ACRx San Antonio.McAllen SOW.pdf
PDF 1 MB Posted
- Attached to
- ACRx San Antonio and McAllen, Texas
- Solicitation number
- 15F06726Q0000448
About this file
Statement of Work Summary
This Statement of Work (SOW) details antenna and tower installation services for the Federal Bureau of Investigation's Operational Technology Division at three communications tower sites in southern Texas. The contractor must install four Janteq SuperSector antennas at Olmito Tower (500 feet tall), four Cambium PTP-820 dishes across all three towers, fiber optic cables, LMR 400 coaxial cables, grounding systems, cable management equipment, and an indoor equipment cabinet at Santa Maria Tower (1,397 feet tall). Additional work includes pre-installation site walks, building permit acquisition, utilities coordination for electrical circuits, cable testing and alignment, and site cleanup. Work locations are Olmito Tower in Los Fresnos, Santa Maria Tower in La Feria, and Flamingo Tower in McAllen, all in Texas. The contractor must possess Motorola R56 Installer Certification, Competent Rigger Certification, and Competent Tower Climber Certification, with a minimum of two years of similar experience. Insurance requirements include Commercial General Liability ($1 million each occurrence), Automobile Liability ($1 million combined single limit), Excess Liability ($3 million), and Workman's Comp ($1 million per accident).
The contract period is 180 days from award, with installation completion required by Tuesday COB to allow FBI testing and personnel training Wednesday through Friday. Quotes must be submitted electronically in two volumes—Volume A (Technical, maximum 10 pages excluding certifications) and Volume B (Price, unlimited pages)—using a Fixed Price structure for Services/Materials (CLIN 0001) and Time & Materials for Travel/ODCs (CLIN 0002). The Government will award based on "Lowest Price Technically Acceptable" (LPTA) methodology, evaluating technical acceptability first, then selecting the lowest-priced technically acceptable offer. Quote submission deadline is September 17, 2026, at 12:00 PM Central Time to dehankins2@fbi.gov, with anticipated award on September 23, 2026. Questions must be submitted by September 14, 2026. The FBI will provide Government-Furnished Equipment including cables, antennas, brackets, and construction drawings. Electronic invoicing is required through the Invoice Processing Platform (IPP). All quotes must remain valid for 30 days.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ 15F06726Q0000448.pdf | ||
| Santa Maria Tower CD.pdf | ||
| Flamingo Tower CD.pdf | ||
| Olmito Tower CD.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment C – Statement of Work Version 2.6 Page 1
FEDERAL BUREAU OF INVESTIGATION
FINANCE AND FACILITIES DIVISION | PROCUREMENT SECTION
STATEMENT OF WORK
ACRx Tower and Antenna Installation Services at
Olmito Tower, Los Fresnos, Texas
And
Santa Maria Tower, La Feria, Texas
And
Flamingo Tower, McAllen, Texas
For the Operational Technology Division
Statement of Work
9/10/2026
Attachment C – Statement of Work Version 2.6 Page 2
1 Scope The contractor must provide antenna installation, ancillary equipment installation, and dish alignment services on multiple towers and within respective communication rooms for the Federal Bureau of Investigation (FBI), Operational Technology Division (OTD), at three sites along the southern Texas border.
This is a non-personal services contract. The FBI must not exercise any supervision or control over contractor employee services performing the services herein. Such contract service providers must be accountable solely to the contractor who, in turn, is responsible to the FBI.
1.1 Description of Services/Introduction
The objective of this contract is to procure services for the installation of antennas and ancillary equipment in support of the Adaptive Central Receive (ACRx) effort for the FBI’s Video Surveillance Unit.
Please reference Section 3 below for details regarding the required installation services.
1.2 Background
The FBI has identified the need to install new active antenna systems at multiple guy-wire towers along a confined region of the southern Texas border. Each location is more explicitly described below:
Olmito Tower, a five hundred foot (500’) tall communications tower at 1540 California Road, Los Fresnos, TX, 78566; 26°2’59.1” N, 97° 31’11” W.
