This is a Construction Schedule template (Solicitation Attachment #2) for a federal lease contract (L201C) that establishes working day timeframes for completing design and construction phases of leased space. The schedule applies to both the Lessor and Government (GSA and Client) and commences within five days after lease award, managing the entire design and construction process through Government acceptance of the space.
The schedule is structured by lease size in ANSI/BOMA office area square feet across six categories: 0K to <10K, 10K to <20K, 20K to <35K, 35K to <50K, 50K to <70K, and 70K+. Each size category has nine sequential phases with defined working day allowances: Lessor-Provided Design Intent Drawings (25-45 days); Government Review and Approval of Design Intent Drawings (30-45 days); Lessor Preparation and Submission of Construction Documents (20-35 days); Government Review of Construction Drawings (15-20 days); Lessor Preparation and Submission of Tenant Improvement (TI) and Building Standard Alterations and Construction (BSAC) Price Proposal (20-40 days); Government Review and Approval of Pricing (30-40 days); Government Notice to Proceed with Construction (10 days); Lessor Completion of TI and Other Required Construction Work (60-100 days); and Government Inspection and Acceptance of Finished Space (10 days). Total project duration ranges from 220 days for smaller leases to 345 days for leases 70,000 square feet and larger.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Expanded DA Map FPD Ocala FL.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LESSOR: ________ GOVERNMENT: ________ CONSTRUCTION SCHEDULE
REV (10/18)
Solicitation Attachment #2 - Construction Schedule
The following chart shall be used by the Lessor and the Government to determine the number of working days allowed to complete each work item under the Lease Contract (L201C) paragraph entitled "Schedule of Completion of Space" and Attachment #3 - Scope of Work for DID’s and Construction Schedule Tasks. The below Construction Schedule commences within five (5) days after lease award. The timeframes below apply to the management of the design and construction process, concluding at the date of acceptance for the space.
PHASE \ SIZE OF LEASE
(ANSI/BOMA Office Area Square Feet)
0K to <10K 10K to <20K 20K to <35K 35K to <50K 50K to <70K 70K +
Lessor-Provided Design Intent Drawings
25 DAYS 25 DAYS 30 DAYS 40 DAYS 40 DAYS 45 DAYS
Government (GSA and Client) Reviews and Approval of Lessor- Provided Design Intent Drawings
30 DAYS 30 DAYS 30 DAYS 30 DAYS 45 DAYS 45 DAYS
Lessor Preparation and Submission of Construction Documents
20 DAYS 20 DAYS 20 DAYS 20 DAYS 35 DAYS 35 DAYS
Government Review of Construction Drawings
15 DAYS 15 DAYS 15 DAYS 15 DAYS 20 DAYS 20 DAYS
Lessor Preparation and Submission of the TI and BSAC Price Proposal
20 DAYS 20 DAYS 30 DAYS 30 DAYS 40 DAYS 40 DAYS
Government Reviews and Approves Pricing 30 DAYS 30 DAYS 30 DAYS 30 DAYS 40 DAYS 40 DAYS
Government Issues Notice to Proceed with Construction
10 DAY 10 DAYS 10 DAYS 10 DAYS 10 DAYS 10 DAYS
Lessor Completes Construction of TIs and Completion of Other Required Construction Work
60 DAYS 60 DAYS 70 DAYS 90 DAYS 100 DAYS 100 DAYS
Government Inspects and Accepts Finished Space
10 DAYS 10 DAYS 10 DAYS 10 DAYS 10 DAYS 10 DAYS
TOTAL WORKDAYS -
(FROM LEASE AWARD
TO GOVERNMENT
ACCEPTANCE)
220 DAYS 220 DAYS 245 DAYS 275 DAYS 340 DAYS 345 DAYS