ACM LBP - Logan Utah - Final Report.pdf

PDF 15 MB Posted

Attached to
Logan Main Building Flooring Repair - Rocky Mountain Research Station Logan UT
Solicitation number
1240LT21Q0092
Issued by

View the file

Other files

File Type Posted
1240LT21Q0092.pdf PDF
DOL Wage Determination.pdf PDF
Final Specifications.pdf PDF
Logan Main Flooring SOW.docx DOCX document
Combined Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Asbestos and LBP Inspection- Logan Forestry Science Laboratory

Prepared for:

United States Department of Agriculture

United States Forest Service

RMRS

Prepared by:

HGS Engineering, Inc.

1121 Noble Street Anniston, Alabama 36201

May 2019

Table of Contents

1. Executive Summary

2. Asbestos Protocol

3. Lead Protocol

4. Asbestos Drawings

5. Asbestos Database

6. Homogenous Area Picture Log

7. Asbestos Sample Picture Log

8. XRF Testing Results

9. Lead Base Paint Picture Log

10. Analytical Reports

11. Certifications

12. Limitations

Executive Summary

HGS Engineering, Inc. was contracted to conduct an asbestos and lead based paint inspection of the Logan Forestry Science Laboratory located in Logan, Utah by the Region 3 United State Forest Service.

Efren Perez, Utah Asbestos Inspector, Management Planer met with Sheryl Ware and Dan Chapel, at the Logan Forestry Science Laboratory on 8 May 2019.

During the inspection, HGS Engineering collected twenty-eight asbestos samples and three hundred and fifty-five lead-based paint samples with the XRF at the Logan Forestry Science Laboratory. The following report describes the results of both inspections.

ASBESTOS INSPECTION – Final Report

HGS Engineering, Inc. conducted asbestos inspections of the three buildings described in the RFQ: the Main Building, the Headhouse, and the Quonset Hut. The inspections were conducted by Efren Perez, a Utah Certified Asbestos Inspector. The inspector used NESHAP protocol for this inspection.

HGS Engineering, Inc. took twenty-five samples in the Main Building and three samples in tthe Headhouse. All of the samples were sent to Laboratory Resources and Solutions in Ashville, Alabama. In the Main Building twenty-four samples were taken of floor tile within the building eighteen of them tested positive for asbestos, and one sample was taken of pipe insulation. In the Headhouse three samples were taken of floor tile, all three tested positive for asbestos. No asbestos containing building materials were suspected in the Quonset Hut.

Exact location and description of materials are listed in the asbestos database.

Samples were taken using appropriate hand tools and were bagged and labeled. These samples were then sent to Laboratory Resources and Solutions in Ashville, Alabama.

LEAD INSPECTION – Final Report

HGS Engineering, Inc. conducted a lead paint inspection of the painted areas noted in this report.

The inspections were conducted by Efren Perez, an EPA Trained Lead Inspector. The inspections included areas that were painted or assumed to have been painted.

The protocol used for testing was compiled using both EPA and OSHA references and guidance.

Testing was completed using a Lead Paint Analyzer.

HGS Engineering, Inc. conducted the lead testing in all areas required and/or recommended by both EPA and OSHA. In the Main Building HGS Engineering, Inc. took 166 samples on the ground floor; 107 samples of walls were taken with 4 samples testing positive for lead, 16 samples of window sills, 4 samples of the elevator doors, 22 samples of doors, 9 samples of railing, 4 samples of stair steps, and 4 samples of support beams. Exact locations are listed in the XRF Testing Results.

In the basement of the Main Building, HGS Engineering Inc. took a total of 81 samples, 54 samples were taken of the walls, 19 samples of doors, 4 samples of door jambs, and 4 samples of window sills. Exact locations are listed in the XRF Testing Results.

Outside the Main Building 55 samples were taken. 12 samples of walls with 9 testing positive for lead, 5 samples of window sills, 13 samples of beams with 11 testing positive for lead, 5 samples of bike racks, 3 samples of bollards, 3 samples of yellow parking lines, 12 samples of railing, and 2 samples of a tube. Exact locations are listed in the XRF Testing Results.

In the Headhouse HGS Engineering Inc. took 30 samples on the ground floor. 12 samples of walls, 3 samples of doors, and 15 samples of cabinet doors. Exact locations are listed in the XRF Testing Results.

Outside the Headhouse 23 samples were taken. 2 samples of bollards, 4 samples of corner guard with all 4 samples testing positive for lead, 4 samples of garage doors, 2 samples of garage door jambs, 3 samples of a panel, 8 samples of soffits with 3 testing positive for lead. Exact locations are listed in the XRF Testing Results.

In the Quonset Hut no samples were taken due to it being made out of metal and wood with an aluminum roof.

Each accessible painted surface with a distinct painting history was tested using a Thermo Scientific portable XRF analyzer, model number XL2980, serial number 81943. The paint testing was accomplished in accordance with the manufacture’s recommendations and the parameters listed in the EPA Performance Characteristics Sheet for the Thermo Scientific XRF analyzer. Samples were collected using protocols described by HUD, EPA and the American Society for Testing and Materials.

Mr. Tim Thompson of HGS Engineering Inc., Senior Certified Asbestos Inspector and Abatement Supervisor, was the project manager and confirmed all aspects of this report. Should you have any questions or comments, please call. HGS Engineering Inc. appreciates your continued confidence in our professional environmental engineering services. Sincerely, Tim Thompson Asbestos and Lead Inspector Project Manager

Protocol for asbestos sampling The Asbestos Survey was performed by an AHERA Building Inspector as defined under 40 CFR

Field Procedures

· A review of any existing information about the structure, including design drawings, as-built drawings, project specifications, and any existing survey and/or laboratory information was conducted.

· Utilize the proper equipment in order to examine all accessible spaces (i.e. ladders, flashlights, etc.)

· Determine the extent to which the building was renovated and/or changed and when.

· Determine and investigate each building’s structural, mechanical, electrical and roofing systems.

· Perform a comprehensive investigation of areas to identify materials to be sampled and/or assumed to contain asbestos.

· Create sampling plan based on suspect materials present and requirements of 40 CFR 763.85 & 763.86.

· Collect bulk samples of all suspect materials that will be disturbed and submit those not assumed to be asbestos to a certified laboratory for analysis.

· Document where asbestos materials exist and record their exact location, condition and approximate quantity.

The following guidelines were intended to help in locating concealed materials:

· Identify the different building systems which may involve concealed asbestos materials such as roofing underlay roofing.

Survey Methodology:

· Description of inspection procedure, including scope of the survey. Inspection must be in accordance with the sampling protocol in 40 CFR 763.85 and 763.86.

· If hidden or inaccessible areas are to be disturbed or are likely to be disturbed, a destructive investigation must be performed. Provide a detailed description of the procedure used to find hidden suspect materials.