Santa Maria Tower, a one thousand ninety-seven foot (1397’) tall communications tower at 31578 County Road 629, La Feria, TX, 78559; 26°6’2.79” N, 97° 50’ 19°49” W.
Flamingo Tower, a four hundred forty foot (440’) tall communications tower at 1804 Flamingo Avenue, McAllen, TX, 78559; 26°15’ 25.25” N, 98 13°54.51” W.
1.3 North American Industry Classification System (NAICS)
The North American Industry Classification System (NAICS) Code for this requirement is 237130, Power and Communication Line and Related Structures Construction.
1.4 Applicable Acquisition Procedures
The Government will conduct this acquisition in accordance with FAR Part 12, Acquisition of Commercial Products and Commercial Services.
1.5 Vendor Registration Requirements
Offerors must maintain an active registration in the System for Award Management (SAM) at all
Attachment C – Statement of Work Version 2.6 Page 3 of the following stages: at the time of quote submission; at the time of contract award; and throughout contract performance until final payment is made.
2 Applicable Documents Multiple site construction drawings will be provided to the vendor by the FBI as part of this solicitation.
3 Requirements/Task Descriptions The contractor must provide installation and ancillary services as follows:
3.1 Pre-Installation Site Walk
After award, the successful contractor must coordinate with the local site management of the Olmito tower, Santa Maria tower, and Flamingo tower, to perform site walks of the premises to include the tower areas and communications rooms, verify construction drawings, and discuss any deviations and changes with FBI technicians. These site walks must be executed at least 30 days prior to the actual installation to allow time for preparation and handling of any unique requirements or changes that could emerge during this visit that could impact the installation. This visit should be considered a separate action apart from the installation.
3.2 Building Permits
The contractor must obtain building permits through the controlling legal authorities for the installations at multiple sites including the identified towers and communication rooms. The contractor must coordinate with the FBI for all documentation required to obtain the building permits.
The contractor must coordinate with the FBI to submit the building permits and contractor credentials to local site management of the Olmito Tower, Santa Maria Tower and Flamingo Tower to obtain the Notice to Proceed (NTP) at all locations. If required, the contractor must register with the necessary controlling legal authorities for approvals and work permits.
3.3 Cable Entry Protection
The contractor must provide and install cable entry boots to facilitate the installation and block off unused entry panel holes.
3.4 Janteq SuperSector Antenna Installation
The contractor must install a total of four (4) Janteq SuperSector antennas on the Olmito tower (provided by the FBI) as part of this installation:
Two (2) Janteq SuperSector antennas must be stacked vertically on Leg A with center lines at 360 feet and 354 feet Above Ground Level (AGL) at an azimuth of Zero (0°) degrees.
Two (2) Janteq SuperSector antennas must be stacked vertically on Leg B with center lines at 360 feet and 354 feet AGL at an azimuth of One-hundred and eighty (180°) degrees.
The contractor must provide and install new antenna tower mounts for the four (4) SuperSector antennas.
Antenna drawings will be provided to the contractor by the FBI so suitable antenna mounts can be chosen. Antenna mount options and orientation will be discussed with contractor prior to any
Attachment C – Statement of Work Version 2.6 Page 4 installation work so the FBI may provide final approvals prior to installation. Construction drawings will be provided by the FBI as part of this solicitation.
3.5 Fiber Tower Box Installation
The contractor must install one (1) Fiber Tower Box on each SuperSector antenna mount assembly, for a total of four (4) Fiber Tower Boxes. Each Fiber Tower Box must be mounted within 10 to 15 feet of a SuperSector antenna. The contractor is responsible for providing mounting hardware for the Fiber Tower Box. The contractor must install the FBI-provided fiber cables to the internal patch panel using contractor-provided gland feed-throughs. Drawings for the Fiber Tower Box will be provided to the contractor by the FBI as part of the Construction Drawings. The contractor must work with FBI Field Technicians to clean or replace the fiber cables if necessary after the FBI runs calibration tests post-install.
