AAAP Post Award Schedule.pdf
PDF 9 KB Posted
- Attached to
- Lease of Office Space within Region 10. Request for Lease Proposals (RLP) #25-REG10-Office Space
- Solicitation number
- 25-REG10_2WA0663
About this file
This document is a post-award schedule for the Automated Advanced Acquisition Program (AAAP) which details the generic timeline for managing the design and construction process following a lease award. The schedule commences within 5 working days of lease award and provides timelines for various activities based on the size of the space requirement, ranging from 0 to 10,000 ABOA square feet.
The related federal contract opportunity is a Request for Lease Proposals (RLP) for the lease of 4,250 to 5,000 ABOA square feet of office space in Port Angeles, WA. The lease term is 17 years with 5 firm. The Government will award the lease to the lowest price, technically acceptable offer without negotiations. The Tenant Improvement Allowance is $63.67 per ABOA SF and the Building Specific Amortized Capital is $12.00 per ABOA SF for locations other than the existing leased space. The RLP outlines various agency-unique requirements such as proximity to public transportation, number of elevators, and seismic standards compliance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Post Award Schedule - 2WA0663 Port Angeles WA.pdf | ||
| H DA.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AAAP POST-AWARD SCHEDULE, PAGE 1 OF 2 RLP VERSION - REV (10/22)
AAAP Post-Award Schedule
This exhibit details the generic post-award schedule for AAAP projects based on the size of the requirement and should be referenced when reviewing section 4.01 of the lease. The Government may modify this schedule for specific projects using an exhibit to the project specific advertisement posted on the System for Award Management website (SAM.gov).
The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.
Activity
Working Days Based on ANSI/BOMA Occupant Area Square Feet
0K to <20K
ABOA SF
20K to <50K
ABOA SF
50K to <70K +
ABOA SF
Lessor-Provided Design Intent Drawings 30 40 45
Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings
45 50 50
Lessor Preparation and Submission of Construction Documents
20 20 35
Government Review of Construction Drawings 20 25 25
Lessor Preparation and Submission of the TI and BSAC Price Proposal
20 30 40
Government Reviews and Approves Pricing 30 30 40
Government Issues Notice to Proceed with Construction
10 10 10
Lessor Completes Construction of TIs and Completion of Other Required Construction Work
60 130 260
AAAP POST-AWARD SCHEDULE, PAGE 2 OF 2 RLP VERSION - REV (10/22)
Government Inspects and Accepts Finished Space
10 10 10
Total Work Days from Lease Award to Government Acceptance
245 345 515