· Description of sampling methods.

Asbestos Identification Process:

· Prepare sample and suspect asbestos material location plan.

· List all materials sampled and tested.

· List all materials assumed to contain asbestos.

· Indicate type and amount of material sampled, be specific.

· Describe suspect material location, friability, and approximate location.

· List all materials not sampled and state why they were not sampled.

- Identify the number of samples collected and sent to Laboratory of analysis. Identify all samples that came back positive by Polarized Light Microscopy. All samples that come back less than 1% need to be point counted.

References followed and used during this inspection included:

-U.S. Department of Labor, Occupational Safety and Health Administration (OSHA) -Title 29 of the Code of Federal Regulations, Part 1926.1101, Asbestos Construction Standard

(29 CFR 1926.1101)

- Asbestos General Industry Standard (29 CFR 1910.1001)

- Personal Protective Equipment (29 CFR 1926, Subpart E)

- Hazard Communication (29 CFR 1910.1200)

- Specifications for Accident Prevention, Signs, and Tags (29 CFR 1910.145)

- U.S. Environmental Protection Agency (EPA) National Emissions Standard for Hazardous Air Pollutants (NESHAP) Asbestos Regulation (40 CFR 61, Subparts A, B, and M) -American National Standards Institute (ANSI)

- Practices for Respiratory Protection (ANSI Standard Z88.2-1980)

- Fundamentals Governing the Design and Operation of Local Exhaust Systems (ANSI Z9.2-79) -National Fire Protection Association (NFPA)

1. The following will be used in establishing the sampling protocol to be used for sampling.

Homogeneous Area

-Any SM, TSI, or Misc material that I uniform in color and texture.

-Date of construction

Sampling -Surfacing Material Sampling in a “statistically random manner” Follow 3-5-7 rule 3 <1000 sq. feet 5 1000-5000 sq. feet 7 >5000 sq. ft -Thermal System Insulation Sampling in a “randomly distributed manner” 3 samples per homogenous material 1 sample per fitting 1 sample per patched area, six feet -Miscellaneous Material

“In a manner sufficient to determine ACM content per homogenous material” Sample at least 2 samples per homogenous material.

2. Assess using the following criteria.

Current Condition -Significantly Damaged, Damaged, Good Distributed

SD >10%

D 1-10% G 0-<1% Localized

SD >25%

D 1-25% G 0-<1% Potential for Damage -Disturbance considerations:

Contact, air erosion, and vibration High, Moderate, Low All assessment will be based on functional space

3. Physical Assessment Categories -Damaged/significantly damaged TSI -Damaged friable surfacing ACM -Significantly damaged friable surfacing ACM -Damaged/significantly damaged friable miscellaneous materials (Undamaged follows) -ACBM with potential for damage -ACBM with potential for significant damage -Any remaining friable ACBM

4. Potential for damage considerations -Frequency of potential contact -Influence of vibration -Potential for air erosion -Overall rating

If any one is high potential for damage should be significant damage.

If any one is moderate potential for damage should be damage.

All three must be low to receive a potential damage of low.

5. Hazard ranking in relation to hazardous potential

Hazard Rank AHERA Category Response Action 1 Non friable or friable with No action required.

Low potential for damage

2 Friable with potential for damage Appropriate action to prevent damage when possible. O&M required.

3 Friable with potential for Take steps to reduce potential significantly damage for disturbance. O&M required.

4 Friable damaged Avoid exposure of personnel To damaged material.

Remove, enclose, encapsulate or repair. O&M required.

5 Friable damaged with Avoid exposure of personnel potential for damage to damaged material. Remove, enclose, encapsulate or correct damage. Take appropriate action to prevent damage when possible.

O&M required.

6 Friable damaged with Avoid exposure of personnel potential for significant damage. to damaged material.

Remove, enclose, encapsulate or correct damage. Take appropriate action to prevent damage when possible.

7 Friable significantly damaged Evacuate or isolate the area if needed. Remove the ACM (enclose or encapsulation is sufficient to contain fibers).

Repair the thermal system insulation is an option if feasible and safe.

6. Classification for Hazard Potential

ACBM Condition Potential Disturbance Hazard Rank

Significantly Damaged Any 7 Damaged High 6 Damaged Moderate 5 Damaged Low 4 Good High 3 Good Moderate 2 Good Low 1

Protocol for Lead Sampling

Sampling locations were chosen with respect to homogenous materials. Areas containing a percentage of lead equal to or above to 1 milligram per centimeter squared will be considered paint containing lead paint. Each accessible painted surface with a distinct painting history was tested using a Thermo Scientific portable XRF analyzer, model number XL2980, serial number 81943. The paint testing was accomplished in accordance with the manufacture’s recommendations and the parameters listed in the EPA Performance Characteristics Sheet for the Thermo Scientific XRF analyzer. Samples were collected using protocols described by HUD, EPA and the American Society for Testing and Materials.

Asbestos Drawings

L-B-5-T-1 L-B-5-T-2 L-B-5-T-3

L-B-8-T-1 L-B-8-T-2 L-B-8-T-3

L-B-10-TSI-1

Legend

Concrete

Red Carpet

Yellow Carpet

Beige 12x12 Tile

White 1x1 Tile

Red= Positive Black= Negative

SAMPLE LEGEND

L-1-126-T-1 L-1-126-T-2 L-1-126-T-3

L-1-131-T-1 L-1-131-T-2 L-1-131-T-3

L-1-122-T-1 L-1-122-T-2 L-1-122-T-3

L-1-103-T-1 L-1-103-T-2 L-1-103-T-3

L-1-117-T-3

L-1-118-T-2

L-1-120-T-1

Legend Beige 9x9 Tile under Red Carpet

White 1x1 Floor Tile

Beige 9x9 Floor Tile

L-1-105-T-1 L-1-105-T-2 L-1-105-T-3

Red= Positive Black= Negative

SAMPLE LEGEND

L-HH-1-T-1

L-HH-1-T-2

L-HH-1-T-3

Asbestos Database

Picture Number Material Description Air Contact Vibration Number Picture ACM Status Type & % of Asbestos Friable

Logan, UT Main Office 1

Room 100, 101, 102, 103, 104, 110, 111, 112, 113, 114, 115, 116, 124, 125, 126, 127, 128, 129, 130, 131, 132,133, and 134

Office Floor Tile 1 Beige 9x9 Tile under Red Carpet Floor M 2000 sf Good Low High Moderate High 1 O&M Plan L-1-126-T-1, L-1-126-T-2, L-1-126-T-3, L-1-131-T-1, L-1-131-T-2, L-1-131-T-3, L-1-103-T-1, L-1-103-T-2, L-1-103-T-3