3.6 Fiber Cable Installation
The contractor must install four (4) 12-core fiber cables (½ inch diameter) from the inside of the equipment room to the Fiber Tower Box using new or existing entry boots, cable hangers, and conduit. The contractor must supply any new cable hangers, cable hanging accessories, and conduit if required. The fiber cable will be provided by the FBI in four separate spools.
3.7 Fiber Cable Testing
FBI Field Technicians will use an optical time-domain reflectometer (OTDR) or Optical Power Meter with Optical Light Source to determine if there are any problems with the fiber strands. The contractor must assist in any inspection, cleaning, or moving of fiber cables in the mounted Fiber Tower Box.
3.8 LMR 400 Coaxial Cable for SuperSector Antennas
The contractor must install four (4) LMR 400 coaxial cables from the inside of the equipment rooms, with proper grounding and lightning arrestors, to the SuperSector antennas (1 per SuperSector antenna), using either existing or contractor-provided entry boots, cable hangers, and conduit. The contractor must terminate the SuperSector end of the LMR 400 cables with provided DIN connectors, and the equipment room end of the LMR 400 cables with N-Type connectors. The LMR 400 cables required for the full installation of antennas across all sites will be provided by the FBI in multiple spools.
3.9 Cambium PTP-820 Dish Installations
The contractor will install a total of four (4) four-foot (4’) diameter Cambium dishes with eight (8) PTP-820 Outdoor Units (ODUs) across all three towers (provided by the government as GFE).
One (1) four-foot (4’) Cambium dish assembly must be installed on Leg C at three hundred forty-nine (349) feet AGL on the Olmito Tower at an azimuth of two hundred seventy-seven and twelve hundredths (277.12°) degrees.
Two (2) four-foot (4’) Cambium dish assemblies must be installed on two separate tower legs at five hundred (500) feet AGL on the Santa Maria Tower – on the northwest leg at an azimuth of two
Attachment C – Statement of Work Version 2.6 Page 5 hundred ninety and eighty-three hundredths (290.83°) degrees and on the eastern leg at an azimuth of ninety-six and ninety-seven hundredths (96.97°) degrees.
One (1) four-foot (4’) Cambium dish assembly must be installed on the southeast leg at one hundred and seventy-two feet (172) feet AGL on the Flamingo Tower at an azimuth of one hundred and ten (110°) degrees.
Ground kits for the ODUs will be provided by the Government and the contractor must properly ground the ODUs to the tower.
3.10 LMR 400 Coaxial Cable for PTP-820 Installation
The PTP-820 uses a dual ODU configuration requiring two (2) LMR 400 coaxial cables to be connected per assembly. The contractor must install two (2) new LMR 400 coaxial cables provided by the FBI from the equipment rooms to each PTP-820 [for a total of eight across all sites for the Cambium dish assemblies] using all appropriate grounding and lightning arrestors. Any hangers required must be provided and installed by the contractor. As noted in Section 3.8, the FBI will provide all LMR 400 cables for all sites in multiple separate spools.
3.11 PTP-820/Dish Alignment
The contractor must assist the Field Technicians in aligning the Cambium dishes between multiple towers including between Olmito Tower and Santa Maria Tower, and between Santa Maria Tower and Flamingo Tower. This will include panning the dish and reading the voltage levels from the ODUs while on the towers. This will require tower crews to be at multiple sites simultaneously to align the dishes.
3.12 Grounding
The contractor must ground all antennas on the tower to Motorola R56 standards. The contractor must ground a total of twelve (12) LMR 400 cables (specified in Sections 3.8, 3.10) to the exterior ground bars of the shelters. If no exterior ground bar exists, the contractor must provide and install the exterior ground bar to Motorola R56 standards.
The contractor must provide and install an interior ground bar near the cable port of entry no smaller than a Maxground MG212U. The FBI will install twelve (12) S580-235-M lightning arrestors and terminate the LMR cables at the internal ground bar. The contractor must ground the equipment cabinet to the shelter ground to Motorola R56 standards.
