Post Award Schedule - 2WA0663 Port Angeles WA.pdf

PDF 15 KB Posted

Attached to
Lease of Office Space within Region 10. Request for Lease Proposals (RLP) #25-REG10-Office Space
Solicitation number
25-REG10_2WA0663
Issued by

About this file

This document is a Post-Award Schedule detailing the timeline for the design and construction process following the award of a lease for office space in Port Angeles, WA. The key details are:

The post-award schedule commences within 5 working days of lease award and includes the following major milestones: Lessor-Provided Design Intent Drawings (120 working days), Government Review of Agency Provided Design Intent Drawings (10 working days), Lessor Preparation and Submission of 95% Construction Documents (15 working days), Government Review of 95% Construction Drawings (10 working days), Lessor Preparation and Submission of 100% Construction Documents (15 working days), Government Review of Construction 100% Drawings (15 working days), Lessor Preparation and Submission of the Tenant Improvement (TI) and Building Specific Amortized Capital (BSAC) Price Proposal (20 working days), Government Reviews and Approves Pricing (30 working days), Lessor Completes Construction of TIs and Completion of Other Required Construction Work (120 working days), and Government Inspects and Accepts Finished Space (5 working days). The total time from lease award to government acceptance is 400 working days.

View the file

Other files

File Type Posted
AAAP Post Award Schedule.pdf PDF
H DA.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section

1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity Working Days

Lessor-Provided Design Intent Drawings Agency-Provided Design Intent Drawings

Government (GSA) Review of Agency Provided Design Intent Drawings 10

Lessor Preparation and Submission of 95% Construction Documents 15

Government Review of 95% Construction Drawings 10

Lessor Preparation and Submission of 100% Construction Documents 15

Government Review of Construction 100% Drawings 15

Lessor Preparation and Submission of the TI and BSAC Price Proposal

Government Reviews and Approves Pricing 30

Government Issues Notice to Proceed with Construction 1

AAAP POST-AWARD SCHEDULE, PAGE 2 OF 2 PSA VERSION - REV (10/22)

Lessor Completes Construction of TIs and Completion of Other Required Construction Work

Government Inspects and Accepts Finished Space 5

Total Workdays from Lease Award to Government Acceptance 400