1, 2, 3, 4, 5, 6, 10, 11, 12

Positive Tile - 3% Chrysotile Mastic - 3-7% Chrysotile

No

Logan, UT Main Office 1 Room 117, 118, 120, 121, 122, and 123

Lab and Storage Room Floor Tile 2 Beige 9x9 Tile Floor M 600 sf Good High High High High 1 O&M Plan L-1-122-T-1, L-1-122-T-2, L-1-122-T-3, L-1-117-T-3, L-1-118-T-2, L-1-120-T-1

7, 8, 9, 16, 17, 18 Positive Tile - 2-4% Chrysotile Mastic- 3-7% Chrysotile

No

Logan, UT Main Office 1 Room 105, 106, 107, 108, and 109

Women's and Men's Restroom and Janitor

Closet Floor Tile 3 White 1x1 Tile Floor M 100 sf Good 1 O&M Plan L-1-105-T-1, L-1-105-T-2, L-1-105-T-3 13, 14, 15 Negative No

Logan, UT Main Office B Room 4, 5, 10, 11, 12, and 13 Storage, Mechanical Room, Break Room, Floor Tile 4 Concrete Floor M 600 sf Good 1 O&M Plan

Logan, UT Main Office B Conference Room and Computer Room

Conference Room and Computer Room

Floor Tile 5 Red Carpet Floor M 50 sf Good 1 O&M Plan

Logan, UT Main Office B Corridor 1 Corridor Floor Tile 6 Yellow Carpet Floor M 50 sf Good 1 O&M Plan

Logan, UT Main Office B Room 8 Freezer Floor Tile 7 12x12 White w/ Gray Streaks Tile Floor M 20 sf Good High High High High 1 O&M Plan L-B-8-T-1, L-B-8-T-2, L-B-8-T-3 22, 23, 24 Positive Tile - 2% Chrysotile Mastic - 2& Chrysotile

No

Logan, UT Main Office B Room 5 Restroom Floor Tile 8 White 1x1 Tile Floor M 10 sf Good 1 O&M Plan L-B-5-T-1, L-B-5-T-1, L-B-5-T-2 19, 20, 21 Negative No

Logan, UT Main Office B Room 10 Herbarium TSI 9 White Pipe Elbow Insulation Pipe TSI 15 LF Good 1 O&M Plan L-B-10-TSI-1 25 Negative No

Logan, UT Headhouse 1 Room 1 Office Floor Tile 10 12x12 White w/Gray Streaks Tile Floor M 30 Sf Good High High High High 1 O&M Plan L-HH-1-T-1, L-HH-1-T-2, L-HH-1-T-3 26, 27, 28 Positive 2% Chrysotile No

Logan, UT Headhouse 1 Room 2 and Workshop Office and workshop Floor Tile 11 Concrete Floor M 1000 Sf Good

ProjectName Building Number Floor Number Room Number SurfaceNameRoom Description SampleMaterial condition Potential for Damage from Potential for damage EPA Hazard Ranking Response actionAHERA Category Quantity Unit of measureHomogenous Material Location

Homogeneous Area

Picture Log

Example of Homogeneous Area #1

Example of Homogeneous Area #2

Example of Homogeneous Area #3

Example of Homogeneous Area #4

Example of Homogeneous Area #5

Example of Homogeneous Area #6

Example of Homogeneous Area #7

Example of Homogeneous Area #8

Example of Homogeneous Area #10

Example of Homogeneous Area #9

Example of Homogeneous Area #11

Asbestos Sample

XRF Testing Results

Reading No Date Time Site Building Floor Room Component Substrate Side Condition Color Picture Number Duration Results Pb Pb Error Type

1 9-May-19 9:06 AM Logan, UT System Check 56.09 System Check 2 9-May-19 9:08 AM Logan, UT System Check 57.58 System Check

9-May-19 9:08 AM Logan, UT Calibration 0.15 Negative <LOD 0.01 Action Lead Paint 9-May-19 9:08 AM Logan, UT Calibration 0.15 Negative 0.08 0.02 Action Lead Paint 9-May-19 9:08 AM Logan, UT Calibration 0.15 Negative <LOD 0.7 Action Lead Paint

6 9-May-19 9:11 AM Logan, UT Main Building 1st Floor Lobby Wall Wood A Good White 1 0.15 Negative <LOD 0.06 Action Lead Paint 7 9-May-19 9:11 AM Logan, UT Main Building 1st Floor Lobby Wall Wood A Good White 1 0.5 Negative <LOD 0.15 Action Lead Paint 8 9-May-19 9:11 AM Logan, UT Main Building 1st Floor Lobby Wall Wood A Good White 1 0.49 Negative <LOD 0.04 Action Lead Paint 9 9-May-19 9:12 AM Logan, UT Main Building 1st Floor Lobby Wall Drywall B Good White 2 0.15 Negative 0.02 0.01 Action Lead Paint