3.13 External Cable Management
The contractor must install cables to follow a direct path to shelter cable penetration. The specific layout and requirements for cable management will be determined during the pre-installation site walk (Section 3.1). The contractor must coordinate with site management to determine the best method of securing cables to the towers and shelters. The contractor must provide and install the cable management equipment (boots, hangers, conduit, etc) if existing cable management equipment or space is not adequate for our installation. The contractor must coordinate with site management to determine if new additional entry ports are required per the construction drawings.
3.14 Internal Cable Management
Attachment C – Statement of Work Version 2.6 Page 6
The contractor must assist the FBI in properly securing the cables from the interior ground bars to the equipment racks in the communications rooms/shelters. This can include climbing ladders and assisting with mounting cable hangers to ceilings, installing grommets, and other assorted tasks to properly secure cables.
3.15 Utilities
The contractor must coordinate with the tower site’s management to identify an approved electrical contractor.
At the Olmito Tower, the installation contractor must coordinate the installation with the electrical contractor of two separate 20A 120V circuits terminating in L5-20 twist lock female receptacles above or near the equipment rack location.
At the Santa Maria Tower, the contractor must coordinate the installation with the electrical contractor of one 20A 120V circuit terminating in L5-20 twist lock female receptacle above or near the equipment rack location.
It is the vendor’s responsibility to acquire these electrical services with the approved electrical contractor and include this work in their price quote.
3.16 Indoor equipment Cabinet
The contractor must procure and install an indoor equipment cabinet in the communications room of the Santa Maria tower. This indoor rack should be a 24U rack height with doors and sides identical or similar to a Hammond Rack Basics Economy Server Cabinet item RB-DC2442.
3.17 Cleanup and Equipment Removal
The contractor must remove and dispose of any refuse associated with the installation and remove or dispose of unused or unnecessary supplies which were provided. The government cannot ship or store unused supplies and has little utility for things like partial spools of cable, etc. Any equipment associated directly with the antennas (SuperSector or Cambium gear) that was not used during the install must be brought to the FBI’s attention and returned to the FBI’s possession.
3.18 Permitting
The contractor will be responsible for ensuring all unique permitting and certifications are in place that may be required to perform work in the McAllen, TX region.
4 Scheduling of Installation
The period of performance will begin on the date of contract award and will end no later than 180 days after contract award. The contractor must coordinate with and provide advance notice to the Contracting Officer’s Representative (COR) (identified in Section 11 below) at least two weeks prior to commencement of installation activities to ensure all pre-installation actions have been completed by all parties involved.
Installation efforts may begin on the weekend if required, but all installations must be completed no later than Tuesday COB on any standard work week to allow time for FBI antenna alignment, testing, troubleshooting, possible repairs and personnel training which are typically planned for Wednesday
Attachment C – Statement of Work Version 2.6 Page 7 through Friday with FBI personnel. The contractor should plan to ensure enough time is allotted in their schedule to be fully complete with installation work on or before the Tuesday of a work week. The contractor must not leave the work site until the FBI has indicated all services are complete and they are no longer required onsite.
5 Contractor Certifications The contractor must have at least two years of experience performing work of similar size and scope.
The contractor must possess Motorola R56 Installer Certification and adhere to the requirements of that certification.
The contractor must possess Competent Rigger Certification accredited through an organization such as COMTRAIN or SafetyLMS.
The contractor team proposed for this work must have at least one team member with Competent Tower Climber Certification with additional team members having at least Authorized Tower Climber Certification.
