400 One Norwegian Plaza

Pottsville, PA 17901 www.benesch.com

P 570-622-4055

Y:\Pennsylvania\03XX-60S\0325-609047.01__Shen_2025RoadPrgm\Office_Docs\Specifications\Addenda\Addendum 1\Addendum No1_2025-08-07.docx

ADDENDUM NO. 1

To: All Prospective Bidders

Date: August 7, 2025

From: Alfred Bronakowski, P.E., Benesch

Doug Weist, E.I.T., Benesch

Subject: Shenandoah Borough 2025 Road Program

Addendum No. 1 – Project No. 0325-609043.23 & 0325-609047.01

Bid Receipt: Wednesday, August 13, 2025, until 9:00 AM

This Addendum forms a part of the Contract Documents and modifies the Bidding Documents dated July, 2025.

1. Minutes from the Pre-Bid Meeting are attached to this Addendum.

2. Section 015100 – Maintenance and Protection of Traffic – Section 3.1.D revised as follows:

Maintenance of Traffic - When indicated on the drawings or specified, the Contractor shall maintain traffic over sections of the old road and/or new roadway and portions adjacent thereto, and shall keep a sufficient width of these sections open and passable, as specified, with minimum traffic interference, consistent with the prosecution of the work. A minimum of one lane of traffic must be maintained on Furnace Street at all times.

This Addendum is issued to all registered plan holders pursuant to the Instructions to Bidders and Conditions of the Contract. This Addendum serves to clarify, revise, and supersede information in the Project Manual, Drawings, and previously issued Addenda. Portions of the Addendum affecting the Contract Documents will be incorporated into the Contract by enumeration of the Addendum in the Owner/Contractor Agreement.

The Bidder shall acknowledge receipt of this Addendum in the appropriate space on PennBID.

End of Addendum No. 1

400 One Norwegian Plaza Pottsville, PA 17901 www.benesch.com

P 570-622-4055

The pre-bid meeting was held for the above-referenced projects. The following items were noted and/or discussed.

The purpose of this meeting is to provide a brief overview of the project and specifications, review County preferences of the bid preparation, highlight project requirements, and answer contractor questions.

1. The project includes 2 separate contracts and 2 separate base bids.

a. Contract A (CDBG) – North Jardin Street (Washington to Coal Streets)

i. Contract A also has 1 alternate – North Market Street (Lloyd to Coal Streets)

b. Contract B – Base Bid – West Oak Street (Gilbert to Chestnut Streets)

i. Contract B also has 9 alternates.

2. Contracts will be awarded based on the lowest qualified bid of the base bid and alternates, if selected, based on available funds. Alternate Bids will not necessarily be selected in numerical order.

3. Work includes base replacement, overlay, and concrete curb ramp construction. Roll curb will also be included in work for the Furnace Street alternate.

Project: Shenandoah Borough 2025 Road Program Borough of Shenandoah, Schuylkill County Pre-Bid Meeting

Project No.: 0325-609043.23 & 0325-609047.01

Date/Time: 10 AM, July 30, 2025

Place: Shenandoah Borough Hall 15 W. Washington St., Shenandoah, PA

Attendees: Cheryl Fuss, Schuylkill County Charles Mengle, Schuylkill County Joe Gawrylik, Shenandoah Borough Council Mike Uholik, Shenandoah Borough Council Joe Boris, Shenandoah Borough Council Mike Cadau, Shenandoah Borough Manager Mike Pennycoff, New Enterprise Stone & Lime Co.

Rodney Krause, Lehigh Asphalt Doug Weist, Benesch

Pre-Bid Meeting Minutes

Page | 2

a. Areas of base replacement on each street are field marked for contractor understanding for the bidding process. The quantities in the bidding documents match the marked quantity of base replacement on each street. Locations that include base replacement for the entire length and width of the roadway are specified under the Pavement Base Repair item in Section 012200 – UNIT PRICES in the Project Manual.

4. Millings will be retained by the Borough, with a delivery site to be determined by the Borough.

5. Curb ramp design is the responsibility of the contractor. Ramps must meet the standards of RC- 67M of PennDOT Pub. 72M.

6. Current Schedule

a. Contractor questions are due on PennBID/Bonfire on Wednesday, August 6th.

b. Bids are due Wednesday, August 13th by 9:00 AM online, on PennBID.

c. Bids will be opened on Wednesday, August 13th. The project will be tentatively awarded on Wednesday, August 27th, at the Commissioners’ meeting.

d. Work must be completed by November 1st, 2025.

7. Davis Bacon Wage rates apply to both contracts – Please check the bid documents for the rate schedule. Any changes will come from Benesch.

8. Document forms

a. All forms must be signed - MBE/WBE – if you are using sub-contractor, you must make a good faith effort to reach out to minority and women business enterprises for the opportunity to compete for work. If you are not using sub-contractors, you must state that on the form and sign at the bottom.

b. A list of all subcontractors must be submitted with the bid, regardless of whether they qualify as a MBE/WBE.

c. Forms not completed or signed are reasons for a bid to be deemed incomplete and rejected.

9. All bids will be submitted electronically via PennBID/Bonfire.

a. Bid bonds will be required with the submission of each bid.

10. A question was asked regarding the number of risers for storm drains or manholes that will be needed. Any manholes or inlets that may need to be adjusted are referenced in the specific street’s “Exhibit A” under the item “Grade Adjustments of Existing Manholes.” Please see Section 012200 – UNIT PRICES in the Project Manual for description of work included in the item.