10 9-May-19 9:12 AM Logan, UT Main Building 1st Floor Lobby Wall Drywall B Good White 2 0.49 Negative <LOD 0.15 Action Lead Paint 11 9-May-19 9:12 AM Logan, UT Main Building 1st Floor Lobby Wall Drywall B Good White 2 0.14 Negative 0.25 0.06 Action Lead Paint 12 9-May-19 9:13 AM Logan, UT Main Building 1st Floor Lobby Wall Brick C Good White 3 0.16 Negative 0.35 0.1 Action Lead Paint 13 9-May-19 9:13 AM Logan, UT Main Building 1st Floor Lobby Wall Brick C Good White 3 0.15 Negative 0.12 0.03 Action Lead Paint 14 9-May-19 9:13 AM Logan, UT Main Building 1st Floor Lobby Wall Brick C Good White 3 0.14 Negative <LOD 0.06 Action Lead Paint 15 9-May-19 9:14 AM Logan, UT Main Building 1st Floor Lobby Wall Drywall D Good White 4 0.15 Negative 0.46 0.11 Action Lead Paint 16 9-May-19 9:14 AM Logan, UT Main Building 1st Floor Lobby Wall Drywall D Good White 4 0.15 Negative 0.19 0.05 Action Lead Paint 17 9-May-19 9:14 AM Logan, UT Main Building 1st Floor Lobby Wall Drywall D Good White 4 0.49 Negative 0.47 0.16 Action Lead Paint 18 9-May-19 9:15 AM Logan, UT Main Building 1st Floor Lobby Window Sill Wood A Good White 5 0.15 Negative 0.35 0.13 Action Lead Paint 19 9-May-19 9:15 AM Logan, UT Main Building 1st Floor Lobby Window Sill Wood A Good White 5 0.49 Negative 0.33 0.15 Action Lead Paint 20 9-May-19 9:15 AM Logan, UT Main Building 1st Floor Lobby Window Sill Wood A Good White 5 0.84 Negative 0.27 0.11 Action Lead Paint 21 9-May-19 9:17 AM Logan, UT Main Building 1st Floor Corridor 134 Wall Drywall D Good White 6 0.14 Negative 0.08 0.02 Action Lead Paint 22 9-May-19 9:17 AM Logan, UT Main Building 1st Floor Corridor 134 Wall Drywall D Good White 6 0.15 Positive 5.44 1.68 Action Lead Paint 23 9-May-19 9:17 AM Logan, UT Main Building 1st Floor Corridor 134 Wall Drywall D Good White 6 0.14 Positive 6.34 1.97 Action Lead Paint 24 9-May-19 9:17 AM Logan, UT Main Building 1st Floor Corridor 134 Wall Drywall D Good White 6 0.15 Positive 7.11 0.11 Action Lead Paint 25 9-May-19 9:18 AM Logan, UT Main Building 1st Floor Corridor 134 Wall Brick B Good White 7 1.3 Positive 10.72 0.73 Action Lead Paint 26 9-May-19 9:18 AM Logan, UT Main Building 1st Floor Corridor 134 Wall Brick B Good White 7 0.14 Negative <LOD 0.01 Action Lead Paint 27 9-May-19 9:19 AM Logan, UT Main Building 1st Floor Corridor 134 Wall Brick B Good White 7 0.15 Negative <LOD 0.01 Action Lead Paint 28 9-May-19 9:20 AM Logan, UT Main Building 1st Floor Corridor 134 Wall Brick B Good White 7 0.15 Negative <LOD 0.01 Action Lead Paint 29 9-May-19 9:21 AM Logan, UT Main Building 1st Floor Rm 130 Wall Wood A Good Brown 8 0.15 Negative <LOD 0.07 Action Lead Paint 30 9-May-19 9:21 AM Logan, UT Main Building 1st Floor Rm 130 Wall Wood A Good Brown 8 0.15 Negative <LOD 0.01 Action Lead Paint 31 9-May-19 9:21 AM Logan, UT Main Building 1st Floor Rm 130 Wall Wood A Good Brown 8 0.15 Negative <LOD 0.06 Action Lead Paint 32 9-May-19 9:22 AM Logan, UT Main Building 1st Floor Rm 130 Wall Drywall B Good White 9 0.15 Negative <LOD 0.13 Action Lead Paint 33 9-May-19 9:22 AM Logan, UT Main Building 1st Floor Rm 130 Wall Drywall B Good White 9 0.15 Negative <LOD 0.04 Action Lead Paint 34 9-May-19 9:22 AM Logan, UT Main Building 1st Floor Rm 130 Wall Drywall B Good White 9 0.15 Negative <LOD 0.05 Action Lead Paint 35 9-May-19 9:23 AM Logan, UT Main Building 1st Floor Rm 130 Wall Wood C Good Brown 10 0.14 Negative <LOD 0.08 Action Lead Paint 36 9-May-19 9:23 AM Logan, UT Main Building 1st Floor Rm 130 Wall Wood C Good Brown 10 0.15 Negative <LOD 0.01 Action Lead Paint 37 9-May-19 9:23 AM Logan, UT Main Building 1st Floor Rm 130 Wall Wood C Good Brown 10 0.15 Negative <LOD 0.08 Action Lead Paint 38 9-May-19 9:24 AM Logan, UT Main Building 1st Floor Rm 130 Wall Wood D Good Brown 11 0.15 Negative <LOD 0.01 Action Lead Paint 39 9-May-19 9:24 AM Logan, UT Main Building 1st Floor Rm 130 Wall Wood D Good Brown 11 0.15 Negative <LOD 0.09 Action Lead Paint 40 9-May-19 9:24 AM Logan, UT Main Building 1st Floor Rm 130 Wall Wood D Good Brown 11 0.15 Negative <LOD 0.01 Action Lead Paint 41 9-May-19 9:24 AM Logan, UT Main Building 1st Floor Rm 130 Window Sill Wood D Good White 12 0.15 Negative <LOD 0.04 Action Lead Paint 42 9-May-19 9:24 AM Logan, UT Main Building 1st Floor Rm 130 Window Sill Wood D Good White 12 0.15 Negative <LOD 0.14 Action Lead Paint 43 9-May-19 9:24 AM Logan, UT Main Building 1st Floor Rm 130 Window Sill Wood D Good White 12 0.15 Negative <LOD 0.11 Action Lead Paint 44 9-May-19 9:25 AM Logan, UT Main Building 1st Floor Rm 130 Window Sill Wood D Good White 12 0.14 Negative <LOD 0.15 Action Lead Paint 45 9-May-19 9:25 AM Logan, UT Main Building 1st Floor Rm 130 Door Wood Good White 13 0.14 Negative <LOD 0.17 Action Lead Paint 46 9-May-19 9:25 AM Logan, UT Main Building 1st Floor Rm 130 Door Wood Good White 13 0.15 Negative <LOD 0.14 Action Lead Paint 47 9-May-19 9:25 AM Logan, UT Main Building 1st Floor Rm 130 Door Wood Good White 13 0.15 Negative <LOD 0.13 Action Lead Paint 48 9-May-19 9:26 AM Logan, UT Main Building 1st Floor Corridor 134 Wall Drywall D Good White 14 0.15 Negative <LOD 0.01 Action Lead Paint 49 9-May-19 9:26 AM Logan, UT Main Building 1st Floor Corridor 134 Wall Drywall D Good White 14 0.15 Negative <LOD 0.07 Action Lead Paint 50 9-May-19 9:27 AM Logan, UT Main Building 1st Floor Corridor 134 Wall Drywall D Good White 14 0.14 Negative <LOD 0.07 Action Lead Paint 51 9-May-19 9:27 AM Logan, UT Main Building 1st Floor Corridor 134 Door Metal Good White 15 0.15 Negative <LOD 0.07 Action Lead Paint 52 9-May-19 9:28 AM Logan, UT Main Building 1st Floor Corridor 134 Door Metal Good White 15 0.15 Negative <LOD 0.06 Action Lead Paint 53 9-May-19 9:28 AM Logan, UT Main Building 1st Floor Corridor 134 Door Metal Good White 15 0.15 Negative <LOD 0.08 Action Lead Paint 54 9-May-19 9:28 AM Logan, UT Main Building 1st Floor Corridor 134 Door Metal Good White 15 0.15 Negative <LOD 0.08 Action Lead Paint 55 9-May-19 9:30 AM Logan, UT Main Building 1st Floor Rm 124 Wall Drywall A Good White 16 0.15 Negative <LOD 0.07 Action Lead Paint 56 9-May-19 9:30 AM Logan, UT Main Building 1st Floor Rm 124 Wall Drywall A Good White 16 0.23 Negative <LOD 0.01 Action Lead Paint 57 9-May-19 9:30 AM Logan, UT Main Building 1st Floor Rm 124 Wall Drywall A Good White 16 0.15 Negative <LOD 0.07 Action Lead Paint 58 9-May-19 9:30 AM Logan, UT Main Building 1st Floor Rm 124 Wall Drywall B Good White 17 0.14 Negative <LOD 0.01 Action Lead Paint 59 9-May-19 9:30 AM Logan, UT Main Building 1st Floor Rm 124 Wall Drywall B Good White 17 0.15 Negative <LOD 0.01 Action Lead Paint 60 9-May-19 9:31 AM Logan, UT Main Building 1st Floor Rm 124 Wall Drywall B Good White 17 0.15 Negative <LOD 0.01 Action Lead Paint 61 9-May-19 9:31 AM Logan, UT Main Building 1st Floor Rm 124 Wall Drywall C Good White 18 0.15 Negative <LOD 0.01 Action Lead Paint 62 9-May-19 9:31 AM Logan, UT Main Building 1st Floor Rm 124 Wall Drywall C Good White 18 0.15 Negative <LOD 0.04 Action Lead Paint 63 9-May-19 9:31 AM Logan, UT Main Building 1st Floor Rm 124 Wall Drywall C Good White 18 0.14 Negative <LOD 0.01 Action Lead Paint 64 9-May-19 9:31 AM Logan, UT Main Building 1st Floor Rm 124 Wall Drywall D Good White 19 0.15 Negative <LOD 0.01 Action Lead Paint 65 9-May-19 9:31 AM Logan, UT Main Building 1st Floor Rm 124 Wall Drywall D Good White 19 0.16 Negative <LOD 0.01 Action Lead Paint 66 9-May-19 9:31 AM Logan, UT Main Building 1st Floor Rm 124 Wall Drywall D Good White 19 0.15 Negative <LOD 0.01 Action Lead Paint 67 9-May-19 9:33 AM Logan, UT Main Building 1st Floor Rm 124 Door Metal Good White 20 0.15 Negative <LOD 0.04 Action Lead Paint