The contractor must coordinate with tower/site management to ensure they possess a certificate of insurance meeting the minimum insurance coverage requirements for the sites involved:
Type of Insurance Details
Commercial General Liability Each Occurrence: $1,000,000 Damage to Rented Premised per Occurrence: $100,000 Medical Expense per Person: $5,000 Personal & Adv Injury: $1,000,000 General Aggregate: $2,000,000 Products Comp/Op Agg: $2,000,000
Automobile Liability Combined Single Limit: $1,000,000
Excess Liability Each Occurrence: $3,000,000 Aggregate: $3,000,000
Workman’s Comp and Employer Liability
Each Accident: $1,000,000 Disease Each Employee: $1,000,000 Disease Policy Limit: $1,000,000
Professional/Pollution Liability $1,000,000 / $1,000,000
The contractor must provide proof at time of quote submission within “Voume A” reflecting that they have the required insurance, or a certification statement that they will be able to obtain insurance that will meet or exceed these requirements. If proof of insurance is not provided at time of quotation, the apparent successful awardee will be notified prior to award and given a two-week deadline to submit insurance documentation. Award is contingent upon receipt of required insurance documentation.
Attachment C – Statement of Work Version 2.6 Page 8
6 Place of Performance The place of performance for this contract is:
the Olmito Tower, 1540 California Road, Los Fresnos, TX 78566; 26°2’59.1” N, 97° 31’11” W, the Santa Maria Tower, 31578 County Road 629, La Feria, TX 78559; 26°6’2.79” N, 97° 50’ 19°49” W, and the Flamingo Tower, 1804 Flamingo Avenue, McAllen, TX 78559; 26°15’ 25.25” N, 98 13°54.51” W.
7 Electronic Invoicing Requirements The FBI requires vendors to submit invoices and supporting documentation electronically through the Invoice Processing Platform (IPP). IPP is a secure, web-based electronic invoicing system provided by the U.S. Department of the Treasury’s Bureau of the Fiscal Service (Treasury) in partnership with the Federal Reserve Bank of St. Louis (FRSTL). IPP is available at no cost to any commercial vendor or independent contractor doing business with a participating government agency. To learn more about IPP, please visit IPP.gov.
Invoice Submission Vendors are required to create and submit electronic invoices using the IPP system. Invoices submitted by email will not be accepted. This requirement applies immediately upon contract award. For contract-specific questions, please contact the designated contracting officer for your contract.
Obtaining IPP Access If your company has already enrolled in IPP:
You will not be required to re-register. Please contact your company’s IPP account administrator so that he/she may add you as an additional user to your company’s IPP Collector account.
If your company has NOT enrolled in IPP:
Your company will be auto enrolled for IPP using information from your SAM.gov account.
Your company’s Primary Electronic Business Point of Contact (POC) will be designated as an IPP administrator. This POC will be contacted by email to register when the FBI initiates the enrollment process through IPP. To prevent enrollment delays, please ensure your designated Electronic Business POC in SAM.gov is up to date.
Your company’s IPP administrator will be responsible for initial account registration as well as creating and managing your company’s IPP users and permissions. Please note that due to U.S.
Department of the Treasury guidelines, IPP cannot set up User UDs using a shared email address.
How to Register for IPP:
Attachment C – Statement of Work Version 2.6 Page 9
1. Once FBI initiates the enrollment process, your company’s designated Electronic Business POC in SAM.gov will receive two emails from IPP Customer Support (ipp.noreply@mail.eroc.twai.gov):
a. The first email contains the initial administrative IPP User ID
b. The second email, sent within 24 hours of receipt of the first email, contains a temporary password
c. You must log in with the temporary password within 30 days
2. Registration is complete when the initial administrative user logs into the IPP web site with the
User ID and password provided and accepts the IPP rules of behavior. Additional user accounts, including administrators, can be created after initial login.
Training Vendor training materials, including a first-time login tutorial, are available on the IPP.gov website. Once you have logged in to the IPP application, you will have access to user guides that provide step-by-step instructions for all IPP capabilities ranging from creating and submitting an invoice to setting up email notifications.
Additional Support IPP Customer Support Team is available Monday through Friday from 8:00am to 6:00pm EST.
- Phone: (866) 973-3131 or Email: IPPCustomerSupport@fiscal.treasury.gov
- For answers to frequently asked questions, visit the Vendor FAQ page on the IPP.gov website.
