaced as part of this project. The system supports over 9,000 radios used countywide by county and city agencies. In Phase I, a radio system consultant will assist the county in assessing existing assets, evaluating microwave and radio system technology, performing high levels needs assessments, and providing financial and technical options analysis. In Phase II, the consultant will assist with radio system design and specifications, procurement, and implementation.
Design Timeline: Phase I – Radio System Modernization Assessment and Planning
Start: 1st Qtr. - FY 16/17 Finish: 3rd Qtr. - FY 17/18
Phase II – Radio System Modernization Design and Procurement
Start: 3rd Qtr. - FY 17/18 Finish: 1st Qtr. - FY 19/20
Project Cost: $ 19,596,072 (estimated) County of Volusia $ 7,000,000 (estimated) City Budgets $ 26,596,072 (estimated) Total
Funding Sources: $ 12,666,330 305-930-4605 General Fund $ 6,929,742 305-930-4606 800 MHz Capital Radio Replacement $ 7,000,000 City Budgets $ 26,596,072 Total
Council Actions: 1. Mini-Budget Workshop July 7, 2016
2. Radio System Consultant Award January 18, 2018
3. Approval of Direction to Issue RFP December 4, 2018
Construction Timeline: Phase II
Start: 1st Qtr. - FY 19/20 (Begin implementation) Finish: 4th Qtr. - FY 20/21
FY 18/19 Q3 Update Revised 053019
BS-IT-1 (Continued)
Project Status: Phase I - Complete
Phase II Task order issued to consultant to assist in RFP development. Soil testing work and site preparation cost estimates underway for land identified for additional tower in southeast Volusia; development of cooperative agreement with Flagler County to share tower space underway.
12/2018: Direction changed to combine microwave and radio system procurement into one RFP solicitation; requirement for two new towers added into the radio system backbone design and work effort; separated procurement process timeline from implementation schedule for tracking clarity.
Development of microwave and radio system RFP scope of work near completion with planned release in July 2019.
Project Adjustment Updated Construction cost estimates based on latest information.
CS-LIB-3
Site: Hope Place Library Services Facility
Acquisition: Donation approved July 6th, 2017 by County Council
Project Scope: Construct a new neighborhood branch library.
Design Timeline: Start: 1st Qtr. - FY 16/17
Finish: 2nd Qtr. - FY 17/18
Project Cost: $ 94,887 Design $ 971,771 Construction $ 1,066,658 Total
Funding Sources: $ 1,066,658 Community Development Block Grant (CDBG)
Council Actions: 1. Architectural Design Firm Selection March 2, 2017
2. Architectural Design Awarded March 2, 2017
3. CMGC Firm Selection May 4, 2017 Part A (pre-construction)
4. CMGC Approval March 6, 2018 Part B (construction)
Construction Timeline: Start: 3rd Qtr. - FY 17/18 Finish: 3rd Qtr. - FY 18/19
Project Status: Conceptual design complete. Schematic design at 30%.
Negotiating Part A fee of Task Assignment with CMGC Architectural Design Firm Task Assignment Initiated: 1st Qtr. FY 16/17 Advertisement of CMGC Solicitation for Bid: 1st Qtr. FY 17/18 Prebid Meeting 1st Qtr. FY 17/18 Project addendum issued 2nd Qtr. FY 17/18 Subcontractor Bids due 2nd Qtr. FY 17/18 Guaranteed maximum price to County Council 2nd Qtr. FY 17/18 Construction Kickoff Meeting March 22, 2018 Notice to Proceed April 16, 2018 Construction at about 75% completion Exterior canopy and concrete work left to complete Completed on May 16, 2019 Ribbon cutting held on June 19, 2019
Project Adjustment: Change in finish date due to 23 days’ inclement weather and 30 days of foundation redesign. Manufacturer delay in glass and storefront delivery. Contractor scheduling includes additional delays as well. Construction estimated completion is now projected to be mid to late April.
CS-LIB-3 (Continued)
FY 18/19 Q3 Update Revised 052119
CS-PRC-1
Site: Lemon Bluff Park
Acquisition: March 13, 2013 (ECHO Funds)
Project Scope: The project scope includes restoration of the seawall and dockage, construction of a boat launch, floating canoe/kayak launch, fishing area, restrooms, pavilions (2), parking, and sidewalks.