Reading No Date Time Site Building Floor Room Component Substrate Side Condition Color Picture Number Duration Results Pb Pb Error Type

68 9-May-19 9:33 AM Logan, UT Main Building 1st Floor Rm 124 Door Metal Good White 20 0.15 Negative <LOD 0.13 Action Lead Paint 69 9-May-19 9:33 AM Logan, UT Main Building 1st Floor Rm 124 Door Metal Good White 20 0.15 Negative <LOD 0.07 Action Lead Paint 70 9-May-19 9:37 AM Logan, UT Main Building 1st Floor Rm 104 Wall Drywall A Good White 21 0.15 Negative <LOD 0.13 Action Lead Paint 71 9-May-19 9:37 AM Logan, UT Main Building 1st Floor Rm 104 Wall Drywall A Good White 21 0.45 Negative <LOD 0.04 Action Lead Paint 72 9-May-19 9:37 AM Logan, UT Main Building 1st Floor Rm 104 Wall Drywall A Good White 21 0.15 Negative <LOD 0.11 Action Lead Paint 73 9-May-19 9:37 AM Logan, UT Main Building 1st Floor Rm 104 Wall Drywall B Good White 22 0.16 Negative <LOD 0.11 Action Lead Paint 74 9-May-19 9:37 AM Logan, UT Main Building 1st Floor Rm 104 Wall Drywall B Good White 22 0.15 Negative <LOD 0.13 Action Lead Paint 75 9-May-19 9:37 AM Logan, UT Main Building 1st Floor Rm 104 Wall Drywall B Good White 22 0.15 Negative <LOD 0.07 Action Lead Paint 76 9-May-19 9:37 AM Logan, UT Main Building 1st Floor Rm 104 Wall Drywall C Good White 23 0.15 Negative <LOD 0.1 Action Lead Paint 77 9-May-19 9:38 AM Logan, UT Main Building 1st Floor Rm 104 Wall Drywall C Good White 23 0.14 Negative <LOD 0.1 Action Lead Paint 78 9-May-19 9:38 AM Logan, UT Main Building 1st Floor Rm 104 Wall Drywall C Good White 23 0.24 Negative <LOD 0.07 Action Lead Paint 79 9-May-19 9:38 AM Logan, UT Main Building 1st Floor Rm 104 Wall Drywall D Good White 24 0.15 Negative <LOD 0.13 Action Lead Paint 80 9-May-19 9:38 AM Logan, UT Main Building 1st Floor Rm 104 Wall Drywall D Good White 24 0.14 Negative <LOD 0.12 Action Lead Paint 81 9-May-19 9:38 AM Logan, UT Main Building 1st Floor Rm 104 Wall Drywall D Good White 24 0.15 Negative <LOD 0.07 Action Lead Paint 82 9-May-19 9:40 AM Logan, UT Main Building 1st Floor Rm 104 Window Sill Wood Good White 25 0.15 Negative <LOD 0.15 Action Lead Paint 83 9-May-19 9:40 AM Logan, UT Main Building 1st Floor Rm 104 Window Sill Wood Good White 25 0.15 Negative <LOD 0.07 Action Lead Paint 84 9-May-19 9:40 AM Logan, UT Main Building 1st Floor Rm 104 Window Sill Wood Good White 25 0.16 Negative <LOD 0.07 Action Lead Paint 85 9-May-19 9:40 AM Logan, UT Main Building 1st Floor Rm 104 Door Wood Good White 26 0.24 Negative <LOD 0.08 Action Lead Paint 86 9-May-19 9:40 AM Logan, UT Main Building 1st Floor Rm 104 Door Wood Good White 26 0.14 Negative <LOD 0.14 Action Lead Paint 87 9-May-19 9:40 AM Logan, UT Main Building 1st Floor Rm 104 Door Wood Good White 26 0.22 Negative <LOD 0.07 Action Lead Paint 88 9-May-19 9:41 AM Logan, UT Main Building 1st Floor Corridor 114 Wall Brick D Good White 27 0.15 Negative <LOD 0.01 Action Lead Paint 89 9-May-19 9:42 AM Logan, UT Main Building 1st Floor Corridor 114 Wall Brick D Good White 27 0.15 Negative <LOD 0.01 Action Lead Paint 90 9-May-19 9:42 AM Logan, UT Main Building 1st Floor Corridor 114 Wall Brick D Good White 27 0.15 Negative <LOD 0.01 Action Lead Paint 91 9-May-19 9:42 AM Logan, UT Main Building 1st Floor Corridor 114 Wall Brick D Good White 27 0.15 Negative <LOD 0.01 Action Lead Paint 92 9-May-19 9:43 AM Logan, UT Main Building 1st Floor Corridor 114 Wall Drywall B Good White 28 0.15 Negative <LOD 0.08 Action Lead Paint 93 9-May-19 9:43 AM Logan, UT Main Building 1st Floor Corridor 114 Wall Drywall B Good White 28 0.15 Negative <LOD 0.07 Action Lead Paint 94 9-May-19 9:43 AM Logan, UT Main Building 1st Floor Corridor 114 Wall Drywall B Good White 28 0.14 Negative <LOD 0.07 Action Lead Paint 95 9-May-19 9:43 AM Logan, UT Main Building 1st Floor Corridor 114 Wall Drywall B Good White 28 0.15 Negative <LOD 0.01 Action Lead Paint 96 9-May-19 9:46 AM Logan, UT Main Building 1st Floor Rm 108 Wall Drywall A Good White 29 0.15 Negative <LOD 0.14 Action Lead Paint 97 9-May-19 9:46 AM Logan, UT Main Building 1st Floor Rm 108 Wall Drywall A Good White 29 0.34 Negative <LOD 0.05 Action Lead Paint 98 9-May-19 9:46 AM Logan, UT Main Building 1st Floor Rm 108 Wall Drywall A Good White 29 0.15 Negative <LOD 0.12 Action Lead Paint 99 9-May-19 9:46 AM Logan, UT Main Building 1st Floor Rm 108 Wall Drywall B Good White 30 0.14 Negative <LOD 0.07 Action Lead Paint