8 Government Furnished Equipment or Information The FBI will provide contractor with LMR 400 cable, Fiber Optic cable, all antennas, antenna mounting brackets, and antenna polyphasers. The FBI will provide the contractor with antenna and cabling diagrams, construction drawings, and when available, site-specific tower and building rooftop details. As noted in Section 3.1, a pre-installation site visit is essential to ensuring any unique additional equipment or supplies are available for the actual installation.
9 Personnel Availability The contractor’s normal workday will typically be eight work hours a day plus a mandatory thirty-minute lunch within the hours of 6:00 a.m. and 6:00 p.m. Flexibility within the normal workday must be coordinated with the Contracting Officer’s Representative (COR).
10 Security Requirements The contractors will not have access to any FBI facilities or systems. The FBI is responsible for all actions required for connectivity to operational FBI networks.
11 Government Representatives The functions inherent to this contract must be performed by the designated Contracting Officer. The duly assigned COR shall ensure all actions pertaining to this contract are requested via the Contracting Officer.
Attachment C – Statement of Work Version 2.6 Page 10
The COR will be identified via letter of COR delegation authority for this contract. The COR is responsible, as applicable, for receiving all deliverables; inspecting, and accepting the supplies or services provided hereunder in accordance with the terms and conditions of this contract; providing direction to the contractor which clarifies the contract effort, fills in details or otherwise serves to accomplish the contractual Scope of Work; evaluating performance; and certifying all invoices/vouchers for acceptance of the supplies or services furnished for payment.
The COR does not have the authority to alter or modify the contractor's obligations, contract terms, conditions, specifications, or cost. If it is because of technical discussions, it is in the Government’s best interest to alter/change contractual obligations or the Scope of Work, the CO shall issue such changes.
The COR for this contract is Scott Fitch, who can be reached at 571-319-1021 or SCFITCH@fbi.gov.
12 Travel and Other Direct Costs When required and authorized by the COR, travel must be conducted in accordance with Federal Travel Regulations.
Other Direct Costs (ODCs) are authorized. ODCs include additional costs such as permitting, electric modifications, or ad-hoc reactionary redline changes to the installation plan. ODCs must be coordinated with and approved by the PM and/or COR.
13 Terms and Conditions The terms and conditions for this contract are noted in the accompanying ACRx San Antonio and McAllen RFQ (SF18) 15F06726Q0000448.
14 Instructions to Offerors Quotes must be submitted in Volumes designated “Volume A-Technical” and “Volume B-Price”.
Volume A-Technical must reference the requirements delineated in Section 3 - Requirements/Task Descriptions.
(1) Explanation of the Offeror’s capabilities, methods/techniques to address all requirements/tasks listed in this SOW. Each bullet and requirement within each section must be addressed. Rather than merely restating the requirements, please elaborate any unique steps, approaches, methods or processes you might take in order to execute the requirements.
(2) Provide a detailed plan for ensuring the Government’s daily schedule in Section 4 will be met.
This includes how many days the plan will take to execute. Simply stating that the contractor will meet the scheduled timeline is not acceptable.
(3) Provide list of any subcontractors planned to be used per requirement.
(4) Verify evidence of required certifications listed above in Section 5.
a. Motorola R56 Installer Certification
b. Competent Rigger Certification
c. Competent Tower Climber Certification(s)
Attachment C – Statement of Work Version 2.6 Page 11
d. Authorized Tower Climber Certification(s)
e. Insurance Certificate meeting site requirements, or certification statement or acknowledgement that insurance can be obtained meeting requirements.
(5) As noted in Section 5, the contractor must have a minimum of two (2) years of experience performing work of a similar size and scope. Contractors must provide a summary of similar work completed within the past 2 to 5 years. The following information should be provided:
a. Site Name/Customer
b. Brief description of the relevant work completed
c. Dates of work completed
d. Contract value
Volume A is limited to 10 pages (documentation for certifications will not count against page limit). Electronic submissions must be compatible with Microsoft Office 365 and must be in 12-point Times New Roman font.