Design Timeline: Start: 3rd Qtr. – FY 15/16 Finish: 4th Qtr. – FY 18/19
Project Cost: $ 150,000 Design $ 1,490,852 Construction $ 1,640,852 Total
Funding Sources: $ 400,000 2016 Council ECHO grant award $ 125,000 FIND Grant $ 1,115,852 Funded from FBIP $ 1,640,852 Total
Council Actions: 1. Purchase Approval December 20, 2012
2. Contract Task Assign – DMC March 17, 2016
3. ECHO Grant Approval May 19, 2016
4. FIND Grant September 30, 2017
5. Conceptual Drawing Approval May 7, 2019
Construction Timeline: Start: 1st Qtr. – FY 19/20 Finish: 4th Qtr. – FY 19/20
Project Status: Met with public on May 13, 2017 Second public meeting was held on October 18, 2018 Boat Launch Facility plans (excluding parking area) 60% Parking area design underway
Project Adjustment: County Council provided direction on conceptual plan to maximize parking on the west side of Lemon Bluff Road
FY 18/19 Q3 Update Revised 052119
CS-PRC-1 (Continued)
FY 18/19 Q3 Update Revised 071819
DAB – TER-03 (Continued)
Plan view of parking lot and roadway pavement areas
The design program for the Terminal Parking Lot Improvements Program consists of four (4) individual project packages. The four projects are:
(1) Parking Lot Paving Project;
(2) Replacement of High Mast Parking Fixtures and lighting Improvements;
(3) Replace Wayfinding Signage and,
(4) Design and Construct Ticketing Canopy’s.
FY 18/19 Q3 Update New Project
PW-COS-18
Site: Edwin W. Peck, Sr. Park (3167 S. Atlantic Ave., Daytona Beach Shores)
Project Scope: Design, permitting and construction of a beachfront park with 102 parking spaces including 6 ADA compliant parking stalls. Other amenities include a restroom, playground equipment, fitness stations, showers, bike racks, grills and an ADA dune walkover.
Design Timeline: Start: 1st Qtr. – FY 15/16
Finish: 1st Qtr. – FY 19/20
Project Cost: $ 181,100 Design $ 1,800,951 Construction $ 1,982,051 Total
Funding Sources: $ 1,982,051 from Beach Capital
Council Actions: Approval of TA for design November 2015 Agreement reached between DBS and County August 2018
Naming of Edwin W. Peck, Sr. Park December 2018
Construction Timeline: Start: 2nd Qtr. – FY 19/20
Finish: 1st Qtr. – FY 20/21
Project Status: Design task assignment issued November 2015
Amendment to design TA December 2018 Topographic survey completed January 2019 Geotechnical testing completed April 2019 30% plans completed April 2019
FY 18/19 Q3 Update New Project
PW-COS-19
Site: Dahlia Ave. Park (3621 S. Atlantic Ave., Daytona Beach Shores)
Project Scope: Design, permitting and construction of a beachfront park with 61 parking spaces including 3 ADA compliant parking stalls. Other amenities include a restroom, playground equipment, picnic pavilions, showers, bike racks, grills and an ADA dune walkover. Construction will include demo of existing structures.
Design Timeline: Start: 1st Qtr. – FY 15/16
Finish: 1st Qtr. – FY 19/20
Project Cost: $ 138,600 Design $ 1,062,562 Construction $ 1,201,162 Total
Funding Sources: $ 1,201,162 from Beach Capital
Council Actions: Approval of TA for design November 2015 Agreement reached between DBS and County August 2018
Construction Timeline: Start: 2nd Qtr. – FY 19/20
Finish: 1st Qtr. – FY 20/21
Project Status: Design task assignment issued November 2015 Amendment 1 to design TA February 2016
Amendment 2 to design TA December 2018 Topographic survey completed January 2019 Geotechnical testing completed April 2019 30% plans completed April 2019
Everyone off campus should get in on the census.
If you live off campus, responding to the 2020 Census is an important and easy way to shape your future. The census impacts federal funding that goes toward critical programs like Pell Grants and health care services.
Students who live on campus count too, with the help of campus housing officials.