100 9-May-19 9:46 AM Logan, UT Main Building 1st Floor Rm 108 Wall Drywall B Good White 30 0.15 Negative <LOD 0.07 Action Lead Paint 101 9-May-19 9:46 AM Logan, UT Main Building 1st Floor Rm 108 Wall Drywall B Good White 30 0.15 Negative <LOD 0.06 Action Lead Paint 102 9-May-19 9:46 AM Logan, UT Main Building 1st Floor Rm 108 Wall Drywall C Good White 31 0.15 Negative <LOD 0.08 Action Lead Paint 103 9-May-19 9:46 AM Logan, UT Main Building 1st Floor Rm 108 Wall Drywall C Good White 31 0.15 Negative <LOD 0.16 Action Lead Paint 104 9-May-19 9:46 AM Logan, UT Main Building 1st Floor Rm 108 Wall Drywall C Good White 31 0.14 Negative <LOD 0.13 Action Lead Paint 105 9-May-19 9:46 AM Logan, UT Main Building 1st Floor Rm 108 Wall Drywall D Good White 32 0.15 Negative <LOD 0.14 Action Lead Paint 106 9-May-19 9:46 AM Logan, UT Main Building 1st Floor Rm 108 Wall Drywall D Good White 32 0.15 Negative <LOD 0.1 Action Lead Paint 107 9-May-19 9:46 AM Logan, UT Main Building 1st Floor Rm 108 Wall Drywall D Good White 32 0.14 Negative <LOD 0.08 Action Lead Paint 108 9-May-19 9:47 AM Logan, UT Main Building 1st Floor Rm 108 Door Wood Good White 33 0.15 Negative <LOD 0.11 Action Lead Paint 109 9-May-19 9:47 AM Logan, UT Main Building 1st Floor Rm 108 Door Wood Good White 33 0.15 Negative <LOD 0.1 Action Lead Paint 110 9-May-19 9:47 AM Logan, UT Main Building 1st Floor Rm 108 Door Wood Good White 33 0.14 Negative <LOD 0.09 Action Lead Paint 111 9-May-19 9:47 AM Logan, UT Main Building 1st Floor Rm 108 Window Sill Wood Good White 34 0.15 Negative <LOD 0.14 Action Lead Paint 112 9-May-19 9:47 AM Logan, UT Main Building 1st Floor Rm 108 Window Sill Wood Good White 34 0.15 Negative <LOD 0.15 Action Lead Paint 113 9-May-19 9:47 AM Logan, UT Main Building 1st Floor Rm 108 Window Sill Wood Good White 34 0.15 Negative <LOD 0.02 Action Lead Paint 114 9-May-19 9:52 AM Logan, UT Main Building 1st Floor Rm 110 Wall Wood A Good Brown 35 0.15 Negative <LOD 0.01 Action Lead Paint 115 9-May-19 9:52 AM Logan, UT Main Building 1st Floor Rm 110 Wall Wood A Good Brown 35 0.15 Negative <LOD 0.02 Action Lead Paint 116 9-May-19 9:52 AM Logan, UT Main Building 1st Floor Rm 110 Wall Wood A Good Brown 35 0.15 Negative <LOD 0.01 Action Lead Paint 117 9-May-19 9:52 AM Logan, UT Main Building 1st Floor Rm 110 Wall Wood B Good Brown 36 0.15 Negative <LOD 0.07 Action Lead Paint 118 9-May-19 9:52 AM Logan, UT Main Building 1st Floor Rm 110 Wall Wood B Good Brown 36 0.15 Negative <LOD 0.01 Action Lead Paint 119 9-May-19 9:52 AM Logan, UT Main Building 1st Floor Rm 110 Wall Wood B Good Brown 36 0.15 Negative <LOD 0.1 Action Lead Paint 120 9-May-19 9:52 AM Logan, UT Main Building 1st Floor Rm 110 Wall Wood C Good Brown 37 0.16 Negative <LOD 0.01 Action Lead Paint 121 9-May-19 9:52 AM Logan, UT Main Building 1st Floor Rm 110 Wall Wood C Good Brown 37 0.15 Negative <LOD 0.08 Action Lead Paint 122 9-May-19 9:53 AM Logan, UT Main Building 1st Floor Rm 110 Wall Wood C Good Brown 37 0.15 Negative <LOD 0.07 Action Lead Paint 123 9-May-19 9:53 AM Logan, UT Main Building 1st Floor Rm 110 Wall Drywall D Good White 38 0.15 Negative <LOD 0.07 Action Lead Paint 124 9-May-19 9:53 AM Logan, UT Main Building 1st Floor Rm 110 Wall Drywall D Good White 38 0.16 Negative <LOD 0.03 Action Lead Paint 125 9-May-19 9:53 AM Logan, UT Main Building 1st Floor Rm 110 Wall Drywall D Good White 38 0.15 Negative <LOD 0.1 Action Lead Paint 126 9-May-19 9:56 AM Logan, UT Main Building 1st Floor Rm 110 Window Sill Wood Good White 39 0.15 Negative <LOD 0.08 Action Lead Paint 127 9-May-19 9:56 AM Logan, UT Main Building 1st Floor Rm 110 Window Sill Wood Good White 39 0.15 Negative <LOD 0.07 Action Lead Paint 128 9-May-19 9:56 AM Logan, UT Main Building 1st Floor Rm 110 Window Sill Wood Good White 39 0.15 Negative <LOD 0.07 Action Lead Paint 129 9-May-19 9:56 AM Logan, UT Main Building 1st Floor Rm 110 Door Wood Good White 40 0.14 Negative <LOD 0.14 Action Lead Paint 130 9-May-19 9:56 AM Logan, UT Main Building 1st Floor Rm 110 Door Wood Good White 40 0.15 Negative <LOD 0.01 Action Lead Paint 131 9-May-19 9:56 AM Logan, UT Main Building 1st Floor Rm 110 Door Wood Good White 40 0.14 Negative <LOD 0.08 Action Lead Paint 132 9-May-19 9:59 AM Logan, UT Main Building 1st Floor Rm 120 Wall Brick A Good White 41 0.15 Negative <LOD 0.09 Action Lead Paint 133 9-May-19 9:59 AM Logan, UT Main Building 1st Floor Rm 120 Wall Brick A Good White 41 0.15 Negative <LOD 0.08 Action Lead Paint 134 9-May-19 9:59 AM Logan, UT Main Building 1st Floor Rm 120 Wall Brick A Good White 41 0.15 Negative <LOD 0.01 Action Lead Paint