The proposal must be clear, concise, and must include sufficient detail for effective evaluation and for substantiating the validity of stated claims.
Volume B-Price Quote must include all price quote information, and be split out according to the following CLIN structure:
CLIN Description Type
0001 Services / Materials FFP
0002 Travel / ODCs T&M
Volume B has no page limit. Electronic submissions must be compatible with Microsoft Office 365.
Offerors must clearly itemize each CLIN to the extent possible.
Electronic submission is the only acceptable method of submission. All information should be UNCLASSIFIED. Any company proprietary information should be marked as such.
Respondents should identify their company name, address, CAGE Code, Unique Entity ID (UEID), email address, and a name and telephone number of a point of contact having the authority and the knowledge to clarify responses with government representatives.
The UEID will be validated in SAM.gov, for which vendors must be active to receive an award.
Any responses received after the required submission time are considered late and will not be reviewed or considered for award.
15 Basis of Award
15.1 Evaluation Criteria
Attachment C – Statement of Work Version 2.6 Page 12
The Government intends to select an Offeror for acquisition award based on a “Lowest Price Technically Acceptable” (LPTA) method according to the following:
A. Technical Factor
This factor is used to evaluate the proposed solution denoted in Volume A to ensure all requirements and tasks can be met by the contractor – either Technically Acceptable or Technically Unacceptable.
B. Price
The Government will evaluate the total proposed price. In addition, this evaluation will include an assessment of the Offeror’s quote for completeness and reasonableness.
The Government reserves the right to award based upon initial quotes without negotiations.
Offerors are to submit their best and final offers in the initial quote.
15.2 Rating Methodology
Proposals will be evaluated as follows:
Technical Factor: Each Offeror will be graded either:
“Technically Acceptable:” The Offeror demonstrates they can deliver each of the required products and services identified in this SOW, including each of the special terms and conditions provided.
“Technically Unacceptable:” The Offeror failed to demonstrate that they can deliver each of the required products and services enumerated in this SOW, including each of the special terms and conditions provided.
Price Factor (Lowest Price):
The contractor's proposed pricing will be evaluated for completeness and reasonableness.
Prices that are determined to be unreasonable or inconsistent with prevailing commercial practices may be grounds for negotiation or rejection.
Completeness: will be assessed by verifying that all required items, services, labor, materials and associated costs necessary to meet the contract requirements are included in the quote.
Reasonableness: The Government reserves the right to determine reasonableness by comparing the proposed prices to relevant market data, historical pricing, an average of the quotes received from this solicitation, independent cost estimates, or other commercially available information to ensure the prices are consistent with those typically charged for similar commercial items and services.
The Government may use non-government advisors to provide guidance and advice on information received in response to this solicitiation.
Attachment C – Statement of Work Version 2.6 Page 13
The Government will incur no costs associated with the preparation of this quote.
16 Process Schedule
16.1 Response Deadline & Delivery Instructions
The due date for responses to this SOW, referred to as the SOW Package which contains both technical and price quotes, must be submitted, on or before 12:00pm Central Time, on September 17, 2026. Responses must be submitted via electronic submission to Dylan Hankins at dehankins2@fbi.gov. All Responses must be marked as follows: "Response for Olmito, Santa Maria, and Flamingo Towers”. ALL QUOTES MUST BE VALID FOR 30 DAYS.
16.2 Questions
If you have questions regarding this requirement, please submit your inquiries via email, no later than 12:00 PM Central Time on September 14, 2026, to dehankins2@fbi.gov. All questions must be submitted in writing on the attached Q&A template.
The table below is provided for convenience but may change:
Anticipated Timeline
Questions Due September 14, 2026 12:00 PM CT
Government Responses September 15, 2026 04:00 PM CT
Quotes Due September 17, 2026 12:00 PM CT
Anticipated Award Date September 23, 2026 04:00 PM CT
All updates and the award announcement will be made available through SAM.gov.