2020CENSUS.GOV
D-HP-HE-EN-026
https://2020census.gov/en
Census data impacts funding for things like:
• School safety
• Federal Pell Grant Program
• Adult education grants
• Agriculture, science, and engineering education
• Community mental health services
• Student wellness programs
• Medical Assistance Program
• School breakfast and lunch and after-school programs
• State Children’s Health Insurance Program
For more information, visit:
2020CENSUS.GOV
https://2020census.gov/en
Emergency Medical Administration
Director
Special Projects Coordinator Medical Director
Deputy Medical Director
Administrative Assistant
Category
FY 2022-23
Adopted Budget
FY 2023-24
Notes
Personnel Services $587,350 -
Operating Expenses $308,119 -
Grants and Aids $1,703,808 Florida Medicaid Public Emergency
Medical Transport (PEMT)
Interfund Transfers $6,617,677 EMS Transfer
Total $9,216,954 -
Funded Full-time Equivalent 4.5 -
Funding Source(s) General Fund -
Fund 717 - Emergency medical services trust fund $409,168
The Division of Emergency Medical Administration provides regulatory and clinical oversight to the entire (county and municipal) emergency medical services system.
STEMI (heart attack)
1,085
Stroke
Trauma, pediatric
Trauma, adult
1,150
Cardiopulmonary arrest
Emergency medical telecommunicator
Emergency medical technician
Paramedic 476
Activities
Legislatively-mandated activities.
Access to prescription medications, controlled substances, and legend devices.
Emergency medical services-to-hospital interface.
Certificates of public convenience and necessity (biennial).
Licensure and registration
Credentialing and provision/approval of continuing medical education.
Manage electronic patient care reporting platform.
System analysis.
Contracted services software - $231,883 EMS Charts, MARVLIS, and ArcGIS
Vehicle lease - $19,000
Medical malpractice and liability insurance - $15,305
Professional development - $19,133
Largest operating expense (software) makes up 75% of total operating budget.
Other - $21,053 or 7%
Automating select processes (e.g., quality assurance) to gain efficiencies and effectiveness.
Conversion from Zoll to EMS charts Functionality, performance, quality assurance, and reporting.
| CPSFY18_19Q3_Final_WebADA |
| 3rd Quarter 062019 |
| CPSFY18_19Q3_Final_WebADA1 |
| _Cover-main_ADA |
| Master - Gantt Draft PDF_ADA1 |
| Cover Sheet |
| Master |
| _Highlighted_ADA1 |
| BS-CES-1 |
| BS-CES-2 |
| BS-IT-1 |
| CS-LIB-03 |
| CS-PRC-01 |
| CS-PRC-02 |
| CS-PRC-18 |
| CS-PRC-19 |
| CS-PRC-20 |
| DAB-AF PAV-01-A |
| DAB-AF PAV-01-B |
| DAB-TER-03 |
| DAB-TER-07 |
| OC-118-08 |
| OC-318-02 |
| OC-318-07 |
| OC-318-12 |
| OC-475-2 |
| OC-475-4 |
| PP-DOC-08 |
| PP-DOC-9 |
| PP-DOC-10 |
| PP-DOC-12 |
| PP-FR-1 |
| PW-COS-6 |
| PW-COS-9 |
| PW-COS-14 |
| PW-COS-17 |
| PW-COS-18 |
| PW-COS-19 |
| PW-DTT-6 |
| PW-ENG-5061 |
| PW-ENG-5240 |
| PW-ENG-5351-1 |
| PW-ENG-5395 |
| PW-ENG-5511-3 |
| PW-ENG-5712 |
| PW-ENG-5766 |
| PW-ENG-5797 |
| PW-MSC-01 |
| PW-RB-1 |
| PW-SW-4 |
| PW-SW-5 |
| PW-TE-09 |
| PW-TE-10 |
| PW-WRU-5 |
| PW-WRU-6 |
| PW-WRU-8 |
| PW-WRU-9 |
| SO-5715 |
| Cover-completed_ADA |
| _Completed_ADA |
| PP-DOC-05 |
| PW-COS-5 |
| PW-ENG-5511-2 |
| PW-ENG-5634 |
| PW-SW-2 |
| PW-TE-07 |
| PW-TE-08 |
| colleges-flyer |
| 2023-EMA-Budget-Service-Level-Presentation-ADA-FINAL-with-MW-adjustmentsfinal.pdf |
| Slide 1: Emergency Medical Administration |
| Slide 2: Emergency Medical Administration – Organizational Chart |
| Slide 3: Emergency Medical Administration Division Budget |
| Slide 4: Emergency Medical Administration – Summary of Operations |
| Slide 5: Calendar Year 2022 – System-wide by the numbers |
| Slide 6: Emergency Medical Administration – Summary of Operations Continued |
| Slide 7: Operating Expenses |
| Slide 8: Future Challenges |
| Slide 9: Questions/Direction |
File details come from the government source that posted it. Updated .