Reading No Date Time Site Building Floor Room Component Substrate Side Condition Color Picture Number Duration Results Pb Pb Error Type

135 9-May-19 9:59 AM Logan, UT Main Building 1st Floor Rm 120 Wall Brick B Good White 42 0.15 Negative <LOD 0.01 Action Lead Paint 136 9-May-19 9:59 AM Logan, UT Main Building 1st Floor Rm 120 Wall Brick B Good White 42 0.14 Negative <LOD 0.05 Action Lead Paint 137 9-May-19 9:59 AM Logan, UT Main Building 1st Floor Rm 120 Wall Brick B Good White 42 0.14 Negative <LOD 0.02 Action Lead Paint 138 9-May-19 9:59 AM Logan, UT Main Building 1st Floor Rm 120 Wall Brick C Good White 43 0.15 Negative <LOD 0.01 Action Lead Paint 139 9-May-19 9:59 AM Logan, UT Main Building 1st Floor Rm 120 Wall Brick C Good White 43 0.14 Negative <LOD 0.07 Action Lead Paint 140 9-May-19 9:59 AM Logan, UT Main Building 1st Floor Rm 120 Wall Brick C Good White 43 0.15 Negative <LOD 0.07 Action Lead Paint 141 9-May-19 10:00 AM Logan, UT Main Building 1st Floor Rm 120 Wall Brick D Good White 44 0.15 Negative <LOD 0.05 Action Lead Paint 142 9-May-19 10:00 AM Logan, UT Main Building 1st Floor Rm 120 Wall Brick D Good White 44 0.15 Negative <LOD 0.12 Action Lead Paint 143 9-May-19 10:00 AM Logan, UT Main Building 1st Floor Rm 120 Wall Brick D Good White 44 0.14 Negative <LOD 0.01 Action Lead Paint 144 9-May-19 10:00 AM Logan, UT Main Building 1st Floor Rm 120 Door Metal Good White 45 0.15 Negative <LOD 0.28 Action Lead Paint 145 9-May-19 10:00 AM Logan, UT Main Building 1st Floor Rm 120 Door Metal Good White 45 0.15 Negative <LOD 0.01 Action Lead Paint 146 9-May-19 10:00 AM Logan, UT Main Building 1st Floor Rm 120 Door Metal Good White 45 0.14 Negative <LOD 0.09 Action Lead Paint 147 9-May-19 10:03 AM Logan, UT Main Building 1st Floor Corridor 114 Elevator Door Metal Good White 46 0.15 Negative <LOD 0.01 Action Lead Paint 148 9-May-19 10:03 AM Logan, UT Main Building 1st Floor Corridor 114 Elevator Door Metal Good White 46 0.15 Negative <LOD 0.07 Action Lead Paint 149 9-May-19 10:03 AM Logan, UT Main Building 1st Floor Corridor 114 Elevator Door Metal Good White 46 0.15 Negative <LOD 0.01 Action Lead Paint 150 9-May-19 10:03 AM Logan, UT Main Building 1st Floor Corridor 114 Elevator Door Metal Good White 46 0.15 Negative <LOD 0.07 Action Lead Paint 151 9-May-19 10:05 AM Logan, UT Main Building 1st Floor North Stairwell Railing Metal Good White 47 0.15 Negative <LOD 0.2 Action Lead Paint 152 9-May-19 10:05 AM Logan, UT Main Building 1st Floor North Stairwell Railing Metal Good White 47 0.25 Negative <LOD 0.18 Action Lead Paint 153 9-May-19 10:05 AM Logan, UT Main Building 1st Floor North Stairwell Railing Metal Good White 47 0.15 Negative <LOD 0.12 Action Lead Paint 154 9-May-19 10:05 AM Logan, UT Main Building 1st Floor North Stairwell Railing Metal Good White 47 0.14 Negative <LOD 0.15 Action Lead Paint 155 9-May-19 10:05 AM Logan, UT Main Building 1st Floor North Stairwell Railing Metal Good White 47 0.15 Negative <LOD 0.15 Action Lead Paint 156 9-May-19 10:06 AM Logan, UT Main Building 1st Floor North Stairwell Stair Steps Concrete Good Blue 48 0.16 Negative <LOD 0.04 Action Lead Paint 157 9-May-19 10:06 AM Logan, UT Main Building 1st Floor North Stairwell Stair Steps Concrete Good Blue 48 0.15 Negative <LOD 0.03 Action Lead Paint 158 9-May-19 10:06 AM Logan, UT Main Building 1st Floor North Stairwell Stair Steps Concrete Good Blue 48 0.25 Negative <LOD 0.04 Action Lead Paint 159 9-May-19 10:06 AM Logan, UT Main Building 1st Floor North Stairwell Stair Steps Concrete Good Blue 48 0.15 Negative <LOD 0.04 Action Lead Paint 160 9-May-19 10:07 AM Logan, UT Main Building 1st Floor North Stairwell Railing Metal Good White 49 0.15 Negative <LOD 0.11 Action Lead Paint 161 9-May-19 10:07 AM Logan, UT Main Building 1st Floor North Stairwell Railing Metal Good White 49 0.15 Negative <LOD 0.13 Action Lead Paint 162 9-May-19 10:07 AM Logan, UT Main Building 1st Floor North Stairwell Railing Metal Good White 49 0.15 Negative <LOD 0.01 Action Lead Paint 163 9-May-19 10:07 AM Logan, UT Main Building 1st Floor North Stairwell Railing Metal Good White 49 0.15 Negative <LOD 0.17 Action Lead Paint 164 9-May-19 10:09 AM Logan, UT Main Building Basement Corridor 01 Wall Concrete B Good White 50 0.15 Negative <LOD 0.01 Action Lead Paint 165 9-May-19 10:09 AM Logan, UT Main Building Basement Corridor 01 Wall Concrete B Good White 50 0.15 Negative <LOD 0.01 Action Lead Paint 166 9-May-19 10:09 AM Logan, UT Main Building Basement Corridor 01 Wall Concrete B Good White 50 0.15 Negative <LOD 0.07 Action Lead Paint 167 9-May-19 10:09 AM Logan, UT Main Building Basement Corridor 01 Wall Concrete B Good White 50 0.16 Negative <LOD 0.01 Action Lead Paint 168 9-May-19 10:09 AM Logan, UT Main