This document is an AAAP (Adjust, Assess, Analyze, Plan) Project Specific Advertisement attachment detailing the post-award schedule for a real estate lease project. The schedule replaces the attachment referenced in section 1.05 of the RLP (R100) and applies to section 4.01 of the Lease (L100). The post-award schedule commences within 5 working days of lease award and governs the design and construction process through Government acceptance of the space.

The schedule comprises 12 sequential activities totaling 196 working days from lease award to Government acceptance. Key activities include: Lessor-Provided Design Intent Drawings (21 days); Government review and approval of design drawings (15 days); Lessor preparation and submission of construction documents (10 days); Government review of construction drawings (10 days); Lessor preparation and submission of TI and BSAC pricing proposal (10 days); Government review, negotiation, and approval of pricing (15 days); Government issuance of Notice to Proceed (5 days); Lessor obtaining construction permits (30 days); Lessor completion of tenant improvements and other required construction (60 days); Government inspection of finished space (10 days); and Lessor completion of punchlist with Government acceptance (10 days). The timeline establishes clear responsibility allocation between the Lessor and Government entities (GSA and Client) throughout the design, permitting, construction, and acceptance phases.

View the file

Other files

File Type Posted
SAM Ad 6NY0829.pdf PDF
Space Layout 6NY0829.pdf PDF
SAM Ad 6NY0829.pdf PDF
Delineated Area Exhibit 6NY0829.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section

1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity Working Days

Lessor-Provided Design Intent Drawings 21

Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings 15

Lessor Preparation and Submission of Construction Documents 10

Government Review of Construction Drawings 10

Lessor Preparation and Submission of the TI and BSAC Price Proposal 10

Government Reviews, Negotiates, and Approves Pricing 15

Government Issues Notice to Proceed with Construction 5

Lessor Obtains Construction Permit 30

Lessor Completes Construction of TIs and Completion of Other Required Construction Work 60

Government Inspects Finished Space 10

Lessor Completes Punchlist and Government Accepts Finished Space 10

Total Work Days from Lease Award to Government Acceptance 196