11. A question was asked regarding whether the asphalt roll curb included in the Furnace Street Alternate of Contract B can be hand-formed or requires specific molds or forms. The asphalt roll curb included in this alternate can be hand formed or formed with molds.

12. A question was asked regarding how pavement tie-ins will be paid for as part of the transition with existing pavement. Paving notches at all tie ins will be incidental to bituminous overlay.

Page | 3

13. A question was asked regarding the number of curb ramp designs within the bid package and how that correlates to the detectable warning surface item. Contract A Alternate 1 - North Market Street includes one curb ramp at the southwest corner of the intersection of Coal Street and Market Street. It is anticipated that the ramp will have two (2) 2’x4’ detectable warning surfaces for a total of sixteen (16) square feet. Contract B Alternate 5 – West Coal Street (Catherine St. to Vine St.) includes one curb ramp at the southwest corner of Coal Street and Catherine Street. It is anticipated that the ramp will have two (2) 2’x4’ detectable warning surfaces for a total of sixteen (16) square feet. Contract B Alternate 6 – West Coal Street (Chestnut St. to Gilbert St.) includes a curb ramp at the northeast corner of the intersection of Coal Street and Gilbert Street. It is anticipated that the ramp will have one (1) 2’x4’ detectable warning surfaces for a total of eight (8) square feet.

14. A question was asked regarding whether each contract will need its own bid bond or if one bid bond can be submitted for the overall amount of both projects. A separate bid bond shall be submitted for each contract.

15. A question was asked regarding the number of times forms need to be submitted if the contractor is bidding on both contracts. Forms specific to each contract must be submitted separately for each contract (Bid Form, Bid Bond, etc.). Other forms not specific to one contract may be submitted once.

16. A question was asked regarding if each contract can be awarded to a different contractor.

Contract A and Contract B can be awarded to different contractors based on if the lowest bidder for the base bid and selected alternatives in each contract are different.

All Attendees are requested to review the above minutes for corrections and/or comments. If no comments are received within two (2) business days, these minutes will become the basis for all official action.

Respectfully submitted, Douglas J. Weist, EIT Designer cc: All Attendees

Borough of Shenandoah – 2025 Road Program – Project Nos. 0325-609043.23 & 0325-609047.01

MAINTENANCE AND PROTECTION OF TRAFFIC Section 015100

MAINTENANCE AND PROTECTION OF TRAFFIC Section 015100 - Page 1

SECTION 015100 - MAINTENANCE AND PROTECTION OF TRAFFIC

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SCOPE OF WORK

A. This work shall consist of the maintenance of traffic and the protection of the traveling public, including pedestrians, as they approach the construction area and within the limits of the construction in accordance with these specifications. It shall be the responsibility of the

Contractor to provide all labor, materials, and equipment necessary for this item.

PART 2 - PRODUCTS

2.1 SIGNAGE, LIGHTING, ETC.

A. All traffic signage and lighting shall be fabricated of material as specified in Pennsylvania

Department of Transportation Publication 408 Specifications, and Publication 213, in its latest revision.

PART 3 - EXECUTION

3.1 CONSTRUCTION REQUIREMENTS

A. During the pre-construction conference, the Contractor shall submit his method for the maintenance and protection of traffic during construction, which shall contain a list of schematic diagrams indicating the quantity, type and employment of all flashing warning lights, signs, barricades, and other protective devices which will be used, including the approximate date of installation. If required, any part of the methods shall be revised as directed by the ENGINEER.

The Contractors method shall be consistent with PennDOT Publication 213. Local streets may be closed to vehicular traffic if approved by Owner and Engineer.

B. Signs, flashing warning light, barricades, markers, and other protective devices shall be maintained by the Contractor in first-class operating condition and shall be moved and relocated as required to conform with construction operations and to keep traffic flowing with minimum restrictions.

C. Construction operations shall be so scheduled that interference with the normal movement of traffic be kept to a minimum. Should the length of operation become excessive or if interruptions of traffic become too frequent, all operations in the areas concerned shall cease until necessary remedial action has been taken to the satisfaction of the ENGINEER.

Borough of Shenandoah – 2025 Road Program – Project Nos. 0325-609043.23 & 0325-609047.01

MAINTENANCE AND PROTECTION OF TRAFFIC Section 015100

MAINTENANCE AND PROTECTION OF TRAFFIC Section 015100 - Page 2

D. Maintenance of Traffic - When indicated on the drawings or specified, the Contractor shall maintain traffic over sections of the old road and/or new roadway and portions adjacent thereto, and shall keep a sufficient width of these sections open and passable, as specified, with minimum traffic interference, consistent with the prosecution of the work. A minimum of one lane of traffic must be maintained on Furnace Street at all times.

E. Within the limits of the project, the Contractor shall be responsible for maintenance of all existing surface roads, including shoulders. The Contractor shall at all times maintain all state highways according to PENNDOT Standards while maintaining Borough roads in acceptable condition.

F. Contractor shall be responsible for daily inspections of all traffic control devices to insure they are in proper working order and in compliance with the approved traffic control plan.

G. Maintenance and protection of traffic refers to pedestrian as well as vehicular traffic in and around the project site. Walkways must remain accessible throughout construction, or provisions as indicated in Publication 213 must be implemented to provide access to an alternate route.

H. Maintenance and protection of traffic shall be performed in accordance with the provisions of the

Pennsylvania Department of Transportation Publication 408 Specifications, Section 901, and

Publication 213, in its latest revision.

END OF SECTION 015100