Building Basement Corridor 01 Wall Concrete D Good White 51 0.14 Negative <LOD 0.01 Action Lead Paint 169 9-May-19 10:09 AM Logan, UT Main Building Basement Corridor 01 Wall Concrete D Good White 51 0.15 Negative <LOD 0.01 Action Lead Paint 170 9-May-19 10:09 AM Logan, UT Main Building Basement Corridor 01 Wall Concrete D Good White 51 0.15 Negative <LOD 0.01 Action Lead Paint 171 9-May-19 10:09 AM Logan, UT Main Building Basement Corridor 01 Wall Concrete D Good White 51 0.25 Negative <LOD 0.03 Action Lead Paint 172 9-May-19 10:11 AM Logan, UT Main Building Basement Rm 14 Wall Drywall A Good White 52 0.14 Negative <LOD 0.01 Action Lead Paint 173 9-May-19 10:11 AM Logan, UT Main Building Basement Rm 14 Wall Drywall A Good White 52 0.14 Negative <LOD 0.07 Action Lead Paint 174 9-May-19 10:12 AM Logan, UT Main Building Basement Rm 14 Wall Drywall A Good White 52 0.15 Negative <LOD 0.04 Action Lead Paint 175 9-May-19 10:12 AM Logan, UT Main Building Basement Rm 14 Wall Drywall B Good White 53 0.15 Negative <LOD 0.01 Action Lead Paint 176 9-May-19 10:12 AM Logan, UT Main Building Basement Rm 14 Wall Drywall B Good White 53 0.25 Negative <LOD 0.04 Action Lead Paint 177 9-May-19 10:12 AM Logan, UT Main Building Basement Rm 14 Wall Drywall B Good White 53 0.14 Negative <LOD 0.05 Action Lead Paint 178 9-May-19 10:12 AM Logan, UT Main Building Basement Rm 14 Wall Drywall C Good White 54 0.15 Negative <LOD 0.04 Action Lead Paint 179 9-May-19 10:12 AM Logan, UT Main Building Basement Rm 14 Wall Drywall C Good White 54 0.15 Negative <LOD 0.01 Action Lead Paint 180 9-May-19 10:12 AM Logan, UT Main Building Basement Rm 14 Wall Drywall C Good White 54 0.14 Negative <LOD 0.08 Action Lead Paint 181 9-May-19 10:12 AM Logan, UT Main Building Basement Rm 14 Wall Drywall D Good White 55 0.15 Negative <LOD 0.01 Action Lead Paint 182 9-May-19 10:12 AM Logan, UT Main Building Basement Rm 14 Wall Drywall D Good White 55 0.15 Negative <LOD 0.01 Action Lead Paint 183 9-May-19 10:12 AM Logan, UT Main Building Basement Rm 14 Wall Drywall D Good White 55 0.14 Negative <LOD 0.01 Action Lead Paint 184 9-May-19 10:15 AM Logan, UT Main Building Basement Rm 14 Door Wood Good White 56 0.15 Negative <LOD 0.05 Action Lead Paint 185 9-May-19 10:15 AM Logan, UT Main Building Basement Rm 14 Door Wood Good White 56 0.14 Negative <LOD 0.11 Action Lead Paint 186 9-May-19 10:15 AM Logan, UT Main Building Basement Rm 14 Door Wood Good White 56 0.15 Negative <LOD 0.01 Action Lead Paint 187 9-May-19 10:15 AM Logan, UT Main Building Basement Rm 14 Door Wood Good White 57 0.15 Negative <LOD 0.07 Action Lead Paint 188 9-May-19 10:15 AM Logan, UT Main Building Basement Rm 14 Door Wood Good White 57 0.15 Negative <LOD 0.01 Action Lead Paint 189 9-May-19 10:15 AM Logan, UT Main Building Basement Rm 14 Door Wood Good White 57 0.15 Negative <LOD 0.06 Action Lead Paint 190 9-May-19 10:17 AM Logan, UT Main Building Basement Corridor 01 Wall Concrete C Good White 58 0.24 Negative <LOD 0.03 Action Lead Paint 191 9-May-19 10:17 AM Logan, UT Main Building Basement Corridor 01 Wall Concrete C Good White 58 0.15 Negative <LOD 0.01 Action Lead Paint 192 9-May-19 10:17 AM Logan, UT Main Building Basement Corridor 01 Wall Concrete C Good White 58 0.15 Negative <LOD 0.03 Action Lead Paint 193 9-May-19 10:17 AM Logan, UT Main Building Basement Corridor 01 Wall Concrete A Good White 59 0.15 Negative <LOD 0.01 Action Lead Paint 194 9-May-19 10:17 AM Logan, UT Main Building Basement Corridor 01 Wall Concrete A Good White 59 0.15 Negative <LOD 0.01 Action Lead Paint 195 9-May-19 10:17 AM Logan, UT Main Building Basement Corridor 01 Wall Concrete A Good White 59 0.14 Negative <LOD 0.01 Action Lead Paint 196 9-May-19 10:19 AM Logan, UT Main Building Basement Corridor 01 Window Sill Metal Good White 60 0.15 Negative <LOD 0.07 Action Lead Paint 197 9-May-19 10:19 AM Logan, UT Main Building Basement Corridor 01 Window Sill Metal Good White 60 0.15 Negative 0.07 0.02 Action Lead Paint 198 9-May-19 10:19 AM Logan, UT Main Building Basement Corridor 01 Window Sill Metal Good White 60 0.14 Negative <LOD 0.01 Action Lead Paint 199 9-May-19 10:19 AM Logan, UT Main Building Basement Corridor 01 Window Sill Metal Good White 60 0.15 Negative <LOD 0.07 Action Lead Paint 200 9-May-19 10:21 AM Logan, UT Main Building Basement Rm 15 Wall Drywall A Good White 61 0.12 Negative <LOD 0.08 Action Lead Paint 201 9-May-19 10:21 AM Logan, UT Main Building Basement Rm 15 Wall Drywall A Good White 61 0.15 Negative <LOD 0.07 Action Lead Paint

Reading No Date Time Site Building Floor Room Component Substrate Side Condition Color Picture Number Duration Results Pb Pb Error Type

202 9-May-19 10:21 AM Logan, UT Main Building Basement Rm 15 Wall Drywall A Good White 61 0.15…